FUTURE PROJECTS<br />
PROJECTS UNDER IMPLEMENTATION<br />
Details<br />
Location of Project<br />
Mine - II<br />
Expn.<br />
Neyveli,<br />
Tamil Nadu<br />
TPS - II<br />
Expn.<br />
Neyveli,<br />
Tamil Nadu<br />
Barsingsar<br />
Mine<br />
Barsingsar<br />
TPS<br />
Rajasthan Rajasthan<br />
Sanctioned Capacity 4.5 MTPA 500 MW 2.1 MTPA 250 MW<br />
Capital cost - in<br />
Million Rs<br />
( in Million USD)<br />
Commissioning<br />
schedule<br />
21610<br />
(527)<br />
20310<br />
(495)<br />
2540<br />
(62)<br />
43<br />
11140<br />
(272)<br />
June 2009 June 2009 June 2009 June 2009