<strong>Concentrated</strong> <strong>Solar</strong> <strong>Power</strong>:<br />
<strong>Modular</strong> <strong>Fresnel</strong> <strong>Collector</strong><br />
<strong>Technology</strong><br />
4th Saudi <strong>Solar</strong> Energy Forum<br />
9 th May 2012
NOVATEC SOLAR´s <strong>Fresnel</strong> <strong>Technology</strong><br />
� Fixed positioned receiver<br />
system<br />
� Direct steam generation<br />
above 500°C<br />
� Primary reflectors using<br />
flat mirrors<br />
� Continuous tracking of<br />
primary reflectors to keep<br />
sun focused on receiver<br />
2
Cost Effective <strong>Fresnel</strong> <strong>Technology</strong><br />
� Minimized assembly works<br />
� Low cost cleaning device<br />
3
Activities along the value chain<br />
Project<br />
Development<br />
Novatec activities<br />
<strong>Solar</strong> Field<br />
Manufacturing<br />
Customers/Partners/Others<br />
ABB/EPC Contractors<br />
Turnkey <strong>Solar</strong><br />
Field Delivery<br />
EPC<br />
Operation &<br />
Maintenance<br />
In March 2011, ABB acquired a 35% shareholding in Novatec <strong>Solar</strong>.<br />
Project<br />
Ownership<br />
www.novatecsolar.com 4
PE1 – NOVATEC SOLAR´s demonstration plant<br />
PE 1: 1.4MW el Demonstration Plant<br />
Synchronized in March 2009<br />
Direct steam generation at 270°C<br />
100 % solar steam generation<br />
Air cooled condensers<br />
5
PE2 – 30 MWel CSP plant<br />
PE 2: 30MW el <strong>Solar</strong> <strong>Power</strong> Station<br />
Synchronized in January 2012<br />
Direct steam generation at 270°C<br />
100 % solar steam generation<br />
Air cooled condensers<br />
6
PE2 – Project Structure<br />
Lenders Advisors<br />
Lenders<br />
O&M Contractor<br />
Owner’s Technical Advisor<br />
Project<br />
Company<br />
PE2<br />
Owner<br />
EPC Contractor<br />
85 %<br />
Off-taker<br />
7
<strong>Solar</strong> Augmentation of a Coal fired power station<br />
Key data<br />
EPC Contractor Novatec <strong>Solar</strong><br />
Owner Macquarie Generation<br />
Application<br />
Net aperture area 18,500 m²<br />
Peak thermal<br />
output<br />
Thermal Output per<br />
year<br />
solar augmentation of a<br />
coal fired power station<br />
in Liddell, Australia<br />
9.3 MW th<br />
13,550 MWh th<br />
8
Local manufacturing in target markets<br />
� High level of prefabrication of solar field key components<br />
� High potential of local component supply<br />
� High skilled job creation
NOVATEC SOLAR – Just In Time Production & Logistics<br />
Production plant<br />
and remote project site<br />
…connected by just in time logistics
Direct superheated steam > 500°C<br />
In future power plants, parallel rows of:<br />
Evaporator 700 m length<br />
Superheater 300 m length<br />
11
Superheater Design<br />
� Design: everything similar to evaporating section, except receiver<br />
design.<br />
� Receiver developed for the use of vacuum absorber tube.<br />
Receiver: Evaporating Section Receiver: Superheating<br />
section<br />
www.novatecsolar.com<br />
12
Commissioning of Superheater August 2011<br />
13
Novatec‘s Global Presence<br />
Novatec Offices<br />
Projects<br />
Target Markets 14
Conclusion<br />
� Novatec <strong>Solar</strong> offers competitive turnkey solar boilers based<br />
on <strong>Fresnel</strong> collector technology achieving superheated steam<br />
with temperatures above 500°C.<br />
� Strong partnership with ABB will ease fund raising.<br />
� The selection of CSP plants based on Novatec <strong>Fresnel</strong><br />
technology will lead to set up of local production capacities for<br />
solar field elements and longterm employment in the market.<br />
15
Thank you for your attention!