Question 6. Question : (TCO 4) Comparing predictive and adaptive approaches, in a predictive project, planning<br />

tasks are:<br />

o<br />

o<br />

o<br />

o<br />

purely project management tasks.<br />

purely SDLC tasks.<br />

more concentrated at the start of the project.<br />

more distributed over the lifetime of the project.<br />

Question 7. Question : (TCO 4) People inside of the company who will use the system to do their work belong<br />

to which category of stakeholders?<br />

o<br />

o<br />

o<br />

o<br />

Internal users<br />

External users<br />

Sponsors<br />

Support staff<br />

Question 8. Question : (TCO 4) Improvements that will accrue to a company as a result of a project and its<br />

deliverables are known as:<br />

o<br />

o<br />

o<br />

o<br />

system capabilities.<br />

business models.<br />

project stakeholders.<br />

business benefits<br />

Question 9. Question : (TCO 4) What is the key question to be answered when completing the problem definition<br />

activity?<br />

o<br />

o<br />

o<br />

o<br />

Can the project be completed on time given available resources?<br />

Do we understand what we are supposed to be working on?<br />

Is it still feasible to begin working on this project?<br />

Are we ready to start the project?<br />

Question 10. Question : (TCO 4) Which column in a risk analysis matrix provides an assessment of how badly<br />

the project will be affected if the risk materializes?<br />

o<br />

o<br />

o<br />

o<br />

Risk description<br />

Potential impact on project<br />

Likelihood of occurrence<br />

Overall threat<br />

1. Question : (TCO 4) Risk management is primarily concerned with:<br />

o<br />

o<br />

o<br />

o<br />

identifying potential trouble spots that could jeopardize project success.<br />

developing a work breakdown structure, including intermediate deliverables.<br />

understanding how the project contributes to the organization's strategic direction.<br />

listing all stakeholders with an interest in the system.<br />

Question 2. Question : (TCO 4) "Fear of change of job responsibilities" is an example of what type of feasibility<br />

issue?<br />

o<br />

o<br />

o<br />

o<br />

Technological feasibility<br />

Schedule feasibility<br />

Resource feasibility<br />

Organizational and cultural feasibility<br />

Question 3. Question : (TCO 4) Which of the following would be an example of a schedule feasibility issue?