215.3 Customers may operate generation equipment in parallel with the Company<br />

distribution system under specific terms and conditions as established in the latest<br />

revision of <strong>CenterPoint</strong> <strong>Energy</strong> specification 007-231-76.<br />

215.4 Before Customer-owned generating equipment may be interconnected to the<br />

Company system, application must be made and approved. (See <strong>CenterPoint</strong><br />

<strong>Energy</strong> specification 007-231-76.) For more information, contact the <strong>Service</strong><br />

Consultant at the nearest Company Office. (See page 3)<br />

215.5 Customers may not install or use any transfer switch on the high side (<strong>CenterPoint</strong><br />

<strong>Energy</strong> side) of the meter or any transfer switch between the meter and the meter<br />

socket jaws.<br />

215.6 Customer owned standby generators that are to be permanently installed, must be<br />

located on the load side (customer side) of the meter, behind the main breaker<br />

(switch) and must have a transfer switch installed that prevents tying the running<br />

generator into the <strong>CenterPoint</strong> <strong>Energy</strong> system, whether the CNP lines are hot or<br />

dead.<br />

216 Electrified Fences<br />

Use of the Company's electric service to energize fencing or to energize devices<br />

which simultaneously energize fencing is prohibited.<br />