Section V Custodial Services<br />
13<br />
<strong>US</strong>AG <strong>Kaiserslautern</strong> DPW Customer Guide<br />
2-9. How to Request Custodial Services. Customers desiring to have their facilities cleaned through a DPW<br />
custodial services contract must submit a memorandum signed by the unit commander, with a floor plan attached.<br />
Requests for custodial services must reach the DPW NLT 90 calendar days prior to the first of the month when<br />
services are required (e.g., NLT 2 April for services to begin 1 July).<br />
2-10. Reimbursement. Customers will reimburse the DPW for custodial services when required by support<br />
agreement and/or for services exceeding approved IMCOM-level support standards.<br />
2-11. DPW Support. The DPW will:<br />
a. Review customer requests for custodial services.<br />
b. Identify areas authorized to receive DPW custodial services as established in the IMCOM approved<br />
standards.<br />
c. Post summaries of services provided and schedules for performance of these services in a conspicuous place<br />
in all male and female latrine areas of each serviced facility.<br />
d. Coordinate any special cleaning, where authorized, with the COR/building manager.<br />
e. Ensure contractor compliance with contract specifications through regular inspections.<br />
2-12. Customer Complaint Procedure. Customers may contact the contractor in case of complaints concerning<br />
custodial service. The contractor is required to respond to customer complaints and perform corrective action. The<br />
custodial contractor can be reached by email to army-contact@standard-jacobs.de or by telephone DSN 483-6206.<br />
Always send a courtesy copy to the DPW Quality Assurance Branch custodial service POC at #DLWKL-Custodial-<br />
QAE@eur.army.mil, telephone DSN 483-8806/8727/7542/8243 or for Pirmasens DSN 495-7322.<br />
Section V Digging Permits<br />
2-13. General. The DPW issues digging permits to minimize damage to underground utility lines. Customers or<br />
contractors must obtain a digging permit prior to the start of any excavation within the community.<br />
2-14. How to Request a Digging Permit. Digging permits should be requested for all ground penetrations<br />
(digging, trenching, grounding rods, mission exercises, etc.) exceeding a depth of 30 cm (11.8 inches). At the<br />
Landstuhl Heliport/SATCOM, this depth is reduced to 15 cm (6.0 inches). Customers or contractors desiring to<br />
excavate within the community should request a digging permit by submitting a memorandum to the <strong>US</strong>AG<br />
<strong>Kaiserslautern</strong> DPW, Engineering Division, Unit 23152, APO AE 09227. Failure to procure a digging permit will<br />
obligate responsibility to the digging party/organization for all damages incurred.<br />
2-15. DPW Support. The DPW will:<br />
a. Issue a digging permit.<br />
b. Provide maps identifying all known underground utility systems in the area of excavation.<br />
Section VI Duplication of Keys<br />
2-16. General. The DPW duplicates keys for <strong>US</strong> <strong>Army</strong> facilities in the community. Types of keys normally used<br />
in the community include:<br />
a. Master Keys. Duplication of master keys may require up to 60 days. Master keys may only be duplicated<br />
when the Master Key Card is submitted with the request. Master Key Cards are filed in the DPW Real Property<br />
Section.