PHASE 3 INITIAL DESIGN DEVELOPMENT AND HAZARD IDENTIfiCATION – 10%<br />
To develop initial design deliverables to Inter Discipline Review stage and identify key hazards.<br />
ACTIVITIES/DELIVERABLE DESCRIPTION DISCIPLINE SUPPORTING DOCUMENTATION<br />
1 Hazard Identification Perform hazard identification studies, as<br />
identified on <strong>Engineering</strong> Audit Schedule /<br />
Technical Safety Events Schedule.<br />
2 Environmental Issue<br />
(NEPA)<br />
Formal assessment of environmental aspects<br />
associated with a modification or a change, and to<br />
propose prevention or mitigating measures.<br />
3 System and Process<br />
Diagram<br />
Issue System and Process Flow / control<br />
Diagrams on formal Inter-Discipline Review.<br />
4 Plot Plans / Layouts Issue equipment Plot Plans / Layouts on formal<br />
inter-Discipline Review.<br />
5 Equipment List Create master project equipment list identifying<br />
all major items of tagged equipment, ie. vessels,<br />
pumps, motors, generators, chemical injection<br />
packages, electrical switchgear, control panels,<br />
etc.<br />
6 Mechanical Handling<br />
Strategy<br />
Develop Mechanical Handling Strategy including<br />
general approach / constraints, platform crane<br />
limits, installation philosophy, operation and<br />
maintenance, etc.<br />
Technical Safety<br />
Technical Safety<br />
Mechanical and<br />
Electrical<br />
Mechanical and<br />
Electrical<br />
Mechanical and<br />
Structural<br />
Develop or Reference: Environmental<br />
Impact Identification <strong>Engineering</strong> &<br />
<strong>Design</strong> Reviews manual<br />
6 | P a g e