06.12.2015 Views

Consulting

1ONEN5f

1ONEN5f

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

According to the IAEA-PRIS database, Russia has nine reactors under construction, second only to<br />

China. Two of these are “floating reactors” (Akademik Lomonosov-1 and -2), which are nominally<br />

32 MWe each. These were ordered in February 2009 and were expected to be delivered to the<br />

customer at the end of 2012. 740 The latest official start-up date is said to be 6 September 2016, 741<br />

although other reports suggest the vessels will be launched only in 2019. 742 Critics of the project<br />

point out that the risk of accidents on a floating nuclear plant is greatly increased because they<br />

are even more susceptible to the elements, subject to threats of piracy, and if deployed widely will<br />

increase the risks of nuclear material proliferation. 743<br />

Figure 35: Age Distribution of Russian Reactor Fleet<br />

Sources: IAEA-PRIS, MSC, 2015<br />

Construction started at the Baltic-1 unit, a 1109 MW VVER-491 reactor, in February 2012.<br />

However, construction was suspended in June 2013 for a variety of reasons, including recognition<br />

of the limited market for the electricity. Despite no indication that construction will restart in<br />

2015, the project remains “under construction” in IAEA statistics. However, given the ongoing<br />

problems in electricity markets with low market prices and sluggish demand, there is little<br />

incentive for construction to restart.<br />

Commissioning work is said to be continuing at the Beloyarsk-4 fast breeder reactor that was<br />

expected to be completed in 2014. Construction of the 880 MW unit began initially in 1986 but<br />

was subsequently suspended and then restarted in July 2006. Fuel was said to be being loaded<br />

into the reactor in June 2014 744 , and according to Rosatom, Beloyarsk-4 is expected to reach full<br />

power in the second half of 2015 745 . Two VVER-1200 MW units are being built at the Leningrad<br />

nuclear power plant near St. Petersburg, where construction started in 2008 and 2010. At the<br />

740 NEI, “KLT-40S nuclear barge project still afloat”, 9 March 2010.<br />

741 WNN, “Reactors installed on floating plant”, 1 October 2013.<br />

742 U.S.EIA, “Russia”, 12 March 2014, see http://www.eia.gov/countries/cab.cfm?fips=RS, accessed 12 May 2015.<br />

743 NTI, “Floating nuclear reactors could fall prey to terrorist, experts say”, Global Security Newswire,<br />

13 August 2010, see http://www.nti.org/gsn/article/floating-nuclear-reactors-could-fall-prey-to-terroristsexperts-say/,<br />

accessed 12 May 2015.<br />

744 WNN, “Rosatom targets growth”, 3 June 2014.<br />

745 Rosatom, “Russia expects to ramp up to full power unit 4 of Beloyarsk NPP in the second half of 2015”,<br />

3 March 2015, see<br />

http://www.rosatom.ru/en/presscentre/nuclear_industry/faacab004781fc808116f36578d50f5d, accessed<br />

25 June 2015.<br />

Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 166

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!