23.06.2021 Views

ASPHALTopics | Summer 2021 | VOL 34 | NO 2

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

a grader, the company laid down the new asphalt in echelon using two ten-foot<br />

pavers and a Material Transfer Vehicle, two steel rollers, two rubber tire rollers,<br />

and a tack truck.<br />

“We were fortunate in that the base was actually in very, very good shape and<br />

didn’t require a lot of Granular A,” Cote says. “So we were able to basically regrade<br />

the existing compacted aggregate and then be ready to pave it.”<br />

The intersection between the two runways was a bit more difficult. Within the<br />

five day closure window, Miller Paving had to remove the original asphalt, place<br />

approximately 3,000 tonnes of Granular A to raise the crown of the intersection by<br />

about 100 mm to improve drainage, then place 125 mm of HMA in two lifts (75 mm<br />

and 50 mm) followed by line painting and<br />

ramping.<br />

“The five day closure was the toughest<br />

to deal with,” Cote explains. “We<br />

completed the work with about four<br />

hours to spare. But the situation could<br />

have been worse — it started to rain<br />

about an hour after we finished. Had<br />

the rain begun earlier, it could have<br />

delayed our completion by days.”<br />

Towards the end of Miller Paving’s<br />

2020 efforts, Timmins’ northern climate<br />

began to become an issue. “This area<br />

may not be that far north, but it is very<br />

windy,” says Cote. “This wind would<br />

cool down the asphalt very quickly. It<br />

was a problem because the delays to<br />

the mix design meant that we weren’t<br />

able to start paving until mid-August,<br />

when the best part of the summer had<br />

already passed. We paved until the end<br />

of September, at which point the winds<br />

and falling temperatures were having a<br />

real impact.”<br />

RESULTS TO DATE<br />

Despite the many challenges<br />

encountered in 2020, the Timmins<br />

Airport project hit its goals. Airport<br />

manager David Dayment credits this<br />

success to Miller Paving’s willingness<br />

to work closely with the City of Timmins,<br />

plus the paving company’s tenacity in<br />

getting things done.<br />

“The guys were very attentive to our<br />

operational needs,” says Dayment.<br />

“They worked through some weekends<br />

to stay on schedule. They were prepared<br />

to work evenings and into weeknights if<br />

they had to, but fortunately things never<br />

got that far. Meanwhile, the runway and<br />

taxiways got paved and restored to peak<br />

condition — and ready to accommodate<br />

737s and other large aircraft.”<br />

20 OAPC | ASPHALTOPICS<br />

As for <strong>2021</strong>? “The last phase of the<br />

Timmins Airport paving project consists<br />

of the ends of Runway 10-28, which<br />

includes the removal of existing asphalt,<br />

regrading and placing approximately<br />

14,000 tonnes of asphalt as well as line<br />

painting,” Cote says. “Just the ends<br />

of that runway — everything else has<br />

already been done!”

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!