29.01.2015 Views

BEESLEY ENGINEERING LTD. - Village of Belcarra

BEESLEY ENGINEERING LTD. - Village of Belcarra

BEESLEY ENGINEERING LTD. - Village of Belcarra

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The final Agreement from WED (dated July 2009) was received and executed by the <strong>Village</strong><br />

in September 2009. Following receipt <strong>of</strong> the Agreement, the <strong>Village</strong> undertook the elector assent<br />

process to adopt the requisite bylaws to authorize borrowing for the municipal portion <strong>of</strong> the capital<br />

costs. Bylaw 413, 2008 was adopted January 11, 2010, being the date the <strong>Village</strong> had legal authority<br />

to borrow monies for it’s share <strong>of</strong> the project. Following adoption <strong>of</strong> the bylaw Dayton & Knight and<br />

Beesley Engineering were instructed to proceed with design, tendering and inspection <strong>of</strong> the project.<br />

In 2010, work was proceeding on design consultation with and obtaining District <strong>of</strong> North Vancouver<br />

permits, archeological permits, environmental permits and permission to carry out construction in the<br />

Fisheries window.<br />

As the grant application, approval process and <strong>Village</strong> approval had taken 3 years and the<br />

completion date was still March 31, 2012 it was understood by all parties that time was <strong>of</strong> the<br />

essence. It was decided to tender and award the work as soon as the design was complete. Splitting<br />

the municipal watermain construction into three phases enabled portions <strong>of</strong> the work to be completed<br />

and tendered rather than waiting for all <strong>of</strong> the design to be complete. (This was not the only<br />

consideration in phasing the work.)<br />

There was no time to carry out all the design work and then re-estimate the project costs prior<br />

to going to tender/construction.<br />

In 2010, the marine portion <strong>of</strong> the work was advanced to construction. This component was<br />

able to be tendered first as the design was completed through a combination <strong>of</strong> funding from WED<br />

which permitted Dayton & Knight to complete a sufficient portion <strong>of</strong> the design to permit regulatory<br />

review. The balance <strong>of</strong> the design was completed by Dayton & Knight who held invoices so that the<br />

<strong>Village</strong> would not immediately incur the costs.<br />

The Marine Pipeline work was awarded to Vancouver Pile Driving on August 12, 2010, the<br />

North Vancouver Vault and Dean Place work was awarded to Merletti Construction on May 9, 2011,<br />

the Midden Building and Tatlow Pump Station work was awarded to Merletti Construction on June<br />

27, 2011. The tender prices for this work, with the exception <strong>of</strong> Tatlow Pump Station, were in line<br />

with the 2008 estimate.<br />

The Municipal Watermains Phase I work was awarded to Mission Contractors on September<br />

13, 2010, the Municipal Watermains Phases II and III work was awarded to Sandpiper Contracting<br />

on August 8, 2011 and November 16, 2011 respectively. Award <strong>of</strong> the Phase III Contract was delayed<br />

due to a shortage <strong>of</strong> funds.<br />

In May <strong>of</strong> 2011, as the tendered construction costs were becoming known, the <strong>Village</strong> began<br />

a comparison <strong>of</strong> the actual and projected construction costs with the 2008 estimate. It was identified<br />

at that time that final construction costs would exceed the 2008 estimate. A complete estimate <strong>of</strong> the<br />

projected final costs and a budget was prepared in mid October 2011. There were insufficient funds<br />

available to award the final phase <strong>of</strong> the waterworks construction to Sandpiper.<br />

As a result, the <strong>Village</strong> arranged for additional funds and the final phase <strong>of</strong> the work was<br />

awarded to Sandpiper Contracting.<br />

4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!