Base Realignment and Closure<br />

Program Management Office West<br />

1455 Frazee Road, Suite 900<br />

San Diego, Cali<strong>for</strong>nia 92108-4310<br />

CONTRACT NO. N62473-07-D-3211<br />

CTO NO. 0009<br />

APPENDIX B<br />

DRAFT<br />

PROJECT CONTRACTOR<br />

QUALITY CONTROL PLAN<br />

March 6, 2009<br />

WORK PLAN FOR PETROLEUM SITES SAMPLING AND<br />

EVALUATION FOR CLOSURE OR REMOVAL ACTIONS<br />

FORMER NAVAL AIR STATION MOFFETT FIELD<br />

MOFFETT FIELD, CALIFORNIA<br />

DCN: ECSD-3211-0009-0003<br />

1230 Columbia Street, Suite 750<br />

San Diego, Cali<strong>for</strong>nia 92101-8536<br />

Gregory Joyce<br />

QC Program Manager


TABLE OF CONTENTS<br />

PAGE<br />

ABBREVIATIONS AND ACRONYMS.................................................................................. B.iii<br />

1.0 INTRODUCTION ...........................................................................................................B.1-1<br />

1.1 PURPOSE/SITE BACKGROUND ......................................................................B.1-1<br />

1.2 SCOPE ..................................................................................................................B.1-1<br />

2.0 ORGANIZATION AND RESPONSIBILITIES .............................................................B.2-1<br />

2.1 REMEDIAL PROJECT MANAGER ...................................................................B.2-1<br />

2.2 QUALITY ASSURANCE OFFICER...................................................................B.2-1<br />

2.3 RESIDENT OFFICER IN CHARGE OF CONSTRUCTION .............................B.2-2<br />

2.4 PROJECT MANAGER.........................................................................................B.2-2<br />

2.5 SITE SUPERINTENDENT ..................................................................................B.2-3<br />

2.6 CERTIFIED INDUSTRIAL HYGIENIST ...........................................................B.2-4<br />

2.7 SITE HEALTH AND SAFETY SPECIALIST ....................................................B.2-4<br />

2.8 QUALITY CONTROL PROGRAM MANAGER ...............................................B.2-6<br />

2.9 PROJECT QUALITY CONTROL MANAGER ..................................................B.2-6<br />

2.10 PROGRAM CHEMIST ........................................................................................B.2-7<br />

2.11 SUBCONTRACTORS AND VENDORS ............................................................B.2-7<br />

3.0 DEFINABLE FEATURES OF WORK...........................................................................B.3-1<br />

4.0 QUALITY CONTROL MEETINGS...............................................................................B.4-1<br />

4.1 KICK-OFF MEETING .........................................................................................B.4-1<br />

4.2 QC MEETINGS ....................................................................................................B.4-1<br />

5.0 INSPECTION PROCESS................................................................................................B.5-1<br />

5.1 PREPARATORY PHASE INSPECTION............................................................B.5-1<br />

5.2 INITIAL PHASE INSPECTION ..........................................................................B.5-1<br />

5.3 FOLLOW-UP PHASE INSPECTION..................................................................B.5-2<br />

5.4 ADDITIONAL PREPARATORY AND INITIAL PHASES...............................B.5-2<br />

5.5 COMPLETION INSPECTION.............................................................................B.5-2<br />

5.5.1 <strong>Field</strong> Quality Control Completion Inspections..........................................B.5-3<br />

5.5.2 Prefinal Inspection.....................................................................................B.5-3<br />

5.5.3 <strong>Final</strong> Acceptance Inspection......................................................................B.5-3<br />

5.6 INSPECTION DOCUMENTATION ...................................................................B.5-3<br />

6.0 SUBMITTALS ................................................................................................................B.6-1<br />

6.1 REVIEW OF SUBMITTALS ...............................................................................B.6-1<br />

6.2 SUBMITTAL PROCESS......................................................................................B.6-2<br />

6.3 REVIEW AND PROCESSING OF SUBMITTALS THAT DO NOT<br />

REQUIRE NAVY APPROVAL...........................................................................B.6-2<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.i Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


TABLE OF CONTENTS<br />

(Continued)<br />

PAGE<br />

6.4 REVIEW AND PROCESSING OF SUBMITTALS THAT REQUIRE<br />

NAVY APPROVAL .............................................................................................B.6-2<br />

6.5 REVISED SUBMITTALS....................................................................................B.6-3<br />

7.0 NONCONFORMANCES................................................................................................B.7-1<br />

7.1 IDENTIFICATION OF NONCONFORMING ITEMS .......................................B.7-1<br />

7.1.1 Condition Requiring Stop Work................................................................B.7-1<br />

7.2 DISPOSITION ......................................................................................................B.7-1<br />

7.2.1 <strong>Field</strong> Change Requests ..............................................................................B.7-1<br />

7.3 CORRECTIVE ACTIONS ...................................................................................B.7-2<br />

8.0 REFERENCES ................................................................................................................B.8-1<br />

TABLES<br />

Table B.3-1<br />

Table B.6-1<br />

Definable Features of Work<br />

Submittal Register<br />

FIGURES<br />

Figure B.2-1<br />

<strong>Project</strong> Organization Chart<br />

ATTACHMENTS<br />

Attachment 1<br />

Quality Control Forms<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.ii Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


