Consulting
1ONEN5f
1ONEN5f
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
shortage of skilled labor; quality control issues; supply chain issues; poor planning either by the<br />
utility or equipment suppliers; shortage of finance; and public opposition.<br />
The role of public opposition in delaying construction is frequently overstated and there is no<br />
evidence that construction of any of the Generation III+ plants has been delayed by public<br />
opposition. At least in the U.S., this reflects the nuclear industry’s successful efforts to restrict<br />
meaningful public access to judicial or regulatory proceedings and to rule that unresolved safety<br />
issues cannot be raised. While obtaining finance is clearly now one of the major hurdles to<br />
building new nuclear plants, this is much more likely to occur before construction starts. Again,<br />
there is no evidence that shortage of finance has delayed construction apart from the plants under<br />
construction in Russia. The Fukushima disaster did delay ordering in some markets, for example<br />
China, but there is no evidence that any of the delays at the Generation III+ plants resulted<br />
directly from lessons drawn of the catastrophe in Japan.<br />
<br />
A frequent problem has been that detailed design is worked out by the vendor only during<br />
construction. If producing the final detailed design proves difficult, for example, or if the regulator<br />
is not satisfied with the detailed design, this can delay construction. A notable example of this was<br />
the Instrumentation & Control (I&C) System for the EPR. In 2009, the safety regulatory<br />
authorities for Finland, France, and the UK issued a joint statement expressing concern about the<br />
adequacy of the safety systems (those used to maintain control of the plant if it goes outside<br />
normal conditions), and their independence from the control systems. 159 This was eventually<br />
resolved in all three countries but with a different solution for each and only after up to five years<br />
of effort to produce designs that would satisfy the national regulator.<br />
Delays can also be caused by designs that meet regulatory requirements but do not function as<br />
specified. A particular example has been the reactor coolant pumps (RCPs) for the AP1000 to be<br />
supplied by Curtiss-Wright. Curtiss-Wright acknowledged that it “failed to meet deadlines for<br />
shipping RCPs from the U.S. to AP1000 plant sites in China and that it had to ship pumps back<br />
from the Sanmen and Haiyang sites in China for modification.” 160<br />
<br />
The low ordering rate for new nuclear power plants over the past 30 years has meant that there<br />
has been little demand for skilled construction workers, so the workforce has aged and its skills<br />
have not been utilized. Re-building a skilled workforce cannot be done quickly, requiring basic<br />
education as well as experience. Until the flow of orders is more established and the job prospects<br />
secure, the incentives for workers to undergo such training will be weak. For both the first orders<br />
for EPRs, the pouring of the concrete base-mat had to be re-done because of errors. Particularly<br />
for France, where EDF, the owner and site engineer had already built 58 PWRs, it seems<br />
reasonable to assume this was due to loss of expertise at diverse levels of craft labor and<br />
management. This is not surprising, since the French vendor’s last construction start before<br />
159 Health and Safety Executive’s Nuclear Directorate (HSE’s ND), French Nuclear Regulator (ASN) and<br />
Finnish Radiation and Nuclear Safety Regulator (STUK), “Joint Regulatory Position Statement on the EPR<br />
Pressurised Water Reactor—Release No V4 22/10/2009”, 2 November 2009, see<br />
http://www.hse.gov.uk/press/2009/hse221009.htm, accessed 21 May 2015.<br />
160 NW, “AP1000 reactor pump issue brings plant design change: Westinghouse”, 6 November 2014.<br />
Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 59