PA Quarterly Meeting Meeting Minutes—11 November 1, 2012<br />

Joanna Morsicato committed that HART will produce quarterly meeting minutes in a more<br />

timely fashion. She also noted that SHPD will receive a formal response to their October 15,<br />

2012 letter to FTA.<br />

XIV.E.2 (Quarterly Meetings)<br />

The next meeting, a semi-annual meeting, will take place on January 25, 2012. HART will<br />

extend the quarterly meeting schedule to continue as needed, beyond the 24-month period<br />

dictated by the PA.<br />

XIV.E.3 (Semi-Annual Report)<br />

The July 2012 Semi-Annual Report was distributed on October 19, 2012 and is available on<br />

the project website.<br />

Blythe Semmer commented:<br />

In order to be most productive, it would be helpful to review the semi-annual report and<br />

meeting handouts/materials at least a week in advance of these meetings. We want to<br />

come prepared to these meetings with questions.<br />

Other Discussion Items<br />

Hinaleimoana Wong-Kalu<br />

Would hate for the Hawaiian community to be the evil face of the project.<br />

Integrity is important.<br />

As the chair of the OIBC, I’ve had people come to me saying “stop the rail.” I’m<br />

not trying to stop anything; I’m only availing my time to be an advocate for my<br />

charge and I don’t want to be labeled as a Hawaiian that’s adversarial to<br />

development. It’s about the integrity we bring to the table.<br />

HART’s public information and media time needs to be more hands-on.<br />

Mahealani Cypher<br />

We are here to ensure that you are educated and informed to be able to make<br />

good decisions.<br />

Kalani Asam<br />

We should be in charge.<br />

*** Meeting adjourned at 1:00 pm ***<br />

Action Items<br />

HART to fill Architectural Historian position<br />

Kāko‘o to start developing Best Practice Manual (BPM) and Lessons-Learned Case<br />

Study<br />

HART to schedule a consulting party project-wide station design-focused meeting that<br />

ahead of the Station Group Design Workshops<br />

HART to provide Chinatown information from Mike Lee to Kepā Maly for TCP Study for<br />

Section 4<br />

HART will respond to Mike Lee with clarification on piers that were not mentioned in<br />

HART’s response to his FOIA request.<br />

Ellyn Goldkind asked who on the URS design team has cultural and local experience<br />

and for URS’ scope of work<br />

Request to include schedule with milestones and deliverable dates that identifies<br />

whether they’re behind schedule, on schedule or ahead of schedule<br />

Navy to provide a list of requested design deliverables to Ken Caswell<br />

HART to provide consulting parties with PE-level designs for WOSG and FHSG once<br />

available, and to clarify schedule