12.07.2015 Views

F. Bertinelli, presentation 25-May-09 - CERN TE-MSC-CMI

F. Bertinelli, presentation 25-May-09 - CERN TE-MSC-CMI

F. Bertinelli, presentation 25-May-09 - CERN TE-MSC-CMI

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Impact on W closing and VACSEC testing• 1-2: IC closed >90%, 3/14 VACSECstesting• 5-6: IC closed >90%, 12/14 VACSECstested but some reopened• 6-7: IC closed >75%, 2/14 VACSECstested• 3-4: IC closed >15%, now closing inL4, no VACSECs tested• W Teams working on reopenings(for R16 and for plastic shimmings in6-7) and thermal screen repairsCourtesy A. Grimaud, P. Cruikshank, J.P. Tock<strong>25</strong> <strong>May</strong>, 20<strong>09</strong> MMM and <strong>TE</strong>MB - Francesco <strong>Bertinelli</strong> 8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!