10.2 Dining Room<br />

During our PCA, we found that there were structural walls removed to give the main floor an open concept feel.<br />

On the ceilings where the old walls were located, there are cracks in the drywall. With no permits obtained for this<br />

structural modification, it is obvious that something is not correct. We have been informed that these cracks have<br />

been repaired 2 times already and they are still coming back.<br />

Also to note, the walls and ceiling were only primed and did not have any paint on them.<br />

Recommendations: We advise that the ceilings be opened up and the engineered beam be inspected to make sure<br />

the work was completed correctly.<br />

We also suggest that the concrete base of the support posts holding up these beams be x-rayed to determine that<br />

the thickness of the concrete slab is sufficient to support the weight of the posts and beams.<br />

After all of the inspections have been made, we suggest that the smooth finish drywall ceilings be repaired and all of<br />

the walls and ceiling be primed and painted.<br />

10.3 Kitchen<br />

During our PCA and onsite interview, we found that the kitchen walls and ceiling are only lightly primed and not<br />

painted.<br />

On inspection of the new kitchen cabinets, we noticed that they are not installed flush and level. Because of the<br />

rustic finished look of the cabinets, this is not very noticeable.<br />

In order to fit a larger refrigerator, the exterior wall was sectioned out and moved back. It is unclear that this work<br />

done to a loadbearing wall was in fact performed correctly due to the fact that no permits were pulled for this<br />

project.<br />

The kitchen electrical also has issues. See section 7.2 Kitchen Electrical for details.<br />

Recommendations: We advise that the new exterior build-out be opened up on the inside of the house to properly<br />

inspect and make sure the work was completed correctly.<br />

We also recommend that the walls and ceilings be painted 10.4 Small TV Area – Off Kitchen.<br />

During our PCA, and under visual inspection only, we noticed that there was cracks in the walls as well as poorly<br />

finished drywall. All of the walls and ceilings were only lightly primed and not painted.<br />

Recommendations: We advise that the drywall be repaired and completed to a smooth wall finish. Also that the<br />

walls and ceiling be primed and painted.<br />

10.4 Utility Rooms/Areas<br />

Laundry Room: During our PCA, we noticed that there are no baseboards on the walls in the laundry room.<br />

We also noticed that the laundry room dryer vent is plumbed into the mudroom and then out to the exterior of the<br />

house. As it sits, the exterior vent is too close to the ground.<br />

Recommendations: We advise that new baseboards are installed to match the rest of the home.<br />

Also, we recommend that the dryer duct and exterior vent be relocated to a higher position.<br />