Task<br />
Indicative Timeframe<br />
Agree base line services with CBC and <strong>Nov</strong>ember <strong>2015</strong> – January 2016<br />
LCC<br />
Initial <strong>Business</strong> consultation <strong>Nov</strong>ember <strong>2015</strong> – January 2016<br />
CBC to prepare BID data base January 2016<br />
Consult businesses on the BID area, Levy January 2016 – February 2016<br />
and BID<br />
Production of BID Proposal February 2016 – March 2016<br />
Production of BID <strong>Business</strong> Plan February 2016 – March 2016<br />
Recommendation to <strong>Cab</strong>inet May 2016<br />
Supply data base to BID May 2016<br />
Develop Operating Agreement May 2016 – June 2016<br />
Production of printed BID Proposal May 2016 – June 2016<br />
business plan and campaign material<br />
Notify ERS of ballot date and May 2016<br />
arrangements<br />
Notify Secretory of State and LA of May 2016<br />
intention to hold ballot<br />
Distribute BID proposal and business plan June 2016<br />
Campaign period June 2016 – August 2016<br />
Publish notice of ballot August 2016<br />
Send out ballot papers August 2016<br />
Ballot period August 2016 – September 2016<br />
Day of ballot September - 16.9.2016<br />
Ballot holder publish results September - 21.9.2016<br />
Bid notifies all businesses 3 days of ballot September - 21.9.2016 – 23.9.2016<br />
results<br />
Further <strong>Cab</strong>inet reports will be submitted at appropriate dates during 2016 that will<br />
set out and seek approval of the proposal and business plan and agree the Council<br />
vote arrangements and levy payment.<br />
Report Implications<br />
The following implications have been identified for this report.<br />
Financial Implications<br />
The cost to the Council to support the BID ballot consultation process including<br />
printing and publishing the BID Proposal and <strong>Business</strong> Plan and delivery of the ballot<br />
has been estimated at £30,000. It is proposed to resource this through the use of the<br />
reinvestment reserve as it relates to a one off cost. The use of this reserve requires<br />
<strong>Cab</strong>inet Member approval and it is recommended in this report that Members<br />
approve this request.<br />
Any future financial implications arising as a result of the outcome of the consultation<br />
will be subject to a further report to <strong>Cab</strong>inet.<br />