ABBREVIATIONS AND ACRONYMS<br />

AHA<br />

APP<br />

CIH<br />

<strong>CQC</strong><br />

CTO<br />

DFW<br />

EHS<br />

EM<br />

FCR<br />

FWENC<br />

<strong>Moffett</strong><br />

NAS<br />

NASA<br />

NAVFAC<br />

NCR<br />

PjM<br />

PQCM<br />

QA<br />

QAO<br />

QC<br />

QCM<br />

ROICC<br />

RPM<br />

SAP<br />

SHSS<br />

SSHP<br />

TtEC<br />

UFGS<br />

USACE<br />

Activity Hazard Analysis<br />

Accident Prevention <strong>Plan</strong><br />

Certified Industrial Hygienist<br />

Contractor Quality Control<br />

Contract Task Order<br />

definable feature of work<br />

Environmental Health and Safety<br />

Engineer Manual<br />

<strong>Field</strong> Change Request<br />

Foster Wheeler Environmental Corporation<br />

Naval Air Station <strong>Moffett</strong> <strong>Field</strong><br />

Naval Air Station<br />

National Aeronautics and Space Administration<br />

Naval Facilities Engineering Command<br />

Noncon<strong>for</strong>mance Report<br />

<strong>Project</strong> Manager<br />

<strong>Project</strong> Quality Control Manager<br />

quality assurance<br />

Quality Assurance Officer<br />

quality control<br />

Quality Control Program Manager<br />

Resident Officer in Charge of Construction<br />

Remedial <strong>Project</strong> Manager<br />

Sampling and Analysis <strong>Plan</strong><br />

Site Health and Safety Specialist<br />

Site Safety and Health <strong>Plan</strong><br />

Tetra Tech EC, Inc.<br />

Unified Facilities Guide Specification<br />

United States Army Corps of Engineers<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.iii Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.iv Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


1.0 INTRODUCTION<br />

The <strong>Project</strong> Contractor Quality Control (<strong>CQC</strong>) <strong>Plan</strong> identifies the specific procedures<br />

and methods to be implemented <strong>for</strong> the investigation of petroleum sites at the <strong>for</strong>mer Naval Air<br />

Station (NAS) <strong>Moffett</strong> <strong>Field</strong> (<strong>Moffett</strong>), <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia. Tetra Tech EC, Inc. (TtEC)<br />

has been contracted by the Navy to per<strong>for</strong>m this investigation at <strong>Moffett</strong> <strong>for</strong> the Base<br />

Realignment and Closure Program Management Office West under Naval Facilities Engineering<br />

Command Southwest Remedial Action Contract No. N62473-07-D-3211. This <strong>CQC</strong> <strong>Plan</strong><br />

fulfills the requirements of the TtEC quality control (QC) system requirements.<br />

1.1 PURPOSE/SITE BACKGROUND<br />

The purpose of this <strong>CQC</strong> <strong>Plan</strong> is to establish the specific procedures and methods <strong>for</strong> field<br />

inspections of the investigation activities proposed in the Work <strong>Plan</strong>.<br />

<strong>Moffett</strong> is located near the southern end of San Francisco Bay in Santa Clara County, Cali<strong>for</strong>nia<br />

(see Work <strong>Plan</strong> Figure 1-1). <strong>Moffett</strong> is bounded by U.S. Fish and Wildlife Service land to the<br />

north, Stevens Creek to the west, U.S. Highway 101 to the south, and a Lockheed Aerospace<br />

facility to the east (see Work <strong>Plan</strong> Figure 1-2). <strong>Moffett</strong> borders the cities of Mountain View and<br />

Sunnyvale, Cali<strong>for</strong>nia. The National Aeronautics and Space Administration (NASA) Ames<br />

Research Center is located in the northwestern portion of <strong>Moffett</strong>.<br />

<strong>Moffett</strong> was originally commissioned as NAS Sunnyvale in 1933. In 1935, NAS Sunnyvale was<br />

transferred to the U.S. Army Air Corps. In 1939, a permit was granted to Ames Aeronautical<br />

Laboratory to use a portion of the base. NAS Sunnyvale was returned to Navy control in 1942<br />

and was renamed NAS <strong>Moffett</strong> <strong>Field</strong>. In 1994, NAS <strong>Moffett</strong> <strong>Field</strong> was closed as an active Navy<br />

base under the Base Realignment and Closure program (Foster Wheeler Environmental<br />

Corporation [FWENC] 2002).<br />

The property was transferred to NASA on July 1, 1994, and the facility was renamed <strong>Moffett</strong><br />

Federal Airfield. Federal and state tenants located at <strong>Moffett</strong> include the U.S. Army, U.S. Air<br />

Force, and Cali<strong>for</strong>nia Air National Guard. Current <strong>Moffett</strong> uses include airfield operations,<br />

military facilities, and NASA research activities. <strong>Moffett</strong> has a fully functional federal airport<br />

and facilities <strong>for</strong> military personnel and their families including family housing, a commissary, a<br />

military clinic, a service station, tennis courts, and an 18-hole golf course (FWENC 2002).<br />

1.2 SCOPE<br />

This <strong>CQC</strong> <strong>Plan</strong> is applicable to all field operations and will be available at the project field<br />

office. All work activities will be conducted in accordance with the Work <strong>Plan</strong>.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.1-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


The <strong>CQC</strong> <strong>Plan</strong> will be implemented <strong>for</strong> the following activities:<br />

• Mobilization<br />

• Geophysical survey<br />

• Concrete coring and cutting<br />

• Soil and groundwater sampling<br />

• Surface restoration including asphalt and concrete work<br />

• Land survey<br />

• Waste characterization and disposal<br />

• Site cleanup and final inspection<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.1-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


2.0 ORGANIZATION AND RESPONSIBILITIES<br />

This section describes the organization and authority of project personnel, including<br />

subcontractors. The organizational structure, functional responsibilities, levels of authority, and<br />

lines of communication have been established within the organization to ensure high-quality<br />

work. The project organization chart showing the reporting lines <strong>for</strong> each individual is provided<br />

in Figure B.2-1. The responsibilities and authorities of the key personnel are described in the<br />

following paragraphs.<br />

The Naval Facilities Engineering Command, Southwest Remedial <strong>Project</strong> Manager (RPM) <strong>for</strong><br />

this project is Mr. Wilson Doctor. Mr. Gary Munekawa and Mr. David Smith, the on-site<br />

