Minutes <strong>of</strong> meeting <strong>of</strong> <strong>Jharkhand</strong> Micro & Small Enterprises Facilitation Council held on<br />

under the Chairmanship <strong>of</strong> Director <strong>of</strong> Industries, Govt. <strong>of</strong> <strong>Jharkhand</strong><br />

Presence <strong>of</strong> Members<br />

1. Smt. Vandana Dadel<br />

2. Sri Dilip Kumar Sharma<br />

3. Sri Mithilesh Prasad<br />

4. Sri H.P.Biyani<br />

5. Jhuma Deb<br />

6. Sri Rajesh Sharan<br />

7. Sri S.N.Kejariwal<br />

Director <strong>of</strong> Industries, Govt. <strong>of</strong> <strong>Jharkhand</strong><br />

Dy. Director <strong>of</strong> Industries<br />

Addl. Legal Remembrancer<br />

Representative <strong>of</strong> J.S.I.A, Kokar, Ranchi<br />

Manager, SIDBI<br />

Sr.Manager, Allahabad Bank<br />

<strong>Department</strong>' s Consultant<br />

I<br />

Case no. JHSEFC-04/08<br />

M/s Giluram Gauri Shankar, Sahid Ashram Road, Deoghar<br />

V/s<br />

Chief Engineer (Electri), JSEB, Ranchi.<br />

Facts <strong>of</strong>the case:<br />

As per Appellant:<br />

l. Principal outstanding against PO no.l24 M (T) dt.02.l1.202 Rs.l, 73,741.85(Rs.l, 03,936 towards penalty & Rs,<br />

.69805 towards rate difference) plus interest.<br />

2. PO no.40,10,84M(T),88M(T),92M(T),67(S&P)-no principal outstanding, only interest claim <strong>of</strong> Rs.57,30,165/- and<br />

PO no.39 Rs.5,74,809 (calculated up to 31.01.10) Plus further interest.<br />

JSEB Stand<br />

3. As per JSEB- deduction <strong>of</strong> Penalty for Rs.103937 againstlate delivery No comment for short payment <strong>of</strong><br />

excise duty.<br />

4. Regarding interest on delayed payment, JSEB has claimed that in most <strong>of</strong> the cases payment has made<br />

within 14 days from the date <strong>of</strong> receipt <strong>of</strong> the bills.<br />

DECISION on 10.12.2012: Both the parties have appeared and were .heard. Both the parties were<br />

advised to jointly reconcile the dues indicating date <strong>of</strong> supply <strong>of</strong> materiaVdate <strong>of</strong> submission <strong>of</strong> bill/Cheque<br />

no and date <strong>of</strong> payment <strong>of</strong> the bill along with their final stand on the issue. The case has been re-fixed on l ltl'<br />

January 2013 for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBI)<br />

<strong>sd</strong>-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dv.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC


<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC<br />

@<br />

2<br />

Case no. JHSEFC-O8/I1<br />

IWs Eastern Engineering Co., Tipudana<br />

V/s<br />

lWs Kedla Washery, CCL<br />

g*-<br />

Facts:<br />

l. Petitioner claim is outstanding principalamount <strong>of</strong> Rs.75, 143/- plus interest. As per pO dt. 16.10.2001, scheduled<br />

delivery was within 15 days. The material was repaired & delivered on 26.03.ioOZ.rne pO stipulates ..suitable<br />

penalty'.<br />

2. opposite party's stand: out <strong>of</strong> total deduction <strong>of</strong> rs.70, 493,Penalty deduction is Rs.23, 050 and balance<br />

deduction is towards Income taxlJvAT/Security money. Party did not claim for refund <strong>of</strong> securitv<br />

money.<br />

3. In previous meeting, both the parties were advised to settle the dispute mutually.<br />

DECISION on 10.12.2012: The first party has appeared and was heard. Opposite party did not appear.<br />

The first was advised to submit documentary evidence within a weeks time in support oltrir claim. The case<br />

has been refixed on I lth January 2013 for frnal trearing and appropriate order.<br />

3<br />

Case no. JHSEFC-09/I1<br />

IWs Solar Industries, Mesara, Ranchi<br />

V/s<br />

M/s Drinking water & sanitation department, Govt. <strong>of</strong> <strong>Jharkhand</strong><br />

