Foreword<br />

Spread over two floors, Tallington Lodge is registered to provide<br />

personalised residential and dementia care. Tallington Lodge has been<br />

purpose built andsympathetically designed to blend in with the local area<br />

featuring a traditional stone frontage.<br />

The care home promotes a lifestyle for residents that offers<br />

beautiful, homely accommodation, whilst delivering the highest standards<br />

of personalised care. The care home has 31 en-suite bedrooms, with ground<br />

floor ‘superior rooms’ featuring patio doors leading out onto their own<br />

garden sitting area. Residents will also be able to enjoy a hair salon,<br />

garden boat-house and beautifully designed lounge and dining areas on<br />

both the ground and first floors.<br />

Situated on the edge of the beautiful Lincolnshire village of Tallington;<br />

Tallington Lodge <strong>Care</strong> Home provides residential and dementia care led<br />

by family values at it’s care in a beautiful, village setting.<br />

Ashley Cooper | Senior Partner<br />

2 3


Overview<br />

Month Zero | March 2018<br />

The existing site had many challenging aspects to<br />

overcome throughout the duration of the construction<br />

programme. Due to the recent completion to the First<br />

Phase of the <strong>Care</strong> Home, space for works were limiting.<br />

4 5


<strong>Completion</strong> of <strong>Demo</strong>lition works and foundation<br />

Month One | March 2018<br />

Works commenced on site on 1st March 2018. During the early weeks, completion of demolition<br />

and stripout works to the existing carehome were achieved; and foundation works commenced.<br />

Remedial works to the roof of the existing carehome were also undertaken within this month.<br />

6 7


Roof Installation, Masonry Works and<br />

Landscaping to existing building<br />

Month two | April 2018<br />

Good progress continued within this reporting period, as the completion of strip<br />

out works allowed for wall formwork to commence to the ground floor of the<br />

Second Phase. Additionally, preperations were made within the period for the<br />

installation of the acoustic flooring.<br />

8 9


<strong>Demo</strong>lition and Foundation installation to rear of site<br />

Month Three | June 2018<br />

Steady progress was made during the period, as wall formwork<br />

continued alongisde roof truss installation and internal plastering<br />

works to the existing home. Externally, the foundation works and<br />

demolition works to the existing works had concluded.<br />

10 11


Roof Covering to Existing <strong>Care</strong><br />

Home and Steelwork to rear of<br />

development<br />

Month Four | July 2018<br />

Good progress was made in the period, as roof truss installation<br />

to the front elevation had commenced to the front extension of<br />

the facility and roof covering works to the existing care home<br />

had achieved completion. Wall formwork to the extension of the<br />

development was nearing completion. Additionally, steelwork to<br />

the rear wing had commenced and foundations were poured<br />

to the rear of the site, where the bedroom extension is situated.<br />

Internally, first fix Mechanical and Electrical works commenced.<br />

12 13


First Fix M&E and Screed installation<br />

Month five | August 2018<br />

Works progressed well within the reporting period as roof truss<br />

installation was close to completion throughout. Blockwork to the rear<br />

extension had commenced and stonework existing building achieved<br />

completion. Sprinkler head installation and screeding works<br />

commenced within the period.<br />

14 15


16 17


Month Six | September 2018<br />

Good progress was made during the period, as roof truss installation had<br />

complete throughout and window installation had commenced. Internally, floor<br />

screed and wall plaster installation had taken place.<br />

<strong>Completion</strong> of Roof Structure and<br />

Commencement of Window Installation<br />

18 19


20 21


Second Fix Service Installation<br />

Month Seven | October 2018<br />

Plaster installation and floor screed progressed well within the period. Also, second<br />

fix service installation commenced alongside First Fix services. Preperation of external<br />

render installation took place during the reporting period.<br />

22 23


24 25


Commencement of Window Installation<br />

Month eight | November 2018<br />

Works progressed well within the period, as window<br />

installation achieved commenced and internal plastering works were<br />

close to completion. Internal finishing commenced and second fix<br />

installation to the services were well underway during the reporting<br />

26 27


28 29


<strong>Completion</strong> of Window Installation<br />

and commencement of internal finishes<br />

Month nine | December 2018<br />

<strong>Completion</strong> to window installation had been<br />

achieved throughout and installation to second<br />

fix services continued. Internal finishes were well<br />

underway and internal plaster works were nearing<br />

completion.<br />

30 31


Commencement of Air Testing<br />

Month Ten | January 2019<br />

Good progress was made during the period, as completion to internal finishes, plastering and<br />

second fix installation to services were achieved, which allowed for air testing to be undertaken.<br />

32 33


<strong>Completion</strong> of internal Fit out<br />

Month Eleven | February 2019<br />

On 4th February 2019,Practical <strong>Completion</strong> was achieved. Within this period<br />

internal fit out, plastering and internal finishes had now achieved completion and<br />

preparations were being made for the lift installation. Externally, hard lanscaping<br />

works had been undertaken.<br />

34 35


Link Frame Installation<br />

Month Twelve | March 2019<br />

Removal of existing roof over phase one had been undertaken to allow<br />

for the steel link frame to be installed, in order to connect Phase 1 & 2<br />

. Installation of the platform lift had been achieved within the period<br />

and minor remdial works to the external paving had been undertaken..<br />

36 37


Fit out of <strong>Care</strong> Home Link<br />

Month Thirteen | April 2019<br />

Within the period, plastering works and internal decoration were<br />

undertaken to the link, whilst completion of First Fix service<br />

installation and insulating of ceilings was achieved. Externally,<br />

rainwater goods had been installed.<br />

38 39


<strong>Completion</strong> to Link<br />

Month Fourteen | May 2019<br />

Delays occured within the reporting period due to inclement weather<br />

conditions which halted the installation of the glazing panels to the<br />

steel linking frame, which had a revised installation date of the 31st<br />

May 2019. During the period the date for practical completion was<br />

pushed back to 7 June 2019, due to client changes.<br />

40 41


Month Fifteen| October 2019<br />

On 17th October 2019, Combined Works Practical <strong>Completion</strong> of both Phase 1<br />

& 2 was achieved.<br />

Combined Works <strong>Completion</strong><br />

42 43


44 45


ECY Services<br />

Employer’s Agent<br />

Development Monitoring<br />

“WEALTH CREATORS IN LAND,<br />

PROPERTY & CONSTRUCTION“<br />

Project Management<br />

Development Consultancy<br />

Quantity Surveying<br />

Building Consultancy<br />

Land Sourcing<br />

Turnkey Services<br />

Fosse House |20 Prince William Road|Loughborough | Leicestershire | LE11 5GU<br />