Leak test protocol<br />

for carrying out a leak test on radiant heating systems<br />

in accordance with DIN EN 1264 Part 4 (2009-11)<br />

Building project:<br />

Client:<br />

Construction stage:<br />

In the above-mentioned building project, a <strong>Roth</strong> radiant heating system of type: __________________________<br />

construction type A according to DIN 18560 Part 2/DIN EN 1264 Part 4, was installed.<br />

Ø <strong>Roth</strong> System Pipe X-PERT S5 ® ____________________ mm<br />

Ø <strong>Roth</strong> System Pipe DUOPEX S5 ® ____________________ mm<br />

Ø <strong>Roth</strong> System Pipe Alu-Laserflex ® ____________________ mm<br />

Method of procedure:<br />

After finishing installation work on anhydrite and cement screeds, the heating circuits on the <strong>Roth</strong> radiant<br />

heating system must be tested for leaks using a water or compressed air test. Tightness against leaks must be<br />

ensured immediately before and whilst laying the screed. The test pressure must not be less than 4 bar and not<br />

more than 6 bar.<br />

If there is a risk of freezing, in case of the water pressure test, suitable measures must be taken, e.g. using<br />

anti-freeze, carrying out the temperature equalisation of the building. If anti-freeze is used that is not designed<br />

for the intended use, then this should be removed by emptying and flushing the system with at least 3 changes<br />

of water.<br />

• Completion of the <strong>Roth</strong> radiant heating system on: ______________<br />

• Start of the pressure test on: ______________ with test pressure: _______ bar<br />

Water Pressurised air<br />

• End of the pressure test on: ______________ with test pressure: _______ bar<br />

• Screed laid on: ______________<br />

• System pressure during application was ______________ bar<br />

• Anti-freeze was added to the system water and handled as described. (Yes/No)<br />

• The system was tested for leaks on: ______________ inspected and approved<br />

Confirmation:<br />

Builder/Client<br />

Stamp/Signature<br />

Building manager/Architect<br />

Stamp/Signature<br />

10<br />

Heating engineering company/installation company<br />

Stamp/Signature<br />

Material no. 1180000337 X710 B Subject to technical modifications.