Resident Officers in Charge of Construction (ROICCs), are responsible <strong>for</strong> the management,<br />

oversight of safety, and quality assurance (QA) of field activities.<br />

The project personnel will be organized to facilitate effective communications and to ensure that<br />

organizational lines of communications, roles and responsibilities, and reporting requirements<br />

are well defined. The organization will be defined to a level sufficient to ensure that each<br />

participant whose actions could affect the quality of field or laboratory operations or reporting<br />

has an understanding of his/her responsibilities and how these responsibilities fit into the overall<br />

team. The project organization chart is provided in Figure B.2-1. Key contacts <strong>for</strong> the project<br />

are listed in Work <strong>Plan</strong> Table 1-3.<br />

2.1 REMEDIAL PROJECT MANAGER<br />

The RPM has primary responsibility with the Navy <strong>for</strong> day-to-day management of the project<br />

activities per<strong>for</strong>med under this Work <strong>Plan</strong> and <strong>for</strong> its successful completion. The RPM’s duties<br />

and authority include:<br />

• Per<strong>for</strong>ming project management <strong>for</strong> the Navy<br />

• Ensuring that the project scope of work requirements are fulfilled<br />

• Overseeing the project cost and schedule<br />

• Providing <strong>for</strong>mal technical direction to the TtEC project team, as needed<br />

2.2 QUALITY ASSURANCE OFFICER<br />

The Quality Assurance Officer (QAO) is the Navy representative with primary responsibility <strong>for</strong><br />

ensuring that the contract-required QA measures are in place and effective <strong>for</strong> the work<br />

per<strong>for</strong>med. The QAO’s duties and authority include:<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Reviewing and approving Sampling and Analysis <strong>Plan</strong>s (SAPs)<br />

• Providing Navy oversight of the TtEC QA Program<br />

• Acting as point of contact <strong>for</strong> matters pertaining to generation and maintenance of<br />

quality of data<br />

• Authorizing the suspension of project execution if QA requirements are not adequately<br />

followed<br />

2.3 RESIDENT OFFICER IN CHARGE OF CONSTRUCTION<br />

The ROICC staff has the primary responsibility <strong>for</strong> providing on-site QA and safety oversight of<br />

contractors. The ROICC staff member’s duties and authority include:<br />

• Reviewing and providing comments to the Work <strong>Plan</strong>, the <strong>CQC</strong> <strong>Plan</strong>, and the<br />

Accident Prevention <strong>Plan</strong> (APP), and the Site Safety and Health <strong>Plan</strong> (SSHP)<br />

including Activity Hazard Analyses (AHAs)<br />

• Verifying that all work has been completed per contract and technical specifications<br />

prior to final government acceptance through pre-final and final inspections<br />

• Per<strong>for</strong>ming ongoing field quality assurance to verify that all work per<strong>for</strong>med under the<br />

Contractor’s <strong>CQC</strong> Program is in compliance with both the contract and technical<br />

specifications<br />

• Notifying the contractor of any work that is not in compliance<br />

• Notifying the contractor of any work that is being per<strong>for</strong>med in an unsafe manner<br />

• Interacting with the contractor’s <strong>Project</strong> Quality Control Manager (PQCM) on qualityrelated<br />

issues<br />

• Reviewing and signing waste manifests as the generator’s representative<br />

• Reviewing Contractor Daily Reports <strong>for</strong> completeness and accuracy<br />

• Attending preparatory phase, initial phase, pre-final, and final acceptance inspections<br />

• Attending weekly QC meetings<br />

• Acting as the interface with NASA personnel on various matters (permits, traffic<br />

control, etc.)<br />

2.4 PROJECT MANAGER<br />

The <strong>Project</strong> Manager (PjM) is responsible <strong>for</strong> the direction, execution, and successful completion<br />

of project tasks in order to achieve overall project goals. The PjM has responsibility <strong>for</strong>, and the<br />

authority to direct, all segments of the project including technical, construction, and<br />

administrative activities. Authorities and responsibilities include the following:<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Coordinating work activities of subcontractors and TtEC personnel and ensuring that<br />

all personnel adhere to the administrative and technical requirements of the project<br />

• Monitoring and reporting the progress of work and ensuring that the project<br />

deliverables are completed on time and within project budget<br />

• Monitoring the budget and schedule and notifying the client and the Program Manager<br />

of any changes that may require administration actions<br />

• Ensuring adherence to the quality requirements of the contract, project scope of work,<br />

and the QC <strong>Plan</strong>s<br />

• Ensuring that all work meets the requirements of the technical specifications and<br />

complies with applicable codes and regulations.<br />

• Ensuring that all work activities are conducted in a safe manner in accordance with the<br />

APP, SSHP, Safety and Health Requirements Manual (Engineer Manual [EM]-385-1-1;<br />

United States Army Corps of Engineers [USACE] 2003), and all applicable<br />

Occupational Safety and Health Administration regulations<br />

• Serving as the primary contact between the Navy and TtEC <strong>for</strong> actions and<br />

in<strong>for</strong>mation related to the work and make sure to include appropriate TtEC lead and<br />

experts in the decision-making<br />

• Coordinating satisfactory resolution and completion of evaluation and acceptance<br />

report <strong>for</strong> Noncon<strong>for</strong>mance Reports (NCRs)<br />

2.5 SITE SUPERINTENDENT<br />

The Site Superintendent reports to the PjM and is responsible <strong>for</strong> coordinating, directing,<br />

implementing, and supervising site construction activities. Specific duties of the Site<br />

Superintendent include the following:<br />

• Implementing construction activities in accordance with the Work <strong>Plan</strong><br />

• Directing field construction leaders, labor, support personnel, and subcontractors<br />

