Del or Ex <strong>Jan</strong>uary 20<strong>08</strong> (RM)<br />
Pulau<br />
Pinang<br />
Selangor Johor Kelantan Perak Pahang<br />
19 High Tensile Deformed Bars - 32mm, MS146 MT 14 del 2,328.00 2,328.00 2,328.00 2,328.00 2,328.00 2,328.00<br />
20 BRC Fabric - A6, MS145 m² 30 del 5.70 5.70 5.70 5.70 5.70 5.70<br />
21 BRC Fabric - A7, MS145 m² 30 del 7.98 7.98 7.98 7.98 7.98 7.98<br />
22 BRC Fabric - A8, MS145 m² 30 del 10.19 10.19 10.19 10.19 10.19 10.19<br />
23 BRC Fabric - A9, MS145 m² 30 del 13.23 13.23 13.23 13.23 13.23 13.23<br />
24 BRC Fabric - A10, MS145 m² 30 del 16.70 16.70 16.70 16.70 16.70 16.70<br />
25 Ready Mix Concrete - Normal Mix - Grade 10 m³ 30 del 144.33 136.00 140.67 132.33 116.00 134.33<br />
26 Ready Mix Concrete - Normal Mix - Grade 15 m³ 30 del 150.33 141.00 146.00 139.33 121.00 138.67<br />
27 Ready Mix Concrete - Normal Mix - Grade 20 m³ 30 del 155.00 145.67 151.00 146.00 126.00 144.00<br />
28 Ready Mix Concrete - Normal Mix - Grade 25 m³ 30 del 161.33 153.00 156.67 153.00 133.00 151.00<br />
29 Ready Mix Concrete - Normal Mix - Grade 30 m³ 30 del 170.00 160.67 163.33 160.33 141.00 159.67<br />
30 Ready Mix Concrete - Normal Mix - Grade 35 m³ 30 del 179.00 170.00 170.00 176.00 150.00 168.00<br />
31 Ready Mix Concrete - Normal Mix - Grade 40 m³ 30 del 188.67 179.67 180.33 183.00 160.33 178.00<br />
32 Clay Brick - Pallet piece 30 del 0.26 0.25 0.25 0.28 0.26 0.26<br />
33 Smooth Face Facing Brick, Red piece 30 del 0.73 0.69 0.72 0.75 0.76 0.76<br />
34 Cement Sand Brick - Pallet piece 60 del 0.17 0.16 0.18 0.17 0.18 0.17<br />
35 Precast Concrete Hollow Block 90mm x 190mm x<br />
390mm M.S 27 1996<br />
Table 1. <strong>Average</strong> <strong>Price</strong> of Building Materials for Peninsular Malaysia (BMDAM) (Continue...)<br />
No. Description Unit Credit<br />
Term<br />
(Days)<br />
Source of Data: This average price is compiled from data supplied by BMDAM<br />
MT = Metric Ton or Tonne, m² = Square Metre, m³ = Cubic Metre, Del = Delivered, Ex = Ex-Factory, Ex-Quarry, Ex-Sand Pit<br />