METROPOLITAN COUNCIL MEETING<br />
October 14, 2015 Page 20<br />
E. VOLUNTEER FIRE DEPARTMENT FIRE DISTRICT #8 - PRIDE<br />
Consideration <strong>of</strong> reappointing or replacing Debra Ballard, whose term<br />
expires on November 26, 2015, effective November 27, 2015. This is a<br />
two (2) year term.<br />
Current Ballot:<br />
Thomas Cobb<br />
Pierre Rizan<br />
Wesley Tucker<br />
(Sent letter requesting reappointment)<br />
(Sent letter requesting reappointment)<br />
APPOINTED THOMAS COBB<br />
F. CAPITAL AREA HUMAN SERVICES DISTRICT (CAHSD):<br />
Concurring in the names submitted by the CAHSD for submission to the<br />
Governor to consider for appointment to the CAHSD. Two vacancies exist<br />
requiring the submission <strong>of</strong> 4 names. The names submitted by the<br />
CAHSD are: Thomas Sawyer, Virginia Pearson, Deborah Dominick<br />
and Gay Johannessen to replace Denise Dugas and Stephanie Manson.<br />
(Names are submitted to the Metro-Council from the CAHSD to be<br />
forwarded to Governor for appointment).<br />
ADOPTED MOTION TO FORWARDED THE NAMES SUBMITTED FROM THE<br />
CAHSD TO THE GOVERNOR FOR APPOINTMENT<br />
13. ITEMS:<br />
A. CHANGE ORDERS:<br />
1. Project Title: Standby Generator<br />
Installations for Sewer Lift<br />
Stations<br />
Project Number:<br />
09-PS-BD-0037<br />
Original Estimated Cost: $10,400,000.00<br />
Purchase Order Number:<br />
PO110562<br />
Account Number: 433.7578663.752400.6087340<br />
Council Award Date: February 9, 2011<br />
Contractor:<br />
Grady Crawford Construction<br />
Change Order Number:<br />
Co., Inc.<br />
3 (three) (extend the contract<br />
for 237 days)<br />
Change Order Amount: $ 684,499.52<br />
Original Contract Amount: $7,180,546.06<br />
Net Previous Changes: $ 740,480.54<br />
New Contract Amount: $8,605,526.12<br />
Description:<br />
Why Required:<br />
RESOLUTION 51763 & EBROSCO 8149<br />
Increase generator size at<br />
pump stations including<br />
automatic transfer switches.<br />
Also includes modifications to<br />
the concrete pad, conduit and<br />
conductor size, and additional<br />
conduit and wire.<br />
To increase generator size at<br />
multiple locations, including<br />
automatic transfer switches