• Administering site access and site security<br />

• Maintaining work site, vehicles, and equipment<br />

• Coordinating and maintaining logistics of all components of on-site tasks, including<br />

all personnel and equipment<br />

• Assisting Site Health and Safety Specialist (SHSS) to ensure that all work is being<br />

conducted in a safe manner<br />

• Preparing daily production and weekly status reports along with a monthly summary<br />

report and estimating future scheduling needs<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-3 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


2.6 CERTIFIED INDUSTRIAL HYGIENIST<br />

The Certified Industrial Hygienist (CIH) has authority to implement and oversee the TtEC<br />

Health and Safety Program. The CIH has the responsibility and authority to per<strong>for</strong>m the<br />

following:<br />

• Ensuring that all staff, including subcontractors, comply with the APP, SSHP, state<br />

and federal regulations, and corporate policies<br />

• Interacting with the PjM on all aspects of health and safety from the initial planning<br />

phase through fieldwork and closeout<br />

• Providing advice and assistance on any safety, industrial hygiene, or accident<br />

prevention issue to the SHSS, PjM, and Site Superintendent<br />

• Reviewing all site health and safety documents and cost estimates, and working to<br />

properly staff projects<br />

• Working to pre-qualify field subcontractors<br />

2.7 SITE HEALTH AND SAFETY SPECIALIST<br />

The SHSS ensures that all elements of the approved APPs and SSHPs are implemented and<br />

en<strong>for</strong>ced on site. The SHSS will report directly to the CIH and will assist in implementing and<br />

en<strong>for</strong>cing the APP and SSHP in the field. The SHSS has full authority to issue stop work orders<br />

or evacuation orders where work operations of noncompliance(s) may threaten the health and<br />

safety of site workers or the public. The SHSS has the responsibility and authority to per<strong>for</strong>m<br />

the following:<br />

• Ensuring that all personnel understand the requirements of TtEC’s Environmental<br />

Health and Safety (EHS) program and procedures through training and<br />

communication<br />

• Ensuring en<strong>for</strong>cement of the APP and SSHP by means of daily site and equipment<br />

inspections that meet the requirements of EM-385-1-1 (USACE 2003)<br />

• Investigating all accidents, injuries, illnesses, near-misses, and other incidents<br />

• Ensuring that project personnel are trained on the hazards of hazardous substances on<br />

the project, maintaining a Material Safety Data Sheet file to provide easy access to<br />

project personnel, and per<strong>for</strong>ming inspections to ensure that all waste containers are<br />

correctly labeled<br />

• Ensuring that the APP and SSHP are read, understood, and signed by all personnel<br />

including subcontractors<br />

• Ensuring that tailgate safety meetings are conducted on days that work is per<strong>for</strong>med<br />

and that documentation of all meetings and any other additional training is completed,<br />

which includes reviewing AHAs during the preparatory and initial phase meetings or<br />

whenever a new worker is brought on site<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-4 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Verifying that project safety equipment is inspected, as required by the EHS program<br />

• Re-evaluating site conditions <strong>for</strong> safety on an on-going basis<br />

• Correcting and/or suspending work activities when unsafe conditions or work<br />

practices are observed at the site<br />

• Coordinating site health and safety requirements with the Site Superintendent and the<br />

PjM<br />

• Ensuring maintenance of all health and safety monitoring and personal protective<br />

equipment and directing site monitoring activities<br />

• Coordinating daily field activities with the Site Superintendent<br />

• Coordinating site safety and emergency response duties; verifying site<br />

communications system with site personnel<br />

• Per<strong>for</strong>ming inspection of safety equipment<br />

• Reporting all incidents to the ROICC within 2 hours, as required by EM-385-1-1<br />

(USACE 2003), and immediately reporting to the ROICC any fatal injury, one or more<br />

persons admitted to a hospital, or property damage to government property<br />

• Conducting and preparing reports of daily safety inspections of work processes, site<br />

conditions, and equipment conditions and submitting to the Site Superintendent<br />

• Verifying that all personnel have the necessary training and medical clearance prior to<br />

entering the exclusion zone or contamination reduction zone at the site; in<strong>for</strong>ming the<br />

Site Superintendent of any site personnel with medical restrictions<br />

• Removing contractor personnel from the project if the contractor is operating in an<br />

unsafe manner<br />

• Determining and posting routes to medical facilities and emergency telephone<br />

numbers arranging <strong>for</strong> emergency transportation to medical facilities<br />

• Controlling access to the exclusion zone and/or work areas, as defined<br />

• Serving as the <strong>Project</strong> Hazard Communication Coordinator<br />

• Maintaining training records and medical certifications <strong>for</strong> all on-site personnel<br />

including subcontractors<br />

• Initiating necessary revisions or changes to the APP and SSHP<br />

• Maintaining site control procedures<br />

• Maintaining current records of certification <strong>for</strong> first aid and cardiopulmonary<br />

resuscitation <strong>for</strong> project field personnel<br />

• Attending required meetings, including the pre-construction conference, weekly QC<br />

meetings, pre- and post-construction site inspections, and other scheduled and<br />

unscheduled meetings<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-5 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Assigning an alternate SHSS if the designated SHSS will be absent with the<br />

concurrence of the Navy and PjM<br />

2.8 QUALITY CONTROL PROGRAM MANAGER<br />

The Quality Control Program Manager (QCM) will report directly to the Corporate QC Manager<br />

and has the responsibility and authority to per<strong>for</strong>m the following:<br />

• Establishing and maintaining the QC program <strong>for</strong> the project<br />

• Overseeing the QC program including data acquisition<br />

• Working directly with the PjM and the QAO to ensure implementation of the <strong>CQC</strong><br />

<strong>Plan</strong><br />

• Acting as a focal point <strong>for</strong> coordination of all QC project-related matters and resolving<br />

all QC issues<br />

• Providing QC direction and training to the PQCM and others per<strong>for</strong>ming QC functions<br />

