PATHFINDER1 19 912030 0 ES5TLSTX312141417. In the diagram above, what is the value <strong>of</strong> the earliest starting time X?A. 12B. 14C. 16D. 21E. 28ABCD18. Which <strong>of</strong> the following is correct in relation to Part <strong>of</strong> Activity-on-Arrow Networkdiagram shown above?A. A and C must finish before B can startB. A and C must finish before D can startC. A only must finish before D can startD. C only must finish before B can startE. C only must finish before D can startINTERMEDIATE EXAMINATION - NOVEMBER 20108