No. 22. THIRTEENTH ANTHRACITE DISTRICT 387<br />

Slush elevator erected south of breaker to give additional height<br />

for slush bank. During the year 20,082 cubic yards of slush were<br />

run into this mine, or 712,410 cubic yards to date.<br />

Kohinoor Colliery.—During the year 60,872 cubic yards of slush<br />

were run into this- mine, or 1,119,100 cubic yards to date.<br />

Gilberton Colliery.—Tunnel to Buck Mountain vein from the West<br />

Seven Foot gangway oft' the new underground slope in Seven Foot<br />

vein 1060 foot level, was completed in March ; length 39 yards.<br />

Single and double track tunnel from foot of underground slope<br />

from Seven Foot vein, north dip. to Seven Foot vein, south dip, was<br />

completed in September ; length 40 yards.<br />

Tunnel to Skidmore vein from the West Ruck Mountain gangway<br />

was completed in July; length 631-3 yards. Tunnel to Little Buck<br />

vein from East Skidmore gangway (932 foot level) off No. 1 slope at<br />

a point 160 feet east of No. 1 slope, was completed in May; length<br />

64 2-3 yards.<br />

Draper Colliery.—Tunnel from Leader gangway to Skidmore vein<br />

second lift, was completed in March ; length 26 yards.<br />

Three rail rock plane from second lift tunnel to Little Tracey vein,<br />

was completed in July; length 26 yards.<br />

Knickerbocker Colliery.—Tunnel to Buck Mountain vein, south dip<br />

tunnel from Buck Mountain underground slope, West Seven Foot<br />

gangway, north dip, near Breast No. 20. was completed; total length<br />

70 2-3 yards.<br />

Boston Bun Colliery.—A rock hole for air on 15 degree pitch to<br />

stump heading in Buck Mountain vein, from East Little Buck fourth<br />

lift, 115 feet east of pumproom, was completed; total length 15|<br />

yards.<br />

A tunnel on shaft level to tender slope in Little Buck vein, for<br />

timberway and men, was completed; total length 64 1-3 yards.<br />

A rock hole on 45 degree pitch to Little Tracey vein from West<br />

Tracey gangway second lift at Breast No. 2, was completed; total<br />

length 21 1-3 yards.<br />

THOMAS COLLIERY COMPANY<br />

Kehley Bun "Colliery.—New supply plane hoisting engine was installed<br />

and engine house erected. New conveyor line to take in culm<br />

bank on west side of breaker was partially installed.<br />

Black Creek Washery.—This is a new operation. During the year<br />

a new breaker with a capacity of 1000 tons daily was erected, and in<br />

it were installed 12 new jigs, together with shakers and other necessary<br />

machinery. Boiler house was erected containing five 150 horse<br />

power locomotive type boilers. Installed 5 locomotives—three 20-ton,<br />

one 18-ton and one 12-ton.<br />

Installed 3 steam shovels—two 45-ton and one 70-ton.<br />

Installed one breaker wash pump, capacity 1000 gallons per minute.<br />

LOCUST MOUNTAIN COAL COMPANY<br />

Weston Colliery. Inside: Installed two 8-ton electric locomotives,<br />

armor plate type, General Electric Company's construction, 36-inch<br />

gauge. The plane to the counter level of the Little Buck Mountain<br />

vein for the purpose of handling the coal from the counter, has been