Facts:<br />

l. Applicant has claimed vide letter dated 17.03.11, for principal outstanding Rs.2,74,155/-plus interest<br />

amount <strong>of</strong> Rs.l, 74,024.<br />

2' The opposite pa(y has informed that eligible amount has already been paid after deduction <strong>of</strong> Security<br />

deposit/Income taxlsales Tax/.Retention money for time extension. The Contract has been terminated due tb<br />

Suppliers failure to supply the remaining material.<br />

3. The petitioner has sent a letter addressed to the Chairman, Facilitation Council informing there in that their<br />

principal amount has been paid and release <strong>of</strong> BG is under progress. In case the claim is mutually settled, the<br />

Petitioner should withdraw the case.<br />

DECISION on 10.12.2012: Both the parties did not appear.. The case has been refixed on 1lth January<br />

2013 for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBI)<br />

<strong>sd</strong>/-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Le gal Remembrancer<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dy.Director <strong>of</strong> Industries


Ft<br />

v<br />

4<br />

Case no. JHSEFC-I2/I1<br />

IvI/s Alcast Engineering Pvt.Ltd., Bokaro<br />

V/s<br />

IWs Manager (finance), Durgapur Steel Plant<br />

Facts Sheet:<br />

1. The Applicant has claimed Rs.1, 87,469.78 towards Principal plus Interest.<br />

2. The opposite party has submitted pointwise reply to the claim <strong>of</strong> first party and has informed that the<br />

claimant has filed a rectification <strong>of</strong> claim to the first party on 03.09.12. In the said rectification claim, it<br />

is informed that the claimant did not submit some <strong>of</strong> the bills to opposite party for payment. The fipst<br />

party should file counter affidavit and submit its final stand with documentary evidence.<br />

DECISION on 10.12.2012: Both the parties have appeared and were .heard. The first party was directed to<br />

submit counter affidavit and rectification <strong>of</strong> claim as was submitted to opposite party.The case has been refixed<br />

on l lth January 2013 for final hearing and appropriate order.<br />

case no. rrsert-t:lt t<br />

IWs Bihar Pesticides & fertilizers, Ramgarh<br />

V/s<br />

M/s Chairman, K.S.Refractories Ltd., Orrissa<br />

Fact Sheet<br />

1. The applicant has claimed principal outstanding <strong>of</strong> Rs.8,01,313 plus interest Rs.16,71,850.<br />

2. The claim relates for the year 1993-94 and the petition filed on 18.08.2012, after a lapse <strong>of</strong> 18 years and<br />

could be treated as time barred application.<br />

3. The opposite party has informed vide its letter dated 20.04.2012 that the Company has ceased its<br />

operation during December 2008 and application for winding up <strong>of</strong> the Company is pending in Odisha<br />

high Court<br />

DECISION on 10.12.20122 The first party has appeared but opposite party did not appear. The case<br />

has been refixed on I lft January 2013 for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBD<br />

<strong>sd</strong>/-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dv.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-<br />

Sd/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC


il<br />

6<br />

w<br />

Case no. JHSEFC-I4/I1<br />

IWs Eastern Engineering Co., Tipudana, Ranchi<br />

V/s<br />

lWs Director Finance, IAG Co. Ltd., 30, CR Avenue, Kolkata<br />

Fact Sheet:<br />

1. The applicant has claimed principal outstanding <strong>of</strong> Rs.75,000 plus interest not yet calculated.<br />

2. Certificate <strong>of</strong> Store entry being documentary evidence <strong>of</strong> dispatch <strong>of</strong> material to purchaser is not<br />

available.<br />

J. CA certificate not available<br />

4. The opposite party has filed an application on 27.04.2012, intimating that the IAG is a BIFR referred<br />

Company and under section 22 <strong>of</strong> the ACT any legal proceedings against the Company cannot be<br />

initiated till the conclusion <strong>of</strong> BIFR.<br />

5. The opposite party did not submit the schedule <strong>of</strong> sundry creditors relating to audited Balance Sheet <strong>of</strong><br />

2009-10 submitted to BIFR to veriff whether the applicants claim is covered under S/creditors or not.<br />

DECISION on 10.12.20122 The first party has appeared but opposite party did not appear. The<br />

opposite party did not appear in consecutive last three meetings. Last opportunity is being.given to<br />

opposite party failing which the case will be decided ex-parte.The case has been refixed on 11th January<br />