• Suspending project activities if quality standards are not maintained<br />

• Interfacing with the Navy, including the QAO, on quality-related items<br />

• Conducting field QC audits to ensure that site QC plans are being followed<br />

• Per<strong>for</strong>ming reviews of audit and surveillance reports conducted by others<br />

• Implementing Navy technical direction letters related to QC topics<br />

2.9 PROJECT QUALITY CONTROL MANAGER<br />

The PQCM is responsible <strong>for</strong> overall management of project QC and reports to the QCM. The<br />

PQCM has the authority to stop work on site-related issues affecting the quality of the work<br />

per<strong>for</strong>med and <strong>for</strong> directing the correction of all noncon<strong>for</strong>ming work. The PQCM will be on<br />

site at all times during field activities. The duties of the PQCM are as follows:<br />

• Implementing the three phases of control (preparatory, initial, and follow-up) to assure<br />

that all prerequisites have been completed prior to the start of and during each<br />

applicable definable feature of work<br />

• Scheduling and conducting QC meetings to review work status; generating meeting<br />

minutes to document discussions and conclusions<br />

• Monitoring QC activities to ensure con<strong>for</strong>mance with authorized policies, procedures,<br />

contract specifications, required standards, sound practices, and methods of quality<br />

construction<br />

• Being responsible <strong>for</strong> issuance and maintenance of the NCR<br />

• Ensuring that all on-site and off-site inspections, testing, and sampling are per<strong>for</strong>med<br />

in accordance with the plans, specifications, and applicable codes<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-6 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Providing inspection and conducting or supervising testing and sampling<br />

• Reviewing and maintaining records of approved submittals and Design Change<br />

Notices <strong>for</strong> construction activities and <strong>Field</strong> Change Requests (FCRs)<br />

• Inspecting material delivery handling and storage in accordance with technical<br />

specifications<br />

• Updating as-built drawings <strong>for</strong> invoice certification and confirming that completed<br />

work meets the contract requirements<br />

• Reviewing and approving submittals and shop drawings and/or <strong>for</strong>ward submittals as<br />

in<strong>for</strong>mation only or <strong>for</strong> approval<br />

• Issuing compliance notice on material, equipment, work in place, and workmanship<br />

• Directing the removal of work, material, and equipment not in compliance with plans<br />

and specifications<br />

• Immediately stopping any segment of work that does not comply with the<br />

specifications and drawings<br />

• In<strong>for</strong>ming the QCM of all proposed changes, concerns, problems, and any deviations<br />

from approved plans, including health and safety issues<br />

• In<strong>for</strong>ming the QCM and PjM of NCRs to document any non-compliant conditions and<br />

<strong>for</strong>warding the NCRs to the QCM to obtain approval of recommended corrective<br />

actions<br />

2.10 PROGRAM CHEMIST<br />

The Program Chemist oversees sample collection, handling, analysis, and analytical data<br />

reporting. The Program Chemist has responsibility and authority <strong>for</strong> the following:<br />

• Developing SAPs<br />

• Evaluating and selecting qualified subcontract laboratories<br />

• Implementing data QC procedures and per<strong>for</strong>ming an audit of field per<strong>for</strong>mance<br />

• Reviewing off-site laboratory data prior to use<br />

• Ensuring that proper review of on-site laboratory data is per<strong>for</strong>med<br />

• Coordinating data validation of off-site laboratory data<br />

• Reviewing data validation reports<br />

• Preparing analytical reports and supporting project report preparation<br />

2.11 SUBCONTRACTORS AND VENDORS<br />

Qualified subcontractors may be selected to provide various construction services <strong>for</strong> this<br />

project. The subcontractor is required to provide labor, material, and equipment necessary to<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-7 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


conduct construction activities as directed by the PjM. Subcontractors and vendors will be<br />

required to con<strong>for</strong>m with TtEC’s QA/QC <strong>Plan</strong> and the requirements of all approved procedures,<br />

technical specifications, and contract provisions.<br />

Subcontractor personnel are responsible <strong>for</strong> maintaining a daily log of the project activities they<br />

per<strong>for</strong>m and <strong>for</strong> providing in<strong>for</strong>mation needed to complete the Daily <strong>CQC</strong> Report. All records,<br />

including inspection reports, deficiency reports, and re-inspections of corrective actions, will be<br />

documented.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.2-8 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


3.0 DEFINABLE FEATURES OF WORK<br />

A definable feature of work (DFW) is defined as an activity or task separate and distinct from<br />

other activities that requires separate control activities. The DFW establishes the control<br />

measures required to verify both the quality of work per<strong>for</strong>med and compliance with specified<br />

requirements, which include inspecting materials and workmanship be<strong>for</strong>e, during, and after<br />

each DFW. Preparatory and Initial inspections will be per<strong>for</strong>med on all DFWs, with the<br />

exception of mobilization and site cleanup and final inspection (demobilization). Activities that<br />

will be covered by the PQCM during the inspections are listed in Table B.3-1. The following<br />

DFWs have been identified <strong>for</strong> the project:<br />

• Mobilization<br />

• Geophysical survey<br />

• Concrete coring and cutting<br />

• Soil and groundwater sampling<br />

• Surface restoration including asphalt and concrete work<br />

• Land survey<br />

• Waste characterization and disposal<br />

• Site cleanup and final inspection<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.3-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.3-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


4.0 QUALITY CONTROL MEETINGS<br />

4.1 KICK-OFF MEETING<br />

Prior to the start of site work, the PQCM will conduct a kick-off meeting with the ROICC to<br />

discuss the QC program required by this contract. The purpose of this meeting is to develop a<br />

mutual understanding of the QC details, including <strong>for</strong>ms to be used; administration of on-site and<br />

off-site work; and coordination of the Contractor’s management, production, and the PQCM<br />

duties with the ROICC. As a minimum, the Contractor’s personnel required to attend will<br />

include the PjM, Site Superintendent, SHSS, and PQCM. Minutes of the meeting shall be<br />

prepared by the PQCM and signed by both the PjM and RPM or ROICC. This meeting may be<br />

held in conjunction with other meetings (e.g., pre-construction meeting).<br />

4.2 QC MEETINGS<br />

After the start of field activities, the PQCM will conduct QC meetings at a frequency of once per<br />

week or as required by the ROICC. The meetings will be held at the project site. Attendees will<br />

include, but not be limited to, the ROICC, QAO, PjM, PQCM, SHSS, and the Site<br />

