12.07.2015 Views

Holford Underground Gas Storage - from FEED to handover - Axc.Nl

Holford Underground Gas Storage - from FEED to handover - Axc.Nl

Holford Underground Gas Storage - from FEED to handover - Axc.Nl

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Holford</strong> <strong>Underground</strong> <strong>Gas</strong> <strong>S<strong>to</strong>rage</strong> -<strong>from</strong> <strong>FEED</strong> <strong>to</strong> <strong>handover</strong>Mike HealyGlobal <strong>Gas</strong> Village 6-8 th June 2012Costain Energy & ProcessCostain Energy & Processwww.costain.com


<strong>Holford</strong> <strong>Underground</strong> <strong>Gas</strong> <strong>S<strong>to</strong>rage</strong>This paper covers the involvement of Costain Energy andProcess during the engineering, procurement and constructionmanagement stage of the gas compression station project,moving the <strong>FEED</strong> in<strong>to</strong> an operational facility.• Project Outline• Project Challenges• ‘Novel’ Equipment• Cost Saving• CommissioningCostain Energy & Processwww.costain.com


The Project• <strong>S<strong>to</strong>rage</strong> Volume• Peak Import Flow• Peak Export Flow• Number of Caverns 8• Cavern Pressures• NTS pressure• Turndown 10:1• Start up times160 million m3833,334 Sm3/h916,667 Sm3/h45 <strong>to</strong> 100 bar40 <strong>to</strong> 70 bar(From zero <strong>to</strong> peak flow)30 minutes for injection and for withdrawal <strong>from</strong> hotstandby90 minutes for cold withdrawal <strong>from</strong> cold standby• Turnround From withdrawal <strong>to</strong> injection 30 minutesFrom injection <strong>to</strong> withdrawal90 minutesCostain Energy & Processwww.costain.com


Project OverviewExisting IneosBrinefieldsKing Street Energyproject (Awaiting FID)S<strong>to</strong>rengy Stublachproject (In Construction)<strong>Holford</strong> projectCostain Energy & Processwww.costain.com


Project TimelineCostain Energy & Processwww.costain.com


Cheshire SaltCostain Energy & Processwww.costain.com


The National <strong>Gas</strong> Network• Located 4.5 km <strong>from</strong> the <strong>Gas</strong>Processing Plant• Operates between 40 and 70 bar• Ties in<strong>to</strong> the same 1050mm lineas the S<strong>to</strong>rengy Stublach project• Cavern depth allow the s<strong>to</strong>rage <strong>to</strong>be operated between 45 and 100bar which makes some gastransfer between the caverns andthe High Pressure <strong>Gas</strong> Networkpossible without compression andvisa versa.Costain Energy & Processwww.costain.com


Process Considerations• <strong>Gas</strong> Network Pressure 40 <strong>to</strong> 70 bar• Cavern <strong>S<strong>to</strong>rage</strong> Pressure 45 <strong>to</strong> 100 barOperating Configuration• Free flow <strong>from</strong> the Network <strong>to</strong> thecaverns and visa versa• Compressed flow <strong>from</strong> theNetwork <strong>to</strong> the caverns and visaversa• ‘Normal’ operation is <strong>to</strong> compressin<strong>to</strong> the caverns, free flow in<strong>to</strong> theNetwork initially, then support withcompressionCostain Energy & Processwww.costain.com


Operational AdvantagesProcess Considerations• The <strong>Holford</strong> caverns are lowpressure caverns (< 100 bar)• Caverns on the NE coast of theUK operate at high pressure(> 200 bar)• High pressure caverns can s<strong>to</strong>relarger quantities of gas, but costmore <strong>to</strong> operate.• Operating costs per churnare approximately 75%.Energy S<strong>to</strong>reThe advantages are more markedwhen using low pressure caverns <strong>to</strong>back up wind power.Costain Energy & Processwww.costain.com


Process Considerations• The above ground processing is straightforward• <strong>Gas</strong> dehydrationSolid dessicant, such as Silica Gel or Molecular SieveGlycolComparisons completed on cost, operation and emissions• <strong>Gas</strong> CompressionDriver (<strong>Gas</strong> or Mo<strong>to</strong>r)Speed ControlDuty pointDebrining• Hydrate InhibitionGlycolMethanolCostain Energy & Processwww.costain.com


<strong>Gas</strong> DryingGlycol was chosen as the drying technology• Originally permitted with Silica Gel technology• Changed <strong>to</strong> Glycol during the <strong>FEED</strong>• Designed such that it could be considered asBATThermal Oxidiser included <strong>to</strong> destroyorganic emissions.Unit does not need <strong>to</strong> be kept hot <strong>to</strong> allowfast online response.• Buffer s<strong>to</strong>rage <strong>to</strong> allow unit <strong>to</strong> operate before thereboiler is up <strong>to</strong> operating temperature• Standard packaged units•Features <strong>to</strong> keep the height as low as practicallypossibleCostain Energy & Processwww.costain.com


