12.07.2015 Views

The Assessment of Applications for Extension of Time Claims ... - IJET

The Assessment of Applications for Extension of Time Claims ... - IJET

The Assessment of Applications for Extension of Time Claims ... - IJET

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

IACSIT International Journal <strong>of</strong> Engineering and Technology, Vol. 4, No. 4, August 2012TABLE III: REASONS FOR DELAYS IN SUBMITTING THE DETAILS OF CLAIMSFOR EXTENSION OF TIMEReasons <strong>of</strong> delaysSite staff inexperienced in contractprocedures and task undertaken by head<strong>of</strong>fice expert who needs time to understandclaim situationIf the claim is related to inclement weatherusually prompt action is takenMeanMean ScoreM’sia’sRank3.31 1 93.25 2 9Engineer requests excessive details 3.19 3 9Poor paperwork control by the contractor 3.17 4 6Contractor wants to know exactly theamount <strong>of</strong> extension <strong>of</strong> time required suchthat their risk to liquidated damages can be3.17 4 6removedPolicy to submit global claims can causedelayed submissions3.14 6 9Lack <strong>of</strong> contractor's management resources 3.06 7 3Overall delay cannot be ascertained/actualdelay could not be determined until end <strong>of</strong> 3.03 8 1delay or constructionGeneral lack <strong>of</strong> details 3.00 9 3Benefit <strong>of</strong> hindsight (choose events thatattracts money)2.89 10 9<strong>The</strong> effects are not known/could not <strong>for</strong>eseethat an event would cause a delay until the 2.67 11 5delay occurredFocus on progress <strong>of</strong> work and not onclaim/contractor's staff too busy on othertasks/lack <strong>of</strong> staff (in contractor's2.58 12 2organisation) to deal with EOT claimsContractor does not want to cause frictionor <strong>of</strong>fend the employer2.50 13 6HK’sRankChange order by consultants was rated as the main reasonused to claim <strong>for</strong> EOT. Late issuance <strong>of</strong> constructiondrawing and material shortage at project site were rated assecond and third reasons used. In Malaysian’s constructionindustry, change order is very common. Wheneverinstruction <strong>for</strong> change order is issued, contractors will need tomake necessary adjustment to the original scheduled workoperation. This will certainly affect the planned finish date <strong>of</strong>the project.Most <strong>of</strong> the time, construction drawings are based onpreliminary design and this design is usually based onprevious design experience and seldom include the crucialanalysis or referred to the actual environment <strong>of</strong> the proposedsite. During construction period, actual environmentconstraints will arise and raise ought to modify the design.This will create variation order and also additional works.Thus, late issuance <strong>of</strong> construction drawing was identified asone <strong>of</strong> the famous reason <strong>for</strong> EOT.<strong>The</strong> respondents were also asked to identify the commontechniques used in assessment <strong>of</strong> claims <strong>for</strong> EOT. It wasfound that contractors prefer <strong>Time</strong> Impact technique, whilethe consulting engineers <strong>of</strong>ten apply Net Impact Technique.<strong>The</strong> difference in technique applied may cause argumentbetween the contractors and consulting engineers in the issue<strong>of</strong> duration <strong>of</strong> EOT.<strong>The</strong> respondents have also been requested to suggest somealternatives solution besides granted the EOT. Developerssuggested that contractors shall be provided incentive <strong>for</strong>their timely completion. Whilst from the viewpoint <strong>of</strong>consultants, they also agreed to compensate time with moneyvalue through acceleration claim. Meanwhile contractors alsosuggested that EOT should be priced into the contract be<strong>for</strong>esubmission <strong>of</strong> a tender; there<strong>for</strong>e the loss can be taken care <strong>of</strong>if delay occurs.TABLE IV: REASONS USED TO CLAIM FOR EXTENSION OF TIReasons UsedMean ScoreChange order by consultants causing project delay 4.44Late issuance <strong>of</strong> construction drawing 4.19Material shortage at project site 3.97Incapability <strong>of</strong> contractor’s site management toorganise site activitiesLate issuance <strong>of</strong> progress payment by client tocontractor Material shortage at project siteNon-payment (financial problem) to supplierscausing the stoppage <strong>of</strong> material delivery to site3.863.813.72Late supply <strong>of</strong> materials in the market 3.58Lack <strong>of</strong> <strong>for</strong>eign and local workers in the market 3.50Coordination problem with subcontractor 3.14Equipment shortage 3.03TABLE V: PREFERRED TECHNIQUE USED IN ASSESSING CLAIMS FOREXTENSION OF TIMERepresentingGlobal ImpactNet ImpactMean ScoreAdjustedas-built CPMDeveloper 3.67 3.33 3.67 3.00 3.67 3.33Consultant 3.83 4.17 3.50 3.17 3.83 3.22Contractor 3.75 3.50 3.75 3.27 3.92 3.58Total 3.79 3.85 3.61 3.15 3.85 3.36VI. CONCLUSIONA study that investigated on the assessment <strong>of</strong> contractualclaims <strong>for</strong> EOT in construction industry in Malaysia has beenconducted. <strong>The</strong> findings <strong>of</strong> this study providerecommendations that may help in minimizing the delays insubmissions and assessment <strong>of</strong> EOT. It is recommended thateach construction organization should develop its ownpolicies, strategies and procedures to expedite an efficientand reliable EOT substantiation and evaluation. <strong>The</strong>following are the conclusions that may answer the objectives<strong>of</strong> this study:1. EOT is one <strong>of</strong> the provision clauses in the standardcontract <strong>for</strong>m. <strong>The</strong> purpose is to preserve an employer’s rightin liquidated damages. In the circumstances that the delaysare caused by inevitable reason, EOT allows contractor to setan agreed completion date.2. <strong>The</strong> most common reason used to claim <strong>for</strong> EOT ischange order by consultants causing project delay. <strong>The</strong>reasons <strong>for</strong> delay in substantial and assessment the extension<strong>of</strong> time is the inexperienced in contract procedures <strong>of</strong> the sitestaff and the head <strong>of</strong>fice expert will need time to understandthe claim situation when the task is undertaken by head <strong>of</strong>ficeand delays in submissions <strong>of</strong> details by the claimant; lack <strong>of</strong>in<strong>for</strong>mation and clarity in substantiation respectively.3. <strong>Time</strong> Impact technique is the most preferable techniqueBut <strong>for</strong><strong>Time</strong> ImpactSnapshot449

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!