2013 for final hearing and appropriate order.<br />

DECISION on 10.12.2012: Both the parties have appeared and were .heard. The first party was<br />

directed to submit the billing details in terms <strong>of</strong> Lab testing report and bill wise payment received and<br />

amount due towards principal with a copy to opposite parry. The case has been re-fixed on 1l'n January<br />

2013 for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

(Jhuma Deb)<br />

Manager (SIDBD<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

tlgsEFC-1<br />

cur",ro. 7/11<br />

M/s L.R.Feno Alloy Pvt. Ltd Kachari Road Ranchi<br />

V/s<br />

M/s Bokaro Steel Plant, Bokaro<br />

Fact Sheet:<br />

l. The applicant has claimed principal outstanding <strong>of</strong> Rs.97,981/ plus interest Rs.3,50,628/-<br />

2. Bokaro Steel Plant has refused to accepthe registered notice on1'|.02.2012.<br />

3. Claimant has sent a copy <strong>of</strong> the application dated 22.02.2012 to opposite party.<br />

4. Opposite party has submitted point wise written statement, challenging the claim <strong>of</strong> the petitioner. The Petitioner<br />

has submitted point wise reply on 30.11.2012<br />

and has sent a copy to opposite party.<br />

5. Point <strong>of</strong> dispute:<br />

i. LD-78,680, supplied within time<br />

ii. Penalty for chemical variation-to prove<br />

iii. ED-Rs.47,003, VAT Rs.l880-to prove<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dy.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-


f<br />

8<br />

Case no. JHSEFC-2112<br />

I\4/s Apna Diesel Pvt.Ltd, Giridih<br />

V/s<br />

lWs DI Williamson, Magor BIO-Fuel Ltd.Kolkata<br />

Fact Sheet:<br />

1. The opposite Party has filed WP case against Secretary/Dl, <strong>Jharkhand</strong><br />

2. The case has been didposed <strong>of</strong> by Hon'ble <strong>Jharkhand</strong> High Court, Ranchi on 10.10.2012 directing the<br />

opposite party to appear before competent authority (IFC)and file the objection before 6th Nov 2012..<br />

3. The opposite party appeared today on 10.12.2012 through his Advocate and prayed four weeks time for<br />

filing Objection.<br />

DECISION on 10.12.2012: Both the parties have appeared and were .heard. The opposite party was<br />

directed to submit their final stand within a weeks time failing which the case will be decided ex-parte.<br />

The case has been re-fixed on llth January 2013 for final hearing and appropriate order. Later on the<br />

Advocate <strong>of</strong> the opposite party filed objection petition at 2.40PM after meeting.<br />

case no. rrisgrc-:lrz<br />

M/s VEXCEL Computers Pvt.Ltd.<br />

V/s<br />

tWs JSEB<br />

Fact Sheet<br />

1. The Applicant was engaged in the work <strong>of</strong> meter reading/surveillance, computerizedata logging and<br />

preparation <strong>of</strong> consumer bill <strong>of</strong> JSEB vide work order no.61 dated 30.09.2002.<br />

2. The Applicant has filed claim for principal outstanding <strong>of</strong> rs.l, 13, 29, 630 and interest <strong>of</strong> Rs.l, 09,<br />

03,255.<br />

3. Applicants claim was sent to opposite party and reply <strong>of</strong> opposite party has been received.<br />

4. The applicant submitted the countereply on dated 10.12.2012.<br />

DECISION on 10.12,20122 The first party has appeared but opposite party did not appear. The case<br />

has been refixed on I lth January 2013 for final hearing and appropriate order'<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBI)<br />

<strong>sd</strong>/-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dy.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC


l0<br />

Case no. JHSEFC-4/I2<br />

M/s Crown Rubber Company, B.S.City, <strong>Jharkhand</strong><br />

Vs.<br />

National Alluminium Company Ltd., Power Plant Division, Angul, Orrissa<br />

Fact Sheet:<br />

l. The applicant is a SME unit registered with Managing Director <strong>of</strong> Industries, BIADA.<br />

