20.01.2015 Views

Commissioning the Desalination Plant - Aquasure

Commissioning the Desalination Plant - Aquasure

Commissioning the Desalination Plant - Aquasure

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

VICTORIAN DESALINATION PROJECT<br />

FACT SHEET<br />

<strong>Commissioning</strong> <strong>the</strong> desalination plant<br />

TDV-FS-0029-00<br />

With construction of Victoria’s new desalination plant nearing completion, commissioning<br />

is now underway – a complex and essential process that all desalination plants must<br />

go through.<br />

What is commissioning<br />

The commissioning process is designed to confirm that <strong>the</strong><br />

desalination plant can reliably produce high quality drinking water<br />

in commercial quantities, as required under AquaSure’s contract.<br />

At Victoria’s new desalination plant, more than 200,000 tests will<br />

be carried out on 28,500 individual pieces of equipment, before<br />

<strong>the</strong>y can all come toge<strong>the</strong>r as one.<br />

How does commissioning work<br />

The commissioning process involves a number of stages.<br />

1. Precommissioning<br />

Detailed quality assurance checks are carried out to confirm that equipment has been<br />

installed correctly and conforms with specifications. Fu<strong>the</strong>r tests <strong>the</strong>n confirm that<br />

equipment functions correctly as part of <strong>the</strong> plant’s sophisticated operating system.<br />

2. Wet<br />

commissioning<br />

Water is introduced to <strong>the</strong> system, and fur<strong>the</strong>r tests carried out to confirm that<br />

equipment is capable of moving water at <strong>the</strong> required flow and pressure, and that<br />

control systems continue to operate correctly.<br />

3. Process<br />

commissioning<br />

Chemicals are introduced and <strong>the</strong> first samples of test water produced and tested<br />

to confirm that water chemistry is correct and consistent.<br />

4. Performance<br />

testing<br />

A series of performance tests to prove that <strong>the</strong> plant is capable of reliably producing<br />

high quality drinking water in commercial quantities. These tests are a requirement<br />

under AquaSure’s contract and include 7- and 30-day continuous operating tests.


How long does commissioning take<br />

<strong>Commissioning</strong> is a detailed process, which begins<br />

as key elements of construction are completed.<br />

In total, <strong>the</strong> process will take around nine months to<br />

complete.<br />

Issues can and do come up, and identifying and<br />

addressing <strong>the</strong>m well before <strong>the</strong> desalination plant<br />

begins operating is exactly what <strong>the</strong> commissioning<br />

process is for, and can prove as simple as replacing<br />

a part under warranty.<br />

Who will oversee <strong>the</strong> commissioning process<br />

The commissioning process will be overseen by <strong>the</strong><br />

Independent Reviewer and Environmental Auditor for<br />

<strong>the</strong> project.<br />

The Environment Protection Authority (EPA) will<br />

also play an active role, confirming that <strong>the</strong> plant is<br />

meeting all necessary environmental guidelines.<br />

Are <strong>the</strong>re any approvals required prior to starting<br />

commissioning<br />

Yes. The EPA has issued an approval for <strong>the</strong><br />

commissioning activities, under Section 30A of<br />

<strong>the</strong> Environment Protection Act 1970.<br />

The approval outlines <strong>the</strong> conditions under<br />

which commissioning activities must be carried<br />

out. It can be viewed on <strong>the</strong> EPA’s website at<br />

www.epa.vic.gov.au.<br />

How many people are involved in process<br />

commissioning<br />

Unlike <strong>the</strong> construction phase of <strong>the</strong> project, <strong>the</strong><br />

process commissioning team is relatively small,<br />

comprising approximately 40 people.<br />

When will desalinated water be available from<br />

<strong>the</strong> plant<br />

Desalinated water will not enter <strong>the</strong> water network<br />

until <strong>the</strong> final water product is tested to confirm it<br />

meets Australian Drinking Water Guidelines, Victorian<br />

health requirements and <strong>the</strong> water quality standards<br />

specified in <strong>the</strong> contract.<br />

Water will also be tested by an independent water<br />

testing laboratory.<br />

Water will gradually enter <strong>the</strong> network during<br />

commissioning.<br />

DID YOU KNOW<br />

Degrémont has been operating in<br />

Australia for 40 years. Around 20% of<br />

Australia’s population is provided with<br />

drinking water from Degrémont<br />

facilities on a daily basis.<br />

Degrémont has built and operated<br />

more than 260 desalination plants<br />

around <strong>the</strong> world.<br />

Specialist engineers from Degrémont<br />

will lead <strong>the</strong> commissioning process<br />

of Victoria’s new desalination plant.


