21.04.2016 Views

SYSTECH SOLICITORS LEGAL UPDATE

4mW0Sv

4mW0Sv

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The question as to whether the Singapore Courts will<br />

enforce an interim Dispute Adjudication Board (DAB)<br />

award under FIDIC has long caused uncertainty<br />

amongst construction practitioners. Many thought<br />

that the issue had been clarified in 2014 with the<br />

High Court decision in the long running case known<br />

as the ‘Perusahaan Saga 1 ’, however the defendants,<br />

true to form, appealed throwing the issues back into<br />

contention.<br />

Unfortunately, and much to the dismay of those in<br />

the construction industry, the Court of Appeal 2 (CoA)<br />

decision did not provide the resonant ending that<br />

we were all hoping for.<br />

Security of Payment<br />

Payment disputes often require time and money in<br />

order to settle matters with any finality, invariably<br />

leaving the contractor in a weakened financial<br />

position and vulnerable to the Employer’s increased<br />

leverage.<br />

The Security of Payment (SOP) regime, established<br />

within sub-clauses 20.4 – 20.7 of FIDIC 1999 Red<br />

Book, is a pragmatic mechanism used within the<br />

construction industry with the central purpose of<br />

addressing the imbalance between contractor and<br />

employer when payment disputes arise.<br />

Under the SOP regime, the contractor refers the<br />

dispute to the DAB under sub-clause 20.4. If the<br />

award is granted in their favour, the DAB can require<br />

the employer to pay the disputed sum to the<br />

contractor, without preventing the employer’s future<br />

entitlement to argue the merits of the payment at a<br />

later date. It thereby facilitates the contractor’s cash<br />

flow by granting an instant right to payment despite<br />

the employer’s right to further determination. For<br />

this reason, the mechanism is commonly referred to<br />

as ‘pay now, argue later’.<br />

The effectiveness of the SOP regime depends<br />

fundamentally on the enforceability of the DAB<br />

award and its ability to compel the employer to<br />

make payment.<br />

If the employer does not dispute the DAB’s decision,<br />

according to sub-clause 20.4, it is considered as<br />

‘final and binding’. However, if the employer issues<br />

a notice of dissatisfaction within the contractually<br />

prescribed deadline, usually 28 days, then the<br />

award is only considered as ‘binding’. The only way<br />

of gaining any finality is by proceeding to arbitration 3 .<br />

What concerned contractors were recalcitrant<br />

Employers who used this to their advantage to<br />

refuse payment in discordance with the SOP regime.<br />

The Background<br />

The ‘Perusahaan Saga’ started when PGN, an<br />

Indonesian state owned company, contracted with<br />

CRW (under FIDIC 1999 Red Book) for the installation<br />

and construction of a pipeline in Indonesia. A dispute<br />

arose between the parties in relation to a number of<br />

variation claims (Underlying Dispute).<br />

The issue was referred to the DAB who held in<br />

favour of CRW, ordering PGN to pay USD$17 million<br />

in line with the SOP regime. PGN issued a notice<br />

of dissatisfaction with the DAB’s decision disputing<br />

CRW’s right to enforce immediate payment<br />

(Secondary Dispute).<br />

In 2009, CRW commenced arbitration proceedings<br />

seeking enforcement of payment. PGN argued that<br />

as it had issued a notice of dissatisfaction, the DAB’s<br />

decision was binding but not final and therefore subclause<br />

20.6 could not compel immediate payment<br />

unless the arbitral tribunal heard the merits of the<br />

Underlying Dispute too. However, the tribunal held<br />

in favor of CRW and a final award issuing immediate<br />

payment was granted.<br />

Undaunted from the ruling, PGN continued to<br />

refuse payment. The matter was taken to the High<br />

Court and later to the CoA where they both set<br />

aside CRW’s application, albeit on different grounds.<br />

The CoA stated that the arbitral tribunal by making<br />

a final award was denying PGN the opportunity to<br />

reopen the case. The CoA did state however that<br />

it would have been permissible for the tribunal to<br />

order an interim award. The CoA also held that the<br />

Underlying Dispute must be settled in the same<br />

arbitration proceedings so that the full merits of the<br />

case could be decided.<br />

In 2011, undeterred from the setback, CRW brought<br />

a second round of arbitral proceedings this time<br />

seeking an interim award to enforce DAB decision<br />

as well as the final award to settle the Underlying<br />

Dispute, as advised by the CoA.<br />

PGN resisted with a new line of argument that a<br />

tribunal had no power to issue an interim award as<br />

this would be contrary to Singapore’s International<br />

Arbitration Act (IAA) 4 .<br />

S19B of the IAA states that “an award whether final<br />

or interim, made by an arbitral tribunal pursuant to<br />

an arbitration agreement is final and binding on the<br />

parties, and that the arbitral tribunal must not vary,<br />

amend, correct, review, add to or revoke the award”.<br />

PGN argued that the interim award according to IAA<br />

was final and binding and therefore could not be<br />

altered by a final award which would unjustly deny<br />

1<br />

PT Perusahaan Gas Negara (Persero) TBK (PGN) v CRW Joint Operation (Indonesia) [2014] SGHC 146<br />

2<br />

PT Perusahaan Gas Negara (Persero) TBK (PGN) v CRW Joint Operation (Indonesia) [2015] SGCA 30<br />

3<br />

Sub-clause 20.6 – Arbitration<br />

4<br />

International Arbitration Act Chapter 143A 2002 Revised Edition<br />

www.systech-int.com<br />

27

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!