23.12.2012 Views

Galloper Substation - Seaway Heavy Lifting

Galloper Substation - Seaway Heavy Lifting

Galloper Substation - Seaway Heavy Lifting

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Galloper</strong> <strong>Substation</strong><br />

The Greater Gabbard Offshore Wind Farm is developed by SSE in a joint venture with RWE npower<br />

renewables. The wind farm includes 140 wind turbines and two substations (Gabbard and <strong>Galloper</strong>),<br />

which are located around two sand banks known as Inner Gabbard and <strong>Galloper</strong> in the North Sea,<br />

12 nm off the Suffolk Coast. To date, Greater Gabbard is the biggest offshore wind farm, located in<br />

water depths of 22 - 32 m and covering an area of 146 km 2 .<br />

Since 1992, <strong>Seaway</strong> <strong>Heavy</strong> <strong>Lifting</strong> (SHL) has built respected experience in the oil and gas market.<br />

As a marine contractor, SHL has completed over one hundred platform installations and removals<br />

throughout the world. SHL owns and operates the monohull crane vessels “Stanislav Yudin”<br />

(2,500 mt revolving), the “Oleg Strashnov” (5,000 mt<br />

revolving) and all key installation equipment like<br />

piling hammers and handling tools. SHL’s vessels<br />

are able to work under harsh offshore conditions,<br />

and these vessels are perfectly suited for the<br />

installation of substations and different types of<br />

wind turbine foundations. For each project, SHL’s<br />

experienced team develops the most safe, reliable<br />

and economical offshore installation method.<br />

As part of the installation subcontract with Fluor Ltd. (Fluor), SHL transported and installed the<br />

<strong>Galloper</strong> substation in early June 2010. Both jacket and topside were transported to the offshore<br />

field on cargo barges: the jacket and piles from Methill, and the topside from Hartlepool.<br />

Once the jacket was set on the seabed, the four lead section foundation piles (diameter: 54”,<br />

length: 67.5 m) were stabbed in the designated jacket legs and were driven to penetration by means<br />

of SHL’s IHC S-600 piling hammer. The add-ons (length: 30.0 m) were stabbed in and welded to the<br />

lead sections after which all foundation piles were driven to final penetration of 60 m. After levelling,<br />

using SHL’s levelling tools, the piles were welded to the jacket and the final cut-off was made.<br />

The topside was installed immediately following jacket installation completion. The entire operation,<br />

from receiving the first cargo barge alongside the Stanislav Yudin until completion of the substation<br />

installation, took only 8 days. The topside was installed fully tested and commissioned by the<br />

fabricator at the fabrication yard.<br />

The selection of a conventional platform design installed with a heavy lift vessel (HLV) proved to be the<br />

best choice to meet the project schedule and allowing for flexibility under a lump sum installation contract.


Project details<br />

SCOPE Transport and installation of <strong>Galloper</strong> substation<br />

DIMENSIONS Topside weight mt 1,650<br />

Jacket weight mt 790<br />

Pile dimensions main piles four in total<br />

Pile weight mt 150<br />

Pile length m 97.5 (lead section + add-on)<br />

Pile diameter in 54<br />

Pile penetration m 57.5<br />

WATERDEPTH m (LAT) 23.0<br />

FABRICATION Topside Newcastle, England<br />

Jacket & piles Methill, Scotland<br />

CLIENT main contractor Fluor Ltd.<br />

INSTALLATION PERIOD June 2010<br />

INSTALLATION SPEED days 8<br />

Key benefits of substation installation with HLV<br />

• Highest offshore workability<br />

• Safe, reliable and proven installation solution<br />

• Full flexibility, capable of maintaining project schedule<br />

• Enable most economical jacket and topside design<br />

• Limit restrictions on fabrication yard and offshore cargo barges<br />

• Topside fully tested and commissioned prior to installation<br />

All specifications are subject to change without notice. No rights can be derived from this information. October 2010.<br />

<strong>Seaway</strong> <strong>Heavy</strong> <strong>Lifting</strong> Engineering B.V.<br />

Albert Einsteinlaan 50, 2719 ER Zoetermeer,<br />

The Netherlands<br />

Tel: +31 (0)79 363 77 00<br />

Fax: +31 (0)79 363 77 99<br />

www.shl.com.cy

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!