Our company was founded by a civil engineer, Mr. Mustafa ÖZAYDIN, in

1993 in Isparta. Since its inception, our company aims to make better all the

time and so far it has succesfully completed a total of over 1.000.000 sqm

superstructure projects. As of today our company, operating with its young,

dynamic and expert staff, has been constructing a total area of 380.000 sqm

for the on going projects.


Our mission is; being a company that provides sources for its country and

staff and being a sample organisation with its hard-working, knowledge

and development.


Our vision is being a preffered company in our sector reflecting our

experience to the projects according to international standarts with our

young, dynamic, innovative structure together with our expert staff who

adopt development continuously as a principle.




Client:

Ministry of Sports

Date of Contract: 04.10.2017

Date of Completion: 05.01.2021

Contract Value: 15.330.361,35 USD

Construction Area: 30.802 sqm

Seating Capacity: 14.000



Client:

Ministry of Justice, Technical Works Department

Date of Contract: 01.03.2018

Date of Completion: 19.10.2020

Contract Value:

32.619.659,23 USD

Construction Area: 102.313,67 sqm



Client:

Ministry of Justice, Technical Works Department

Date of Contract: 03.01.2018

Date of Completion: 18.10.2020

Contract Value:

20.878.864,26 USD

Construction Area: 36.787 sqm



Client:

Governorate of Ordu

Date of Contract: 16.12.2016

Date of Completion: 11.08.2021

Contract Value:

11.305.888,06 USD

Construction Area: 38.706 sqm



Client: AKU Department of Conctruction and Technical Works

Date of Contract: 24.07.2018

Date of Completion: 31.07.2020

Contract Value: 2.795.491,73 USD

Construction Area: 9.650 sqm



Client

: Environment and Urban Ministry

Date of Contract : 30.08.2020

Date of Completion : 18.03.2021

Contract Value : 8.402.163,69 USD

Construction Area : 32.607,00 sqm



Client

: Ministry of Health

Date of Contract : 30.04.2020

Date of Completion: 16.10.2022

Contract Value : 28.061.994,41 USD

Construction Area : 76.680,98 sqm



Date of Contract: 01.09.2020

Date of Completion: 30.06.2022

Construction Area: 32.382,00 sqm



Date of Contract: 21.04.2019

Date of Completion: 31.12.2020

Construction Area: 20.725,00 sqm



NR. CLIENT NAME OF PROJECT

1

2

3

SDU DEPARTMENT OF

CONSTRUCTION AND

TECHNICAL WORKS

USAK UNIVERSITY DEPARTMENT

OF CONSTRUCTION AND

TECHNICAL WORKS

MAKU DEPARTMENT OF

CONSTRUCTION AND

TECHNICAL WORKS

SULEYMAN DEMIREL UNIVERSITY

CONSTRUCTION OF DINING HALL

USAK UNIVERSITY FACULTY OF SPORTS,STADIUM

AND ATHLETICS TRACKS

MEHMET AKİF ERSOY UNIVERSITY STADIUM AND

SPORTS CAMPING FACILITY

DATE OF

CONTRACT

DATE OF

COMPLETION

CONTRACT

VALUE (USD)

CONSTRUCTION

AREA

06.11.2017 26.07.2019 7.017.269,79 20.680,00

03.04.2017 10.12.2018 3.209.338,79 29.626,00

03.07.2017 30.09.2019 20.244.807,29 46.200,00

4 MUNICIPALITY OF AFYON HOTELS AND CAMPING FACILITIES 11.07.2016 17.11.2017 4.288.671,88 11.015,00

5

SULEYMAN DEMIREL

UNIVERSITY

BUILDING OF ECONOMICS AND ADMINISTRATIVE

SCIENCES FACULTY

11.03.2014 09.09.2016 11.932.243,15 26.850,00

6 AFYON KOCATEPE UNIVERSITY POLYCLINIC BUILDING 05.06.2013 02.10.2014 5.528.835,92 10.639,93

7

KUTAHYA DUMLUPINAR

UNIVERSITY

FOREIGN LANGUAGE SCHOOL 23.05.2013 17.10.2014 4.875.015,55 11.194,92

8 USAK UNIVERSITY CENTRAL MANAGEMENT BUILDING 20.09.2012 13.01.2014 3.587.872,28 6.275,19

9 GOVERNORATE OF YOZGAT POLICE COLLEGE 12.09.2012 28.09.2015 13.179.232,65 31.860,69

10 MINISTRY OF JUSTICE BURHANIYE PRISON FACILITIES 24.08.2012 13.06.2014 15.034.722,66 36.045,44

11

12

13

MEHMET AKIF ERSOY

UNIVERSITY

SULEYMAN DEMIREL

UNIVERSITY

GREAT MUNICIPALITY OF

GAZIANTEP

BUILDINGS OF VETERINARY CLINICS 15.08.2012 04.11.2014 5.550.027,38 10.934,98

LAW FACULTY BUILDING 14.06.2012 02.09.2013 3.470.711,38 13.043,39

UNDERPASS TUNEL PROJECT 05.05.2012 03.09.2012 4.543.794,46


NR. CLIENT NAME OF PROJECT

DATE OF

CONTRACT

DATE OF

COMPLETION

CONTRACT

VALUE (TRY)

CONSTRUCTION

AREA

14

MEHMET AKIF ERSOY

UNIVERSITY

SOCIAL ACTIVITIES BUILDING 07.06.2011 09.10.2013 7.775.476,80 19.552,00

15 AFYON KOCATEPE UNIVERSITY FACULTY OF FINEARTS AND CONSERVATORIES 29.09.2010 21.01.2013 10.477.185,26 25.563,00

16 AFYON KOCATEPE UNIVERSITY

200-BED PHYSIOTERAPY AND REHABILITATION

HOSPITAL

09.03.2010 31.05.2012 17.929.732,01 32.178,00

17

MEHMET AKIF ERSOY

UNIVERSITY

FACULTY OF SCIENCE AND LETTERS 07.08.2009 22.11.2011 13.479.902,95 33.970,00

18

SULEYMAN DEMIREL

UNIVERSITY

FACULTY OF DENTISTRY 13.05.2009 30.12.2010 6.289.780,07 23.300,00

19

SULEYMAN DEMIREL

UNIVERSITY

FACULTY OF FORESTRY 10.10.2008 31.12.2009 4.624.331,92 12.500,00

20

SULEYMAN DEMIREL

UNIVERSITY

POLYCLINIC BUILDING 15.05.2008 31.12.2009 11.171.699,38 17.500,00

21 GOVERNORATE OF BALIKESIR 300-BED HOSPITAL BUILDING 05.02.2008 17.11.2008 7.068.728,52 36.000,00

22 GOVERNORATE OF BALIKESIR BALIKESIR JUSTICE HALL 20.02.2007 11.10.2007 5.501.599,30 18.000,00

23 GOVERNORATE OF MUGLA HIGH SCHOOL BUILDING 26.07.2005 21.03.2008 2.967.934,37 14.000,00

24

AYDIN DIRECTORATE OF

EDUCATION

EFELER PRIMARY SCHOOL BUILDING 19.09.2003 09.01.2004 204.695,52 3.000,00

25 GOVERNORATE OF AYDIN SPORTS HALL 10.10.2002 10.09.2003 1.221.001,22 7.000,00