Test4Direct provides latest PDF questions of Cisco 350-080 exam. You have an opportunity to pass the Cisco 350-080 exam in one go. Test4Direct is most accurate source to prepare Cisco 350-080 exam as your success will become site’s responsibility after purchasing 350-080 exam product. There are also lots of discounts and promotion offers that you can avail. Let’s try a free demo http://www.test4direct.com/350-080.html
Test4Direct provides latest PDF questions of Cisco 350-080 exam. You have an opportunity to pass the Cisco 350-080 exam in one go. Test4Direct is most accurate source to prepare Cisco 350-080 exam as your success will become site’s responsibility after purchasing 350-080 exam product. There are also lots of discounts and promotion offers that you can avail. Let’s try a free demo http://www.test4direct.com/350-080.html
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
they each have a CMP. Although only one supervisor module is active at any one time, the CMP<br />
software in each supervisor module is always active. For a high-availability configuration, you should<br />
connect four Ethernet cables <strong>to</strong> these supervisor modules—one for each ther 0 interface and one for<br />
each cmp-mgmt interface. You should also configure three IP addresses—one for each cmp-mgmt<br />
interface and one that is shared between the active and standby supervisor ther 0 interfaces.<br />
Explanation:<br />
Reference:<br />
http://www.cisco.com/c/en/us/products/collateral/switches/nexus-1000v-switch-vmwarevsphere/qa_c67-556624.html<br />
Question: 12<br />
VLAN configuration using DCNM can be completed by which two supported methods? (Choose two.)<br />
A. Copy and paste the VLAN, along with its VLAN ID, name, type, admin state, and admin status, from<br />
one device <strong>to</strong> another.<br />
B. Create a single VLAN or a range of VLANs.<br />
C. A VLAN is created only after choosing File > Deploy <strong>to</strong> apply changes.<br />
D. After a VLAN is created, it requires the state <strong>to</strong> be enabled.<br />
E. Modify the existing VLAN by choosing Interface > VLAN > VLAN Settings.<br />
Question: 13<br />
Answer: A, B<br />
Explanation:<br />
You can copy and paste the VLAN, along with its VLAN ID, name, type, admin stat, and admin status,<br />
from one device <strong>to</strong> another.<br />
Procedure<br />
Step 1 From the Feature Selec<strong>to</strong>r pane, choose Switching > VLAN <strong>to</strong> open the VLAN pane.<br />
Step 2 In the Summary pane, click the Device View tab.<br />
Step 3 Click the device from which you want <strong>to</strong> copy the VLAN.<br />
Step 4 Expand the view for the device. The system lists the VLANs configured on that device.<br />
Step 5 Highlight the VLAN that you want <strong>to</strong> copy.<br />
Step 6 From the menu bar, choose Actions > Copy.<br />
Step 7 In the Summary pane, click the device <strong>to</strong> which you want <strong>to</strong> paste the VLAN.<br />
Step 8 From the menu bar, choose Actions > Paste.<br />
Step 9 (Optional) From the menu bar, choose File > Deploy <strong>to</strong> apply your changes <strong>to</strong> the device.<br />
Explanation:<br />
Reference:<br />
http://www.cisco.com/c/en/us/td/docs/switches/datacenter/sw/6_x/dcnm/layer2/configuration/gui<br />
de/b_Cisco_DCNM_Layer_2_Switching_Configuration_Guide_Release_6 -<br />
x/b_Cisco_DCNM_Layer_2_Switching_Configuration_Guide_Release_6 -<br />
x_chapter_011.html#task_1268189<br />
Enabling jumbo frame support on a Cisco Nexus 5500 Switch can be done through which method?<br />
A. Changing the default policy map from a default MTU of 1500 <strong>to</strong> 9216<br />
B. Using the command system jumbomtu 9216<br />
C. Using the command interface MTU 9216