Superintendent. The following will be discussed at each meeting:<br />

• Review the minutes of the previous meeting.<br />

• Review the schedule.<br />

- Work or testing accomplished since last meeting<br />

- Rework items identified since last meeting<br />

- Rework items completed since last meeting<br />

• Review the status of submittals.<br />

- Submittals reviewed and approved since last meeting<br />

- Submittals required in the near future<br />

• Review the work to be accomplished in the following 2 weeks and documentation<br />

required. Schedule the three phases of control and testing.<br />

- Establish completion date <strong>for</strong> rework items<br />

- Required preparatory phase inspections<br />

- Required initial phase inspections<br />

- Required follow-up phase inspections<br />

- Required testing<br />

- Status of off-site work or testing<br />

- Required documentation<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.4-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Resolve QC and production problems.<br />

• Address items that may require revisions to the <strong>Project</strong> <strong>CQC</strong> <strong>Plan</strong>.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.4-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


5.0 INSPECTION PROCESS<br />

5.1 PREPARATORY PHASE INSPECTION<br />

With the exception of mobilization and site cleanup and final inspection (demobilization), the<br />

PQCM will conduct preparatory phase inspections prior to starting the DFWs listed in Table B.3-1.<br />

The PQCM will oversee the activities shown on Table B.3-1 <strong>for</strong> mobilization and site cleanup<br />

and final inspection. Results of preparatory inspections will be documented on the <strong>CQC</strong> daily<br />

report. These inspections will include:<br />

• Reviewing the Work <strong>Plan</strong> and drawings<br />

• Ensuring that materials and/or equipment have been tested, submitted, and approved<br />

• Ensuring that provisions have been made to provide required control inspection and<br />

testing<br />

• Examining the work area to ensure that required preliminary work has been<br />

completed and is in compliance with the approved requirements<br />

• Conducting a physical examination of the required materials and equipment to ensure<br />

that they are properly delivered to the site, con<strong>for</strong>m to approved shop drawings or<br />

specifications, and are properly stored<br />

• Reviewing the appropriate AHAs to ensure that safety requirements are met<br />

• Discussing procedures applicable to the work<br />

• Ensuring that the Work <strong>Plan</strong> has been accepted by the Navy<br />

The PjM, RPM, and the ROICC shall be notified at least 2 working days in advance of<br />

preparatory phase activity. This phase shall include a meeting conducted by the PQCM and<br />

attended by the Site Superintendent and any other personnel involved in per<strong>for</strong>ming the DFW.<br />

The issues discussed during the preparatory phase meetings will be documented on the<br />

Preparatory Inspection Checklist. The PQCM will direct personnel per<strong>for</strong>ming work activities as<br />

to the acceptable level of workmanship required.<br />

5.2 INITIAL PHASE INSPECTION<br />

An initial inspection will be per<strong>for</strong>med at the beginning of a DFW and will include the<br />

following:<br />

• Checking preliminary work to ensure that it is in compliance with requirements<br />

• Reviewing the Inspection Checklist documenting results of the preparatory phase<br />

meeting<br />

• Verifying full contract compliance, including required control inspection and testing<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.5-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• Establishing the required level of workmanship and verification to ensure that work<br />

meets the minimum acceptable standards<br />

• Checking safety requirements to include compliance with the applicable AHAs, APP,<br />

and SSHP<br />

The PjM, RPM, and ROICC will be notified at least 2 working days in advance of any initial<br />

phase activity. The PQCM will document initial inspections <strong>for</strong> each item using the Initial<br />

Inspection Checklist and attach it to the Daily <strong>CQC</strong> Report. The exact location of the initial<br />

phase inspection will be indicated <strong>for</strong> future reference and comparison with follow-up<br />

inspections.<br />

An initial phase inspection will be conducted each time a new crew arrives on site or any time<br />

acceptable specified quality standards are not being met.<br />

5.3 FOLLOW-UP PHASE INSPECTION<br />

During the completion of a particular DFW, follow-up inspections will be conducted to ensure<br />

continued compliance with contract requirements. The frequency of the follow-up inspections<br />

will depend on the extent of the work being per<strong>for</strong>med on each particular feature. Each followup<br />

inspection will be documented on the Follow-up Inspection Checklist, which will be attached<br />

to the Daily <strong>CQC</strong> Report. A final follow-up check will be conducted on any completed work<br />

phase prior to the commencement of a subsequent phase. Any deficiencies will be corrected<br />

prior to starting additional phases of work or will be identified on a list of items that do not<br />

con<strong>for</strong>m to the specified requirements or are incomplete.<br />

5.4 ADDITIONAL PREPARATORY AND INITIAL PHASES<br />

The PQCM may conduct additional preparatory and initial inspections on the same DFWs under<br />

the following circumstances:<br />

• If the quality of ongoing work is unacceptable as determined by the PQCM, PjM,<br />

RPM, QAO, or ROICC<br />

• If there are substantial changes in the staff, on-site supervision, or work crew<br />

• If work on a DFW is resumed after a substantial period of inactivity<br />

• If other problems develop<br />

• If new tasks arise<br />

5.5 COMPLETION INSPECTION<br />

Completion inspections will be per<strong>for</strong>med as summarized in this section.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.5-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


