Davis Campus Open for Science<br />

$15.2M South Dakota Commitment to Davis Campus Development<br />

– $1.8M design (CNA Consulting Engineers)<br />

– $4.8M excavation & shotcrete (SDSTA performed)<br />

– $8.6M outfitting (Ainsworth-Benning Construction general contractor, local subs)<br />

– 9,979 ft 2 laboratory space; 29,402 ft 2 total Davis Campus footprint<br />

– Timeline:<br />

• Sep 2009 – Jan 2011: Excavation performed in-house (16,632 tonnes excavated)<br />

• Jan 2011 – Jun 2011: Shotcrete (1,264 – 2,000 lb bags)<br />

• Jun 2011: Outfitting contractor mobilized<br />

• May 2012: Substantial completion (Dedication May 30)<br />

• Jul 2012: Final occupancy<br />

• Zero lost-time injuries<br />

Davis Campus 3D Laser Scan"<br />

Sanford Underground Research Facility<br />

14