2. Theapplicanthasclaimedon28.08.2012,Rs3,97,945towardsprincipalplusinterest<strong>of</strong>Rs.2,87,62<br />

aggregating to Rs.6, 85,569.<br />

DECISION on 10.12.2012: Both the parties have appeared and were .heard. Both the parties were<br />

directed to settle the dispute mutually. The case has been refixed on l lth January 2013 for final hearing<br />

and appropriate order.<br />

ll<br />

Case no. JHSEFC-I/I2<br />

IWs Khetan Udyog,2nd Phase, AIADA, Jamshedpur<br />

Vs.<br />

M/s K.S. Refractories Ltd. ( Subsidiary <strong>of</strong> lWs Orrissa Small lndustries Co.Ltd.<br />

Fact Sheet:<br />

1. The applicant is a SME unit registered with AIADA on 02.03.1990.<br />

2. The applicant has claimed Rs.4,56,054.19 towards principal amount for supply <strong>of</strong> goods against<br />

purchase order dated 22.03.1994 and 18.06.1996 issued by lWs K.S.Refractories, a wholly owned<br />

Company <strong>of</strong> lWs Orissa Small Scales <strong>Industry</strong> Co. Ltd.A<br />

3. The applicant did not submit copy <strong>of</strong> bills /delivery challan.<br />

4. The claim has been filed on 07.08.2012 after lapse <strong>of</strong> nearly 16 years and has become time barred.<br />

DECISION on 10.12.2012: Both the parties did not appear. The case has been refixed on 1lth January 2013<br />

for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

<strong>sd</strong>/-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, AllahabadBank<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBD<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dy.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC


l2<br />

Case no. JHSEFC-6/12<br />

IWs Khetan Udyog,2nd Phase, AIADA, Jamshedpur<br />

Vs.<br />

M/s Ind.Synergy Ltd., Chakradhar Nagar, Roygarh (Chattishgarh).<br />

Fact Sheet:<br />

l. The applicant is a SME unit registered with AIADA on 02.03.1990.<br />

2. The applicant has claimed Rsl, 51,482 towards principal amount for supply <strong>of</strong> magnetite powder against<br />

purchase order dated 18.07.2008 plus interest.<br />

DECISION on l'0.12.2012: Both the parties did not appear. The case has been refixed on 1lth January<br />

2013 for final hearing and appropriate order.<br />

l3<br />

Case no. JHSEFC-7/I2<br />

IWs Pensol Industries Ltd., Upper Bazar, Ranchi<br />

Vs.<br />

M/s Hindusthan Cables Ltd., Rupnarayan Unit, Burdwan, W.Bengal.<br />

Fact Sheet:<br />

l. The applicant is a SME unit registered with Director <strong>of</strong> Industries, Govt.<strong>of</strong> Bihar dated 04.02.1982.<br />

2. The applicant has claimed on 28.08.2012 , Rs2,38,000 towards principal plus interest aggregating to<br />

Rs.7,89,063 for supply <strong>of</strong> Lubricants against purchase order <strong>of</strong> 200012001<br />

DECISION on 10.12.20122 The first party has appeared but opposite party did not appear. The case<br />

has been refixed on I lth January 2013 for final hearing and appropriate order.<br />

<strong>sd</strong>/-<br />

(S.N.Kejariwal)<br />

Consultant<br />

<strong>sd</strong>/-<br />

(Jhuma Deb)<br />

Manager (SIDBD<br />

<strong>sd</strong>/-<br />

(H.P. Biyani)<br />

(JSIA, Ranchi<br />

<strong>sd</strong>/-<br />

(Mithilesh Prasad)<br />

Addl. Legal Remembrancer<br />

<strong>sd</strong>/-<br />

(Rajesh Sharan)<br />

Sr.Manager, Allahabad Bank<br />

<strong>sd</strong>/-<br />

(Dilip Kumar Sharma)<br />

Dy.Director <strong>of</strong> Industries<br />

<strong>sd</strong>/-<br />

( Smt. Vandana Dadel )<br />

Director <strong>of</strong> Industries cum Chairman JHMSEFC<br />

Memo no.. 39 /Ranchi dated oalot lzut}<br />

F.No. V/,J<strong>of</strong>uo/ eal"gr&Z -otfzao<br />

Copy forwarded to all membbrd <strong>of</strong> the Facilitation Council for information and record.<br />

/1<br />

D eputy D il"fi I I J ifd,,,,i".<br />

Directorate <strong>of</strong> Industries<br />

<strong>Jharkhand</strong>. Ranchi