2007 Mine Development‣ Utilizing Henderson Personnel for Key Work:• Drawpoint Mining - 5,500 LF• Concrete - 20,000 CY for150 Drawpoints• Shotcrete - 9,000 CY• Ring-drilling – 435,000 LF• Caving – 140 Drawpoints‣ Utilizing Contractors:• Mining -18,000 LF• Chute Construction – 4 each12