5.5.1 <strong>Field</strong> Quality Control Completion Inspections<br />

The PQCM or designee will conduct a preliminary inspection prior to the prefinal inspection, when<br />

all of the work or an increment of work is deemed to be substantially complete. The work will be<br />

inspected <strong>for</strong> con<strong>for</strong>mance to plans, specifications, quality, and completeness. The PQCM will<br />

prepare a rework items list of work not properly completed or work that does not con<strong>for</strong>m to plans<br />

and specifications. The list will be included in the QC documentation and submitted to the PjM<br />

following the inspection and will specify an estimated date <strong>for</strong> correction of each deficiency. The<br />

completion inspection will be documented on the Completion Inspection Checklist and attached to<br />

the Daily <strong>CQC</strong> Report.<br />

5.5.2 Prefinal Inspection<br />

The PjM will conduct the prefinal inspection. The RPM, ROICC, PQCM, and other primary<br />

management representative(s), as applicable, will attend. The PjM will schedule the prefinal<br />

inspection in response to notification from the PQCM prior to the planned inspection date. The<br />

PQCM is required to verify at this time that all specific items previously identified as being<br />

unacceptable, along with all remaining project work, will be complete and acceptable by the<br />

scheduled date <strong>for</strong> the prefinal inspection. At this inspection, the ROICC will develop a list of<br />

incomplete and/or unacceptable work per<strong>for</strong>med under the contract and will provide this list to<br />

the TtEC site management team.<br />

5.5.3 <strong>Final</strong> Acceptance Inspection<br />

The PjM will schedule the final acceptance inspection based on notification from the PQCM of<br />

readiness. The RPM, ROICC, PQCM, and other primary management representative(s), as<br />

applicable, will attend. Notification will be provided prior to the planned final acceptance<br />

inspection date and must include verification that all specific items previously identified as being<br />

unacceptable, along with all remaining work per<strong>for</strong>med under the contract, will be complete and<br />

acceptable by the date scheduled <strong>for</strong> the final acceptance inspection.<br />

5.6 INSPECTION DOCUMENTATION<br />

The PQCM is responsible <strong>for</strong> the maintenance of the inspection records. Inspection records will<br />

be legible and clearly provide all necessary in<strong>for</strong>mation to verify that the items or activities<br />

inspected con<strong>for</strong>m to the specified requirements or, in the case of noncon<strong>for</strong>ming conditions,<br />

provide evidence that the conditions were brought into con<strong>for</strong>mance or otherwise accepted by<br />

the ROICC. All inspection records will be made available to the Navy. Inspection <strong>for</strong>ms are<br />

included in Attachment 1.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.5-3 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.5-4 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


6.0 SUBMITTALS<br />

This section describes the review and approval process of submittals. In addition, TtEC will<br />

institute and maintain a submittal register (Table B.6-1) to track submittals from issuance to<br />

approval. A list of required submittals will be developed at the initiation of project activities and<br />

revised as necessary. Submittals will be scheduled, reviewed, certified, and managed in<br />

accordance with the procedures defined in this section.<br />

Standard Unified Facilities Guide Specification (UFGS) Submittal titles are as follows:<br />

• SD-01 Pre-construction Submittals<br />

• SD-02 Shop Drawings<br />

• SD-03 Product Data<br />

• SD-04 Samples<br />

• SD-05 Design Data<br />

• SD-06 Test Reports<br />

• SD-07 Certificate<br />

• SD-08 Manufacturer’s Instructions<br />

• SD-09 Manufacturer’s <strong>Field</strong> Reports<br />

• SD-10 Operation and Maintenance Data<br />

• SD-11 Closeout Submittals<br />

The submittal descriptions are described in Section 1.1.2 of the UFGS 01330 (Naval Facilities<br />

Engineering Command [NAVFAC] 2006). The title list does not infer that they are all applicable<br />

to the Navy’s scope of work <strong>for</strong> this project.<br />

6.1 REVIEW OF SUBMITTALS<br />

Submittals will be reviewed to ensure completeness, accuracy, and contract compliance.<br />

Submittal of a certification will be inspected and approved by the PQCM <strong>for</strong> con<strong>for</strong>mance to the<br />

project specifications or certification criteria. Any submittals requiring modifications or changes<br />

will be returned to the originating organization <strong>for</strong> correction and then resubmitted <strong>for</strong> review<br />

and approval by the PQCM, or designee, prior to acceptance. Approved submittals will be signed<br />

and dated. During the preparatory phase of the QC inspections, the PQCM or designee will<br />

ensure that all materials and equipment have been tested and approved. No field activities will be<br />

per<strong>for</strong>med without the required approval of applicable submittals.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.6-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


6.2 SUBMITTAL PROCESS<br />

Required submittals will be submitted to the Navy and project personnel as determined by the<br />

distribution schedule. Each submittal will have a unique submittal register. All possible attempts<br />

will be made to schedule submittals to allow <strong>for</strong> sufficient review and approval time. However,<br />

certain submittals will require accelerated processing to maintain the schedule.<br />

A transmittal <strong>for</strong>m will accompany each submittal. Each transmittal will be identified with:<br />

• The contract and Contract Task Order (CTO) number<br />

• Name and address of the submitting organization<br />

• Date of submittal<br />

• Description of item being submitted, including reference to specification section (if<br />

applicable)<br />

• Approval of submitting organization indicating con<strong>for</strong>mance to the requirements<br />

