14.12.2012 Views

BOLDON SCHOOL SOUTH TYNESIDE - Wayne Ellison

BOLDON SCHOOL SOUTH TYNESIDE - Wayne Ellison

BOLDON SCHOOL SOUTH TYNESIDE - Wayne Ellison

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SB14_24-29/<strong>BOLDON</strong> 2/2/07 15:08 Page 1<br />

24 PROJECT<br />

<strong>BOLDON</strong> <strong>SCHOOL</strong><br />

<strong>SOUTH</strong> <strong>TYNESIDE</strong><br />

>26


SB14_24-29/<strong>BOLDON</strong> 2/2/07 15:08 Page 2<br />

PROJECT<br />

25


SB14_24-29/<strong>BOLDON</strong> 2/2/07 15:08 Page 3<br />

26 PROJECT<br />

FLAGSHIP £17.5M PFI SCHEME IN<br />

<strong>BOLDON</strong> REACHES TIMELY<br />

COMPLETION<br />

The project team delivering the flagship<br />

£17.5 million PFI project to replace Boldon<br />

School in South Tyneside is celebrating its<br />

successful completion.<br />

The team for the state-of-the-art<br />

1505-pupil secondary school comprised<br />

Gleeson Building’s north east regional office,<br />

architects at the multidiscipline consultancy for<br />

the built environment Waring and Netts, and<br />

the Newcastle office of White Young Green,<br />

consultants to the built, natural and social<br />

environment. All have significant experience of<br />

delivering high profile PFI schemes.<br />

The new school which is located on New<br />

Road, has been constructed in three blocks:<br />

the three storey Block A comprises teaching<br />

facilities; Block B comprises a 200-place<br />

theatre with fixed seating and back of house<br />

changing; Block C incorporates a 25-metre<br />

indoor swimming pool and sports centre.<br />

Having fostered a pro-active and close<br />

relationship with the School throughout the<br />

construction process, the Gleeson team<br />

ensured that it was kept up-to-date with all<br />

logistical requirements of both construction<br />

and site access.<br />

Bill Law, Director in charge of the project for<br />

Gleeson Building, said<br />

“A major strength of this project has been<br />

the close professional working relationships<br />

with the project team which were established<br />

from the very beginning. We are delighted to<br />

have delivered this landmark project on time,<br />

a major achievement given the financial and<br />

scheduling constraints of the scheme.


SB14_24-29/<strong>BOLDON</strong> 2/2/07 15:09 Page 4<br />

“The project has run very smoothly and<br />

despite the school’s concern regarding access<br />

to their existing building, we managed<br />

accessibility for staff, students and the<br />

community association users next to our site,<br />

throughout the construction period.”<br />

Waring and Netts was the lead designer,<br />

responsible for the architecture and coordination<br />

of the rest of the design team.<br />

Having received a very positive response to<br />

the scheme from the Headmaster and staff,<br />

Richard Howe, lead architect for Waring and<br />

Netts, commented:<br />

“One of the most successful aspects of the<br />

building for me has to be the shared school<br />

and theatre atrium; this makes a very light<br />

and impressive entrance for the school.<br />

“Throughout the whole building we<br />

have maximised circulation space and have<br />

PROJECT<br />

“<br />

The new school which is located on<br />

New Road, has been constructed in three blocks:<br />

the three storey Block A comprises teaching<br />

facilities; Block B comprises a 200-place theatre<br />

with fixed seating and back of house changing;<br />

Block C incorporates a 25-metre indoor<br />

swimming pool and sports centre.<br />

”<br />

created space for informal student<br />

interaction which reflects the School’s open<br />

and friendly atmosphere.<br />

“This has been an extremely rewarding<br />

project where yet again our relationship with<br />

Gleeson Building has proved highly effective.”<br />

White Young and Green drew upon a<br />

number of its core disciplines throughout as it<br />

undertook a wide-ranging role including civil<br />

and structural, mechanical and electrical and<br />

environmental. Trevor Little, Technical Director<br />

of White Young Green Newcastle, said:<br />

“We enjoyed a very good working<br />

relationship with the design and<br />

construction team, having worked with them<br />

on similarly high profile PFI schemes before.<br />

In addition, the support and enthusiasm<br />

for the project from the Headteacher has<br />

been unparalleled.” >28<br />

27


SB14_24-29/<strong>BOLDON</strong> 2/2/07 15:09 Page 5<br />

28 PROJECT<br />

PROJECT TEAM<br />

Client:<br />

Boldon School<br />

Architects:<br />

Waring and Netts<br />

Contractors:<br />

Gleeson Building<br />

Consultants:<br />

White Young Green<br />

Images:<br />

Sally Ann Norman<br />

“<br />

One of the most successful aspects of the<br />

building for me has to be the shared school and<br />

theatre atrium; this makes a very light and<br />

impressive entrance for the school.<br />

”<br />

RICHARD HOWE > LEAD ARCHITECT > WARING AND NETTS<br />

All three companies started work on the<br />

project in July 2003 following a competitive<br />

tender, which was issued by South Tyneside<br />

Metropolitan Borough Council. Work<br />

commenced on site in March 2005.<br />

Colin Whitfield, Headteacher of Boldon<br />

School, said:<br />

“The new school has been successfully<br />

delivered on time by Gleeson Building which<br />

has brought into reality Waring and Netts’<br />

innovative and exciting design concept. Inside<br />

the space and light in all areas provides a<br />

superb flexible teaching and learning<br />

environment. They have, with White Young<br />

Green, set the building into the local<br />

environment so that it makes a bold<br />

statement about its purpose and yet<br />

complements the surrounding area.<br />

“Everyone is excited about the move into<br />

the new building which will take place in<br />

November. Demolition of the old school<br />

buildings will take place in December.”