CompressionMan Turbo HOFIMs were selected• The compressors were selected and purchased after the<strong>FEED</strong>• Variable Frequency Drive• <strong>Gas</strong> cooled magneticbearings• Series wheels <strong>to</strong> increasehead• No seals so no emissions• Process duty selected <strong>to</strong>match compressor capacity• Good capability for repeats<strong>to</strong>p/start and turnaroundCostain Energy & Processwww.costain.com


Base Control SystemControl System• Normal DCS based control system• Opera<strong>to</strong>r based, control loops and sequences• Opera<strong>to</strong>r selects caverns <strong>to</strong> be traded• EDP and ESD• Fire & <strong>Gas</strong>Trading Functionality• Fully au<strong>to</strong>mated, capable of being operated by a ‘gas trader’• Spreadsheet Control• Unmanned operation (initial intent by gas trader)• Opera<strong>to</strong>r inputs nominationCostain Energy & Processwww.costain.com


TradingEnergy Balancing•Control system• Selects required mode• Selects required number of trains• Lines plant up (equalisation)• Starts plant up (at required time)• Shuts plant down• Responds <strong>to</strong> equipment failure• Responds <strong>to</strong> changing pressure drops• Starts and S<strong>to</strong>ps Compressors• Responds <strong>to</strong> shortfalls in throughputCostain Energy & Processwww.costain.com


Vent Design• Visual impact limits vent <strong>to</strong>15m• Plot area limits sterile area <strong>to</strong> 50m radius• No continuous venting/purging, hence no flare required• All Relief Valves go <strong>to</strong> atmosphere• No closed drains system• No fire water system• Venting limited <strong>to</strong>:Depressurisation (EDP)Maintenance Venting• EDP in plant sectionsCostain Energy & Processwww.costain.com


Pipeline Liquids Management• Hydraulic simulations (Olga) forecast a potential 150m 3 liquidsdisplaced on start up.• With intermittent operation and potential variation in cavernoperating temperatures and gas moisture content, could a largeexpensive slug catcher be justified?• Inlet Separa<strong>to</strong>r liquid capacityincreased• Slug Catcher deleted• Liquid drainage rate increased• Large low pressure ProducedWater Tank• Ramp Rate limited at low flowCostain Energy & Processwww.costain.com


Commissioning• Water is present during construction.Must be removed <strong>to</strong> meet the NTS specification on thedry side of the plant (-10 0 C)sideCostain Energy & ProcessMust be removed <strong>to</strong> prevent hydrates on the cavern•More attention needed during the design with identification oflow points, especially where there is extensive undergroundpiping• Noise• FAT• Pipework• Check Valves• Compressor TestConditions• Acoustic Enclosure Testwww.costain.com


NoiseLimits given in the Planning Permission• Rural location• M6 background noise• Absolute guarantee• Approach <strong>to</strong> prove by calculation• Generate model based on typical noise levels• Impose noise levels on vendors• Update model with any deviations• Prove on site by readings (plant on and off)Costain Energy & Processwww.costain.com


Environment• The plant is located away <strong>from</strong> the wellsites and the NTS on abrownfield site• The site was previously Cranage Airfield with shelter and thepotential for old munitions• There were the usual wildlifeconcerns such as newts, batsand badgers• Water discharge was <strong>to</strong> a smallbrook and had <strong>to</strong> be buffered andneeded continual glycol analysis• Visual Impact was important withequipment limited <strong>to</strong> 10m andextensive screening• Double skinned tanks, no bunds and leak detection.Costain Energy & Processwww.costain.com


Contract FormEPCm+• The <strong>FEED</strong> was supplied ‘for information only’• Key document was ‘Employer’s Requirements’• Minimal ‘Warranted Information’• One absolute guarantee – Noise• One economic guarantee – Import and Export Flows• A number of plant performance targets and demonstrations• A reliability test• Equipment supply was a change <strong>to</strong> the contract with each orderlet with different levels of responsibility for E.ON and Costain• Supply Chain, Best of Costain, E.ON UK and E.ON RuhrgasCostain Energy & Processwww.costain.com


Team Working• Costain experience on dehydration, compression and UK gasplant design, procurement and construction, located less than20km <strong>from</strong> the site• Costain enhanced their underground experience by use of aconsultant• E.ON experience of multiplefacilities in Germany• Fully integrated team locatedin Manchester• Due <strong>to</strong> location the team couldrelocate <strong>to</strong> site.Costain Energy & Processwww.costain.com


Awards• RoSPA Gold Awards in 2009, 2010 & 2011• RoSPA Silver in 2012• 750,000 man-hours worked• The project has received industry-wide recognition, being HighlyCommended in the Chemical Engineering Project of the Yearcategory at the IChemE Awards for Innovation and Excellence inNovember 2011.Costain Energy & Processwww.costain.com


<strong>Holford</strong> <strong>Underground</strong> <strong>Gas</strong> <strong>S<strong>to</strong>rage</strong> -<strong>from</strong> <strong>FEED</strong> <strong>to</strong> <strong>handover</strong>Mike HealyGlobal <strong>Gas</strong> Village 6-8 th June 2012Costain Energy & ProcessCostain Energy & Processwww.costain.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!