03.02.2021 Views

Water & Wastewater Asia March/April 2019

Water & Wastewater Asia is an expert source of industry information, cementing its position as an indispensable tool for trade professionals in the water and wastewater industry. As the most reliable publication in the region, industry experts turn this premium journal for credible journalism and exclusive insight provided by fellow industry professionals. Water & Wastewater Asia incorporates the official newsletter of the Singapore Water Association (SWA).

Water & Wastewater Asia is an expert source of industry information, cementing its position as an indispensable tool for trade professionals in the water and wastewater industry. As the most reliable publication in the region, industry experts turn this premium journal for credible journalism and exclusive insight provided by fellow industry professionals. Water & Wastewater Asia incorporates the official newsletter of the Singapore Water Association (SWA).

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

26 | FROM THE GROUND<br />

The 38-ton pump with an impeller diameter of 1,905mm<br />

One of the original KSB ME plants that was installed when the plant was first constructed<br />

of Montreal requested that KSB submit a<br />

tender for another pump of the same design<br />

and capability.<br />

Unfortunately, after such a long interval, the<br />

original pumps were no longer in production.<br />

However, KSB circumvented the issue by<br />

coming up with a plan that involved making<br />

an updated replica – a proposal that ended<br />

in them winning the order.<br />

KSB’S MEF PUMP<br />

Constructed in accordance with customer<br />

specifications, the KSB MEF pump is a<br />

vertical split-case, single stage pump, that<br />

is an updated version of the original pumps<br />

supplied in 1975.<br />

The footprint and layout of the new pump<br />

resembles its older counterparts, but up-todate<br />

seals and optimised hydraulic elements<br />

have enhanced its reliability and improved<br />

operating efficiency. Duplicating the older<br />

pump configuration also simplified the<br />

installation of the new unit in the Charles-<br />

J.-Des Baillets high-pressure pump gallery.<br />

Having secured the contract, KSB<br />

manufactured the new MEF pump in Brazil,<br />

and shipped out the 38-ton pump with an<br />

impeller diameter of 1,905mm in late 2013.<br />

With a drive shaft measuring 5 metres in<br />

length and operating at a fixed speed of 400<br />

rpm, it delivers 4.2m³ per second at a head of<br />

67m. Initially planned to be used as a backup<br />

unit, the pump also operates in parallel<br />

with the existing large-capacity pumps. Due<br />

to its size, the pump had to be disassembled<br />

for shipment and reassembled on site.<br />

In <strong>April</strong> 2015, work commenced on the<br />

assembly and installation of the pump at<br />

the Charles-J.-Des Baillets water filtration<br />

plant under KSB’s supervision. Between<br />

May 2015 and <strong>April</strong> 2016, installation of the<br />

5,500 HP synchronous motor and line shaft<br />

was performed by the mechanical contractor.<br />

The next phase was the commissioning<br />

and configuration of the control panels and<br />

auxiliary electrical components undertaken<br />

between <strong>April</strong> 2016 and September 2017,<br />

with performance and acceptance tests of the<br />

pump conducted in October 2017.<br />

The hydraulic acceptance tests were<br />

performed on the new pump unit with<br />

the scope of the tests being to verify the<br />

contractual efficiency guarantee point of 87<br />

per cent at 4.2 m³/s. Summarising the key<br />

results, at the rated flow of 4.2m³ per second,<br />

the pump efficiency was 90.4 per cent; 3.4<br />

per cent greater than the guarantee efficiency<br />

of 87 per cent. The results show that the<br />

performance of the pump GP5 fulfilled the<br />

contractual guarantee obligations.<br />

CHALLENGES<br />

Installing the new pump set was not without<br />

its challenges, given that the area allocated<br />

was between two existing units and involved<br />

a three storey, open high-pressure pump<br />

gallery, and the excavation of foundations to<br />

accommodate the water intake pipework and<br />

pump volute.<br />

The pump gallery was constructed on three<br />

storeys with the motors and the control<br />

panels mounted on the upper floor and the<br />

pumps three storeys directly below on the<br />

bottom level. A five-metre-long drive shaft<br />

from the 5,500 HP motor on the upper<br />

floor couples to the pump below. Because<br />

the new pump had the same hydraulic<br />

configuration as its older counterparts, it was<br />

installed alongside them in exactly the same<br />

arrangement.<br />

KSB engineers played a significant<br />

role in overseeing the installation and<br />

commissioning of the new pump as the<br />

process was somewhat complicated by<br />

the ingress of water from the adjacent<br />

underground supply reservoir. Each pump<br />

intake was secured by two sets of stop logs,<br />

as compared to large gate valves, creating a<br />

serious problem with water infiltration into<br />

each intake chamber in which the pumps<br />

are mounted. Thus, it was necessary for<br />

the safety of the engineers and the<br />

construction personnel to continually pump<br />

water from the foundations during the<br />

construction of the intake chamber of the<br />

new pump.<br />

CUSTOMER SATISFACTION<br />

According to an engineer from the City of<br />

Montreal’s water department, the addition<br />

of the new pump provides more redundancy<br />

to the system.<br />

<strong>Water</strong> & <strong>Wastewater</strong> <strong>Asia</strong> • <strong>March</strong> / <strong>April</strong> <strong>2019</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!