School: The work on construction of a School building has started and going on with vigour and speed. This will be<br />

completed before Sector-3 is opened for construction.<br />

<br />

Health Care Center: The construction of the health care center is almost complete and the furnishing/finishing work<br />

is in progress.<br />

ICT BUILDING<br />

COMMERCIAL BUILDING SECTOR-3<br />

<br />

ICT & Security Building: The construction work is near finishing while furnishing/renovation work is in progress.<br />

<br />

Commercial Building: The construction of state-of-the-art Communication Building has almost been completed.<br />

Furnishing/finishing work is in progress.<br />