COMMERCIAL <strong>SEC</strong>TOR AND LOCAL AUTHORITY PROJECTS<br />

MAHLE, Power Train, Northampton<br />

<strong>SEC</strong>’s neighbours MAHLE have invested £8 million in this new ‘State of the Art’<br />

test facility. The new site will become the campaigns global centre for (RDE)<br />

“Real Dimming Emissions”. The development of this facility is to respond to the<br />

new European wide emission tests introduced in September 2017, another project<br />

where <strong>SEC</strong> have contributed to keeping the carbon footprint to a minimum.<br />

Teaming alongside a local Mechanical Contractor to provide a fully integrated<br />

M&E package, our installations began at the client supplied Transformer and<br />

<strong>SEC</strong> provided the LV connections for the new facility.<br />

A new 2500A bespoke arrangement Switch Panel provides power to Distribution<br />

Boards, Mechanical Plant, Lighting, Small Power, Fire, Security systems, Access<br />

Control, External Services.<br />

Project Value: £350,000<br />

Main Contractor: J Coffey Construction<br />

Services Included: LV Distribution, LV Switchgear and Cabling, Small Power,<br />

General & Emergency Lighting, External Lighting, Earthing and Bonding, Telecommunications,<br />

Access Control, Intruder Alarm, CCTV, Fire Alarm, Assistance<br />

Call Systems, Lightning Protection.<br />

Saints, Franklins Gardens, Northampton — New Barwell Stand<br />

<strong>SEC</strong> have recently completed the electrical works to the new Barwell Stand at<br />

Northampton Saints. Working to a very tight deadline this intensive programme of<br />

works highlights our ability to get the job done on time. The new stands estimated<br />

cost of £6.5million has raised the stadiums capacity to nearly 16,000.<br />

Project Value: £700,000<br />

Main Contractor: Buckingham Group<br />

Services Included: Enabling Works, Mains Cabling, Lighting & Lighting Control<br />

Installation, Small Power, Fire Alarm, CCTV, Door Access, IT Cabling, Photovoltaic,<br />

Intruder Alarm, Lightning Protection, Data Communications. Reconfiguration of<br />

existing systems to allow for the demolition of the existing stand.<br />

Capital Park, Cambridge - Phase 2 (CPC2)<br />

The new CPC2 offers 40,190 sq. ft. (3,733 sq. m) of prestige Grade A office accommodation<br />

consisting of ground, first and second floors.<br />

The new development offers space to high-tech companies seeking a world renowned<br />

Cambridge address.<br />

Project Value: £500,000<br />

Main Contractor: Buckingham Group<br />

Services Included: Mains Cabling, Distribution, Generator, Containment, Lighting<br />

& Controls, Fire Alarm, Small Power, Feature Lighting, Intruder Alarm, Access<br />

Control, Photovoltaic Array, Car Charging Points, Lightning Protection, Disabled<br />

Refuge Alarm.