13.07.2015 Views

Manby H1L15 Breaker Incident - July 5, 2010 - IESO

Manby H1L15 Breaker Incident - July 5, 2010 - IESO

Manby H1L15 Breaker Incident - July 5, 2010 - IESO

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Manby</strong> <strong>H1L15</strong> <strong>Breaker</strong> <strong>Incident</strong> - <strong>July</strong> 5, <strong>2010</strong>1. Synopsis1. Synopsis♦ Extreme Event (Category D) 1 : a phase-to-ground fault causing a 230 kV breaker tofail explosively, triggering five subsequent faults and removing an entire 230 to 115kV transformer station from service.♦ Duration: 3.6 seconds from the beginning of the first fault to the end of the last.Clearance times ranged from 64 to 89 milliseconds while fault magnitudes rangedfrom 22 to 42 kilo-amps (kA).♦ Root Cause: internal failure of the breaker♦ Impact on Generation: no generation loss was linked to the event, however severalgenerating stations reported noticeable swings to their terminal voltages in responseto the faults.♦ Impact on Load: approximately 1550 MW of load was interrupted, 902 MW ofwhich was removed from service by configuration. The remaining 648 MW wastriggered by the operation of customer-owned under-voltage protection withinsurrounding local distribution centres.♦ Impact on Tie lines: Michigan and New York experienced flow increases of 725MW and 690 MW from Ontario respectively. Flows were well within interfacecapabilities and were restored to pre-contingency levels within 12 minutes.♦ Impact on other Reliability Coordinator Areas: MISO and NYISO reported noadverse impact to their systems.- End of Section -1 As defined by NERC Standard TPL-004-0: an extreme event resulting in two or more (multiple) elementsremoved or cascading out of service.October 20, <strong>2010</strong> Public 5

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!