CompTIA Project+ PK0-004 Project Documentation Exam Questions

https://www.premiumdumps.com/CompTIA/PK0-004-exam-dumps-pdf. Getting a certificate means a lot in your professional life, as it enables you to stand apart from the competition and enhances your worth in the eyes of the companies. You can prepare you CompTIA PK0-004 exam through “premiumdumps.com” as it gives guarantee of your success.

https://www.premiumdumps.com/CompTIA/PK0-004-exam-dumps-pdf.
Getting a certificate means a lot in your professional life, as it enables you to stand apart from the competition and enhances your worth in the eyes of the companies. You can prepare you CompTIA PK0-004 exam through “premiumdumps.com” as it gives guarantee of your success.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

How to pass <strong>CompTIA</strong> <strong>PK0</strong>-<strong>004</strong> Certification <strong>Exam</strong>?<br />

If you are intending to excel in your career by validating your <strong>CompTIA</strong> <strong>PK0</strong>-<strong>004</strong> credential, then stop stressing about it.<br />

Though, <strong>PK0</strong>-<strong>004</strong> <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> certification exam is not easy to pass, but still you can pass it in he first attempt with<br />

Premiumdumps.com quality exam material. Premiumdumps offers you trustworthy and convenient exam material to guide you<br />

and mto make you <strong>CompTIA</strong> <strong>PK0</strong>-<strong>004</strong> certified Management. The <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> study material is available in two easy<br />

format, Pdf book and easy to download-desk practice software. This software is intended to provide you a platform to practice<br />

questions on regularly and get familiar with the real exam simulation. The purpose of <strong>PK0</strong>-<strong>004</strong> <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> practice<br />

software is to prepare you real exam and increases your self-possession.<br />

Premiumdumps <strong>PK0</strong>-<strong>004</strong> <strong>Exam</strong> policy: Now be <strong>CompTIA</strong> Certified in first<br />

attempt<br />

Premiumdumps is concerned for your investment, thats why offer you 100% refund policy. If, in case, a candidate fails in <strong>PK0</strong>-<br />

<strong>004</strong> exam. So he will be reverted his amount after the basic inquiry. Also, we have customer support for all our esteemed<br />

customers, our dedicated team is available 24/7 at the back-end to answer your product related queries. You may write us an<br />

email against the bugs, our support team will respond to your queries in the best possible time.<br />

Now try <strong>PK0</strong>-<strong>004</strong> Dumps Certification <strong>Exam</strong> demo before Purchase: prepare<br />

with Quality Material<br />

Premiumdumps recommend its potential customers to must try the free demo of <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> Certification <strong>Exam</strong>, before<br />

purchase. Our product demo will give you an exposure of real product which carries more features. Also, this demo will help you to<br />

get acquainted with <strong>PK0</strong>-<strong>004</strong> exam interface. Our exam practice software offers you real exam simulation which can also be tested<br />

on demo product. Premiumdumps keeps your data protected with our enhanced security protocols, by McAfee and SSL 64-Bit. Our<br />

dedicated team is very consistent and driven, who keeps a check on your data 24/7. No third party has an access to your personal<br />

details under any circumstances.<br />

Try free demo of <strong>PK0</strong>-<strong>004</strong> exam product before Purchase<br />

Premiumdumps strongly recommend you try the free demo of <strong>PK0</strong>-<strong>004</strong> exam Braindumps before purchase. You may test the quality<br />

features of our <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> exam practice test, this demo offer will make you acquainted with the interface. Also, we offer<br />

you 90 days free updates upon purchase of <strong>PK0</strong>-<strong>004</strong> <strong>CompTIA</strong> <strong><strong>Project</strong>+</strong> exam material.<br />

Download Latest <strong>CompTIA</strong> <strong>PK0</strong>-<strong>004</strong><strong>Exam</strong> Dumps Follow This Link!<br />

https://www.premiumdumps.com/<strong>CompTIA</strong>/<strong>PK0</strong>-<strong>004</strong>-exam-dumps-pdf


Question: 1<br />

Version: 8.0<br />

A project manager is attempting to establish the proper sequencing and duration of project activities.<br />

Which of the following would be the MOST beneficial?<br />

A. Network diagram<br />

B. Ishikawa diagram<br />

C. WBS<br />

D. Gantt chart<br />

Answer: A<br />

Question: 2<br />

Which of the following are characteristics of a project? (Select TWO)<br />

A. Ongoing<br />

B. Temporary<br />

C. Start and finish<br />

D. Achieving a goal<br />

E. Consisting of milestones<br />

F. Restricting the budget<br />

Answer: CD<br />

Question: 3<br />

A company has determined it does not have the in-house capability to perform a project and wants to<br />

procure third-party services. Which of the following documents will the company MOST likely release-<br />

FlRST?<br />

A. RFO<br />

B. RFI<br />

C. RFP<br />

D. RFQ<br />

Answer: A<br />

Question: 4<br />

The project manager was asked to provide recommendations for the removal of a vendor. A meeting<br />

was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this<br />

recommendation. Which of-the following should the project manager bring to the meeting to support<br />

this recommendation? (Select TWO)<br />

A. The issue log to show why the vendor should be replaced


B. The team action items to show why the vendor should be replaced<br />

C. The scope statement to show why the vendor should be replaced<br />

D. A procurement plan to show why the vendor should be replaced<br />

E. A change management plan to have the vendor replaced<br />

Answer: AE<br />

Question: 5<br />

A project manager is creating the WBS. In which of the following phases is the project?<br />

A. Initiation<br />

B. Planning<br />

C. Execution<br />

D. Closing<br />

Answer: A<br />

Question: 6<br />

Which of the following is a characteristic of a matrix organization?<br />

A. Authority lies solely with the project manager.<br />

B. Authority is directed by the project architect.<br />

C. Authority is shared between the project manager and project coordinator.<br />

D. Authority is shared between functional and project managers.<br />

Answer: D<br />

Question: 7<br />

A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost<br />

and time estimates for the project activities?<br />

A. <strong>Project</strong> team members<br />

B. <strong>Project</strong> sponsor<br />

C. <strong>Project</strong> manager<br />

D. <strong>Project</strong> scheduler<br />

Answer: D<br />

Question: 8<br />

A project manager is assigned to a project and has not had a handover meeting with the previous<br />

project manager. The new project manager is reviewing the percent of project completion, schedule<br />

progress, and budget constraints Which of the following documents should the project manager use to<br />

obtain this information?


A. <strong>Project</strong> schedule<br />

B. Balanced scorecard<br />

C. Issue log<br />

D. Status report<br />

Answer: A<br />

Question: 9<br />

A stakeholder is unaware of a project's status Which of the following documents should the project<br />

manager consult to ensure a» stakeholders are notified of project changes?-(Select TWO).<br />

A. Status report<br />

B. Organizational chart<br />

C. RAO matrix<br />

D. Meeting minutes<br />

E. Communication plan<br />

Answer: AC<br />

Question: 10<br />

There are four parallel, paths on a network diagram. The summer duration d each path is below:<br />

A, C, G: 10 weeks<br />

A, B, F:8 weeks<br />

D, E,H: 12 weeks<br />

D, B, F: 7 weeks<br />

Which of the following tasks are on the critical path?<br />

A. A,C,G<br />

B. A, B,F<br />

C. D,E,H<br />

D. D,B,F<br />

Answer: C