WorkSafe
ZUJe3
ZUJe3
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Penalties<br />
(continued)<br />
information, instruction, training, and supervision needed to ensure their health and safety in carrying out their work, a<br />
repeated violation.<br />
G S Framing Ltd. | $8,257.60 | Vancouver | April 9, 2015<br />
This firm was framing a newly built two-storey house. <strong>WorkSafe</strong>BC observed three of the firm’s workers among the trusses near the<br />
edge of the steep partially sheathed roof. No fall protection system was in use, so the workers were exposed to a risk of falling 8 to<br />
9.5 m (26 to 31 ft.). The firm’s failure to ensure that fall protection was used was a repeated and high-risk violation.<br />
HA Brar Siding & Woodwork Ltd. | $5,092.73 | Mission | February 20, 2015<br />
At a site where a two-storey house was under construction, <strong>WorkSafe</strong>BC observed two of this firm’s workers on a plank supported by a<br />
ladder-jack system at a height of 4.5 m (15 ft.). The plank had no guardrails and the workers were not using personal fall protection gear.<br />
The firm failed to ensure that fall protection was used where a fall of 3 m (10 ft.) or more could occur, a repeated and high-risk violation.<br />
As well, the firm failed to ensure that guardrails were used, a high-risk violation.<br />
HA Brar Siding & Woodwork Ltd. | $5,000 | Mission | June 1, 2015<br />
This firm was applying siding to a two-storey house under construction. <strong>WorkSafe</strong>BC observed the firm’s worker on a plank supported<br />
by a ladder-jack system at a height of about 3.4 m (11 ft.). The plank had no guardrails and the worker was not using personal fall<br />
protection gear. The firm knowingly or with reckless disregard failed to ensure that fall protection was used where a fall of 3 m (10 ft.) or<br />
more could occur, a repeated and high-risk violation. This is the second time in less than four months that the firm has been penalized<br />
for this type of violation.<br />
Haab Holdings Ltd. | $34,995.62 | Fort St. John | April 7, 2015<br />
<strong>WorkSafe</strong>BC observed two of this firm’s workers in a 2 m (6.5 ft.) deep excavation that was not sloped, shored, benched, or otherwise<br />
supported as required. The workers were exposed to a high risk of serious injury or death if the excavation walls had collapsed. The<br />
firm’s failure to meet the sloping and shoring requirements of section 20.81(1) of the Occupational Health and Safety Regulation was a<br />
repeated and high-risk violation.<br />
Hayer Demolition Ltd. | $1,661.16 | Richmond | April 7, 2015<br />
Three of this firm’s workers were stripping the interior of a pre-1990 house slated for demolition. A <strong>WorkSafe</strong>BC prevention officer<br />
inspected the worksite and found that asbestos-containing materials such as duct tape had not been safely removed prior to demolition<br />
work. The workers were not wearing the required safety gear for such work and were not using safe asbestos-removal procedures. They<br />
were therefore exposed to asbestos fibres, increasing their risk of serious illness and death. The firm failed to ensure that demolition<br />
work was stopped when hazardous materials were discovered at the site. This was a repeated violation.<br />
Hayer Demolition Ltd. | $4,152.90 | Richmond | April 7, 2015<br />
An inspection of this firm’s work at a pre-1990 house slated for demolition found violations of safety requirements related to hazardous<br />
materials. On June 2, 2014, <strong>WorkSafe</strong>BC ordered this firm to submit a Notice of Compliance with sections of the Workers<br />
Compensation Act and the Occupational Health and Safety Regulation. The firm had until June 18 to do so. In September 2014 the firm<br />
submitted an inadequate response to the orders. By March 18, 2015, no further communication from the firm had been received. The<br />
firm is being penalized for its failure to comply with an order of <strong>WorkSafe</strong>BC, a violation of section 115(1)(b) of the Act committed<br />
knowingly or with reckless disregard.<br />
Integrity Roofing Corporation | $5,982.75 | Salmon Arm | May 7, 2015<br />
Two of this firm’s workers, including a supervisor, were roofing a newly built hay shed. Neither was using personal fall protection gear,<br />
nor was any other form of fall protection in place. They were exposed to a risk of falling 4.5 m (15 ft.). Tripping hazards on the roof<br />
included air lines and piles of roofing material. The firm failed to provide its workers with the information, instruction, training, and<br />
supervision needed to ensure their health and safety, a repeated violation.<br />
K2 Roofing Ltd. / K2 Roofing | $7,059.03 | Halfmoon Bay | April 16, 2015<br />
This firm was re-roofing a flat-roofed house. The firm’s worker was climbing a ladder to access the roof, carrying a 20 kg (45 lb.) roll of<br />
roofing paper, when he lost his balance and fell 4 m (13 ft.) to the concrete driveway below. He sustained serious injuries. Use of a<br />
ladder hoist and guardrails where the ladder met the roof surface would have lessened the risk of such an incident. The firm failed to<br />
ensure that a fall protection system was used, a repeated violation. It also contravened the requirement not to allow workers to carry<br />
heavy or bulky items up a ladder. Overall, the firm failed to provide its worker with the training and supervision needed to ensure his<br />
health and safety at the jobsite.<br />
32<br />
September / October 2015 | <strong>WorkSafe</strong> Magazine