The PQCM will update the submittal log regularly.<br />

6.3 REVIEW AND PROCESSING OF SUBMITTALS THAT DO NOT REQUIRE<br />

NAVY APPROVAL<br />

Material submitted <strong>for</strong> review by the PQCM will indicate that it either con<strong>for</strong>ms or does not<br />

con<strong>for</strong>m to established requirements. The PQCM will advise the submitter of the results of the<br />

review. The submittal log will be updated to indicate status.<br />

Noncon<strong>for</strong>ming submittals will be returned to the submitter <strong>for</strong> correction, resolution of<br />

comments, and re-submittal.<br />

6.4 REVIEW AND PROCESSING OF SUBMITTALS THAT REQUIRE NAVY<br />

APPROVAL<br />

Material submitted <strong>for</strong> review by the PQCM will be signed to indicate that it con<strong>for</strong>ms to<br />

requirements.<br />

Submittals reviewed by the PQCM will then be transmitted to the Navy in accordance with the<br />

project distribution schedule <strong>for</strong> review and approval. All items sent to the Navy will use a<br />

transmittal <strong>for</strong>m that will indicate each item transmitted, the date reviewed by the PQCM, and its<br />

review status. Upon completion of review, the ROICC will either return the transmittal <strong>for</strong>m to<br />

the PQCM <strong>for</strong> further action, or accept the submittal as complete.<br />

The PQCM will advise the submitter of the results of the review in writing and include any<br />

comments. The submittal log will be updated to indicate status.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.6-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


Noncon<strong>for</strong>ming submittals may be returned to the submitter <strong>for</strong> correction, resolution of<br />

comments, and resubmittal, if required.<br />

6.5 REVISED SUBMITTALS<br />

Revised submittals will be logged, reviewed, and processed in a manner identical with the initial<br />

submittal.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.6-3 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.6-4 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


7.0 NONCONFORMANCES<br />

The PQCM documents any work or materials not con<strong>for</strong>ming to the technical specifications or<br />

project/contract requirements on a NCR. The NCR will detail the noncon<strong>for</strong>ming condition, the<br />

recommended corrective action(s), and the disposition of the corrective action(s). Qualified<br />

representatives from engineering, QC, and construction will review the NCR and either accept or<br />

reject the recommended corrective action or disposition. The NCR will remain open until the<br />

noncon<strong>for</strong>ming condition has been satisfactorily resolved and verified by QC inspection staff and<br />

the PQCM. Upon receipt of notification of a detected noncon<strong>for</strong>mance, NCRs <strong>for</strong> each item will<br />

be completed.<br />

7.1 IDENTIFICATION OF NONCONFORMING ITEMS<br />

Items identified as noncon<strong>for</strong>ming will be documented. Copies of completed NCRs will be sent<br />

to the ROICC.<br />

7.1.1 Condition Requiring Stop Work<br />

If corrective actions are insufficient, resolution cannot be reached, or results of prior work are<br />

indeterminate, work may be stopped. The PQCM will direct the PjM to suspend work associated<br />

with the noncon<strong>for</strong>mance until correction action is complete. If there is a disagreement between<br />

the PQCM and the PjM, the difference will be brought to the attention of the QCM until<br />

resolution is achieved.<br />

The conditions of the suspension of work will be described in detail on the <strong>CQC</strong> daily report and<br />

on the Rework Items List, if corrective action is not completed by the end of the working day.<br />

Work will not continue until directed by the individual who authorized it.<br />

7.2 DISPOSITION<br />

The disposition of NCRs will include the necessary actions required to bring the noncon<strong>for</strong>ming<br />

condition to an acceptable condition and may include use-as-is, reworking, replacing, retesting,<br />

or reinspecting. Implementation of the disposition may be done in accordance with the original<br />

procedural requirements, a specific instruction, or an FCR.<br />

7.2.1 <strong>Field</strong> Change Requests<br />

Site personnel shall document changes to the approved plans in the field through the FCR <strong>for</strong>m.<br />

At a minimum, the following in<strong>for</strong>mation will be documented in the FCR <strong>for</strong>m:<br />

• <strong>Project</strong> name<br />

• CTO number<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.7-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


• FCR number<br />

• <strong>Documents</strong> to which a change is requested (including revision number if applicable)<br />

• Description of the item or condition <strong>for</strong> which the change is requested<br />

• Reason <strong>for</strong> the change<br />

• Recommended disposition<br />

• Cost and schedule implication of the change, if any<br />

• Approval of disciplines if changes involve risk-sensitive items in that discipline<br />

• Approval of the PjM, Site Superintendent, <strong>Project</strong> Environmental Safety Manager, and<br />

QCM<br />

7.3 CORRECTIVE ACTIONS<br />

On detection of a noncon<strong>for</strong>ming condition, the PQCM will immediately take corrective action.<br />

The procedure <strong>for</strong> identification, analysis, and implementation of the corrective action is<br />

described in TtEC’s Quality Program-12 procedure, Corrective Action.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.7-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


8.0 REFERENCES<br />

FWENC (Foster Wheeler Environmental Corporation). 2002. <strong>Final</strong> First Annual Groundwater<br />

Report <strong>for</strong> WATS and EATS. Includes 1999 and 2000 Data and August 2000 and<br />

November 2000 Quarterly Reports, <strong>Moffett</strong> Federal Airfield, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia.<br />

January.<br />

NAVFAC (Naval Facilities Engineering Command). 2006. Unified Facilities Guide<br />

Specification (UFGS) 01330, Submittal Procedures. January.<br />

USACE (United States Army Corps of Engineers). 2003. Safety and Health Requirements<br />

(EM-385-1-1).<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.8-1 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc B.8-2 Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


TABLES<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


FIGURES<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


ATTACHMENT 1<br />

QUALITY CONTROL FORMS<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009


This page intentionally left blank.<br />

ECSD-3211-0009-0003 Dr<strong>CQC</strong>_PetroSites_AppB.doc<br />

Draft <strong>Project</strong> Contractor Quality Control <strong>Plan</strong><br />

<strong>for</strong> Work <strong>Plan</strong> <strong>for</strong> Petroleum Sites Sampling and<br />

Evaluation <strong>for</strong> Closure or Removal Actions<br />

Former NAS <strong>Moffett</strong> <strong>Field</strong><br />

DCN: ECSD-3211-0009-0003<br />

CTO No. 0009