A LOOK INSIDE THE COMMISSIONING PROCESS<br />

Outlined below are just a few of <strong>the</strong> 200,000 performance and reliability tests that <strong>the</strong> desalination<br />

plant and its supporting infrastructure must pass before it begins commercial operation.<br />

<strong>Commissioning</strong> <strong>the</strong> reverse osmosis membranes<br />

The heart of <strong>the</strong> desalination plant is <strong>the</strong> reverse<br />

osmosis building, where seawater is pushed through<br />

55,000 membranes to separate salt from seawater.<br />

To prepare <strong>the</strong> membranes for operation, <strong>the</strong><br />

many components and pumps that drive <strong>the</strong><br />

membranes will first be tested and checked to<br />

confirm <strong>the</strong>y have been installed correctly.<br />

These tests are carried out both with and<br />

without water, to check that equipment continues<br />

to function as required.<br />

When <strong>the</strong> commissioning team is confident that<br />

all systems and equipment are operating correctly,<br />

seawater is pushed through <strong>the</strong> reverse osmosis<br />

membranes.<br />

Seawater concentrate is checked and analysed,<br />

<strong>the</strong>n returned to <strong>the</strong> ocean, while pure water is<br />

potabilised, tested and analysed against <strong>the</strong><br />

required drinking water standards, <strong>the</strong>n also<br />

returned to <strong>the</strong> ocean.<br />

Put simply, <strong>the</strong> commissioning team is producing<br />

potable water simply to confirm that <strong>the</strong> membranes<br />

and <strong>the</strong>ir operating systems are operating correctly.<br />

<strong>Commissioning</strong> <strong>the</strong> transfer pipeline<br />

Hydrotesting of <strong>the</strong> transfer pipeline is one<br />

of many activities that form part of <strong>the</strong><br />

commissioning process.<br />

To conduct a hydrotest, <strong>the</strong> transfer pipeline<br />

is filled with water and pressurised well above<br />

standard operating limits.<br />

A certified, independent technician <strong>the</strong>n carries<br />

out a series of detailed inspections and quality<br />

tests to confirm that <strong>the</strong> transfer pipeline and its<br />

supporting structures, like air valves, have been<br />

well constructed and are operating correctly.<br />

<strong>Commissioning</strong> <strong>the</strong> power cable<br />

When underground power cable installations<br />

and terminations are complete, all components<br />

such as transformers, circuit breakers and<br />

monitoring equipment are checked.<br />

The process of connecting <strong>the</strong> power to <strong>the</strong> grid<br />

and making it ‘live’ is called energisation.<br />

Energisation is initially carried out at low voltage,<br />

with crews checking that all components are<br />

performing correctly.<br />

When this work is complete, <strong>the</strong> cable is fully<br />

energised to 220kV and power from <strong>the</strong> grid is<br />

<strong>the</strong>n available at <strong>the</strong> plant site.


When will <strong>the</strong> desalination plant start<br />

producing waste<br />

The desalination plant will begin producing waste<br />

during <strong>the</strong> advanced stages of commissioning.<br />

What kinds of waste will <strong>the</strong> desalination<br />

plant produce<br />

The desalination plant will generate two main<br />

waste streams – liquid waste (known as ‘seawater<br />

concentrate’ or ‘brine’) and solid waste (often<br />

referred to as ‘sludge’).<br />

Where will <strong>the</strong> waste be disposed<br />

Brine will be returned to <strong>the</strong> ocean, while solid<br />

waste will be trucked away to landfill.<br />

Only when <strong>the</strong> plant begins producing solid waste,<br />

can it be classified by <strong>the</strong> EPA. This classification<br />

will dictate where <strong>the</strong> waste can be disposed.<br />

Do you need approval to discharge brine to<br />

<strong>the</strong> ocean<br />

Yes. Any form of discharge into public waters requires<br />

approval from <strong>the</strong> EPA, and Victoria’s desalination plant<br />

is no exception. The EPA has issued an approval for<br />

commissioning activities, which specifies discharge<br />

requirements.<br />

Would <strong>the</strong> solid waste ever be disposed to <strong>the</strong> ocean<br />

No. This would be a significant violation of EPA<br />

guidelines and <strong>the</strong> environmental performance<br />

requirements for <strong>the</strong> project, and would put AquaSure’s<br />

license to operate at serious risk.<br />

It is also not physically possible. The solid waste looks<br />

and feels like soft clay, and <strong>the</strong> plant is simply not<br />

equipped with <strong>the</strong> infrastructure required to discharge<br />

such material.<br />

Fur<strong>the</strong>r reading<br />

• Water Treatment Processes Fact Sheet<br />

• Pipeline Hydrotesting Fact Sheet<br />

Printed on Tudor RP, an Australian made paper that contains 100% recycled fibre. No chlorine bleaching occurs in <strong>the</strong> recycling process<br />

and Australian Paper is ISO 14001 certified. Sales of Tudor RP support Landcare Australia.<br />

CONTACT US<br />

Visit <strong>the</strong> Victorian <strong>Desalination</strong> Project Community Information Centre<br />

Shop 2, 33– 35 Murray St, Wonthaggi<br />

Opening hours Wednesday – Friday 9.30am – 4.30pm.<br />

MARCH 2012<br />

Freecall<br />

1800 811 214<br />

Email<br />

contactus@aquasure.com.au<br />

Web<br />

www.aquasure.com.au<br />

www.water.vic.gov.au/desalination<br />

Post<br />

AquaSure C/– PO Box 7387<br />

St Kilda Road, Melbourne<br />

VIC 8004

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!