<strong>Lindenberg</strong> <strong>Anlagen</strong> <strong>GmbH</strong><br />
EGP3 ONSHORE PROJECT<br />
D/G FSO Set<br />
1
Index<br />
<strong>Lindenberg</strong> <strong>Anlagen</strong> <strong>GmbH</strong><br />
Project information<br />
01 FSO<br />
02 Base Frame<br />
03 Piping CAD Drawing<br />
03.1 Piping<br />
04 Side Walls<br />
05 Installation CAD Drawing<br />
05.1 Installation<br />
06 DG Set<br />
07 Purifier Installation CAD Drawing<br />
07.1 Purifier Installation<br />
08 Cable Letters<br />
09 Working Platform<br />
10 Lifting Eyes<br />
11 Module CAD Drawing<br />
11.1 Module<br />
12 Shipping and Mounting Bonn<br />
13 Shipping Rotterdam<br />
14 Shipping Rotterdam<br />
15 – 15.4 Installation of DG 5 Module on board of FSO Exravos<br />
Certification<br />
2
<strong>Lindenberg</strong> <strong>Anlagen</strong> <strong>GmbH</strong><br />
<strong>Lindenberg</strong>‐<strong>Anlagen</strong> employs around 170 people.<br />
Our production allows us to produce compact aggregates with a total weight up<br />
about 100 tons. We can also fabricate aggregates in volume production<br />
produced at rates of up to 70 units per month.<br />
In addition to a wide range of aggregates, we supply medium and low‐voltage<br />
switchgears and control and distribution boxes for industrial applications. We are<br />
prepared to take full responsibility for all engineering production and even –in<br />
costumer requests for installation and activation, both in Germany and abroad.<br />
The <strong>Lindenberg</strong>‐<strong>Anlagen</strong> construction division uses the latest technology and CAD systems.<br />
Supported by an exclusive proprietary software developed for the design of power stations, we<br />
process a wide range of electrical and mechanical materials and perform all services relating to<br />
installation construction. The fact that all products and services originate from a single source<br />
derived is of great advantage for our costumers.<br />
The <strong>Lindenberg</strong>‐<strong>Anlagen</strong> customer service department allows us to maintenance contracts and<br />
regular inspections of the entire installation, even after activation ‐ especially when plants are<br />
affected by the global level (world‐scale plants) ‐ with our own staff, both in Germany and<br />
abroad to supervise and monitor.<br />
3
Project information<br />
Modularized Diesel Engine Generator<br />
Enclosure<br />
Project: EGP3 ONSHORE PROJECT<br />
Customer: Hyundai Heavy Industries CO., LTD<br />
End customer: Chevron Shipping Company<br />
The Diesel Engine Generator will be mounted onshore at the deck<br />
of a FSO (Floating Storage & Offloading)<br />
to produce energy.<br />
<strong>LIAG</strong> <strong>order</strong> <strong>code</strong>: 110015000<br />
Number of units: 1<br />
Classification Society: ABS (American Bureau of Shipping)<br />
Gen Set Measurements: 11m x 6,5m x 10,1 m ((l x b x h)<br />
150 Tons gross weight<br />
4
01 FSO Tanker<br />
<strong>Lindenberg</strong> <strong>Anlagen</strong> constructed the Diesel Engine Generating Enclosure due to the<br />
requirements of the client. The tailor made weather and fire protecting Enclosure, with<br />
all auxiliary equipment is constructed to mount this set on deck of the FSO.<br />
5
Technical data<br />
length 11,3 m<br />
Bright6,5 m<br />
height 10,2 m<br />
Weight 25 tons<br />
02 Frame Fabrication<br />
The steel frames for the base and walls had been welded, blasted and painted<br />
in separate sections and assembled together at a later stage.<br />
Welding material and procedure had been done under the verification of<br />
ABS and the welding procedure had been certified by ABS approved<br />
laboratory for welding.<br />
6
03 Installation and Piping<br />
The complete set has been drawn and constructed before the<br />
installation/fabrication to give the client the possibility for detail approval.<br />
7
03.1 Piping<br />
The piping and installation of the equipment had been preassembled,<br />
pressure tested and painted at our workshop before installation at the<br />
module..<br />
8
Technical data<br />
Length: 11,3 m<br />
Height: 10,2 m<br />
Weight: 1 t<br />
04 Side Walls<br />
After preinstallation the site walls had been mounted<br />
9
05 Module Installation Design<br />
10
Technical data<br />
Manufacturer<br />
MAN<br />
Length: 7 m<br />
Bright :3 m<br />
Height: 3 m<br />
Weight: 54 t<br />
Power: 2000 KW<br />
Speed: 720 rpm<br />
05.1 Installation of D/G Set<br />
11
07.1 Purifier Installation<br />
Separator Tank<br />
12
08 Installation of Cable trays and letters<br />
The mounted ladders allow an additional fitting of cabling to assure protection<br />
from stumbling, damage.<br />
13
09 False floor installation<br />
<strong>Lindenberg</strong> <strong>Anlagen</strong> took attention by the design of the working platform to<br />
assure an optimal usability.<br />
14
10 Lifting Eyes<br />
The fittings were mounted especially for the transportation.<br />
All static components of Diesel Engine Generating Enclosure are certified<br />
according the ABS rules.<br />
15
11 Modul CAD Drawing<br />
16
Technical data<br />
Length: 11,3 m<br />
Bright: 6,5 m<br />
Height: 10,2 m<br />
Weight: 140 to<br />
11.1 Modul<br />
The manufacturing of the modules took place at the same time in different<br />
workshops.<br />
The high quality and the robust construction assures an optimal cover for the<br />
Aggregate inside.<br />
All elements of the Diesel Engine Generator Enclosure which have to be<br />
conform to the atmospheric conditions (Offshore) had been sandblasted,<br />
grounded, painted due to the client requirements.<br />
17
12 Shipping / Mounting Bonn<br />
After a manufacturing period of 9 month the final acceptance test had been<br />
done at our workshop. For transport parts of the modules had to be<br />
demounted to reduce the weight and measurements for truck transport. The<br />
final assembling then had been done at Rhein River Port, so that the whole<br />
module could be lifted to a river barge.<br />
18
13 Shipping Rotterdam<br />
19
14 Shipping Rotterdam<br />
20
15 Installation of DG 5 Module on board of FSO<br />
Escravos<br />
Crane used for installation<br />
21
15.1 Module rigged into place<br />
22
15.2 Closer…………<br />
Closer………….<br />
23
15.3 Fit-up Fit up was nearly dead on<br />
24
15.4 An important milestone completet<br />
25
Certification<br />
26
Technology & Experience since 1948<br />
<strong>Lindenberg</strong>‐<strong>Anlagen</strong> Worldwide<br />
As an international company with 85% foreign share of exports, see<br />
<strong>Lindenberg</strong>‐agencies worldwide<br />
Europe South America Australia Africa<br />
Russia Brasilien Egypt<br />
Italy Argentina Cameroon<br />
Turkey Sudan<br />
Poland Marocco<br />
Croatia Mauritania<br />
Romania Nigeria<br />
France<br />
Swiss<br />
Ukraine<br />
Belarus<br />
England Asia<br />
Spain Japan<br />
Sweden China<br />
Norway South-Corea<br />
EMEA Vietnam<br />
Pakistan Philippines<br />
U.A.E Bangladesh<br />
Yemen India<br />
Saudi Arabia Thailand<br />
Iran Indonesia<br />
27