08.08.2020 Views

The Creighton Report

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Wagga Wagga Report

The original application was subject to extensive flood reporting and assessment to

determine the impacts associated with the proposed development. The conclusion of the

original assessments as reported to the Joint Regional Planning Panel was as follows: 159

The findings of the flood impact assessment shows that the proposed development is

compatible with the flood hazard of the land and will not significantly affect flood behaviour.

As a condition of consent it will be necessary for the applicants to prepare a flood evacuation

and management plan and that will incorporate measures to manage risk to life from flood.

The minor flood impacts are unlikely to have any significant adverse impact on the

environment or cause avoidable erosion, siltation, destruction of riparian vegetation or a

reduction in the stability of river banks or watercourses in the area. The area is already flood

prone and the risk of flood to the surrounding community is well known, the introduction of

this major recreation facility is not likely to result in unsustainable costs to the community as

a result of flooding.

Flooding is a natural phenomenon and whilst models are the most effective way of predicting

levels and impacts they remain an educated prediction. The flood will never behave exactly

in accordance with a model and therefore a degree of inaccuracy and variation should be

expected, accordingly current practice accepts that a flood impact of less than or equal to

0.02m can be assumed as negligible and in most cases accepted as model height variances.

The proposed development will be a valuable resource to the local economy and to the

regional harness racing industry. The impacts of flooding on this investment are clear and

the proposed mitigation in terms of raising key features of the development are considered

to be appropriate and acceptable in this case.

It was a condition of the consent (issued November 2015) that HRNSW, as the applicant of

the development, obtain the necessary flood work approval from Water NSW. HRNSW

engaged WMA Water to complete the required additional assessment which was completed

in August 2017. This was over two years since the original plans were prepared and

amendments to the layout of the clubhouse and surrounds had already commenced by the

applicants. The plans that were used by WMA Water to prepare the report of August 2017

were therefore those that are currently the subject of this modification. Whilst these plans

were not the approved plans (emphasis added), at the time they were the plans used for the

flood modelling and therefore the report provided (dated August 2017) in support of the

modification application was considered appropriate and acceptable. 160

The additional report was required to review the impacts on local catchment flooding not just

riverine flooding. The report was also to be based on the current levee height not the

completed raised levee as the original reports had been.

As noted, the modelling was based on the plans that are now included as a modification

application and included a solid colourbond steel fence to the track (excluding the southern

spectator and access area) of 1.2 metres in height that is designed to block water other than

for a 0.1 metre gap at the base of the fence. The assessment found that the solid boundary

fence would not significantly alter flood impacts.

In terms of riverine flooding, the findings of the report conclude that the modified layout

results in the same outcome as originally reported, that is that the flood impacts are no

159

Ibid pp 20-2.

160

Ibid.

39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!