ASPHALTopics | Summer 2021 | VOL 34 | NO 2
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
a grader, the company laid down the new asphalt in echelon using two ten-foot<br />
pavers and a Material Transfer Vehicle, two steel rollers, two rubber tire rollers,<br />
and a tack truck.<br />
“We were fortunate in that the base was actually in very, very good shape and<br />
didn’t require a lot of Granular A,” Cote says. “So we were able to basically regrade<br />
the existing compacted aggregate and then be ready to pave it.”<br />
The intersection between the two runways was a bit more difficult. Within the<br />
five day closure window, Miller Paving had to remove the original asphalt, place<br />
approximately 3,000 tonnes of Granular A to raise the crown of the intersection by<br />
about 100 mm to improve drainage, then place 125 mm of HMA in two lifts (75 mm<br />
and 50 mm) followed by line painting and<br />
ramping.<br />
“The five day closure was the toughest<br />
to deal with,” Cote explains. “We<br />
completed the work with about four<br />
hours to spare. But the situation could<br />
have been worse — it started to rain<br />
about an hour after we finished. Had<br />
the rain begun earlier, it could have<br />
delayed our completion by days.”<br />
Towards the end of Miller Paving’s<br />
2020 efforts, Timmins’ northern climate<br />
began to become an issue. “This area<br />
may not be that far north, but it is very<br />
windy,” says Cote. “This wind would<br />
cool down the asphalt very quickly. It<br />
was a problem because the delays to<br />
the mix design meant that we weren’t<br />
able to start paving until mid-August,<br />
when the best part of the summer had<br />
already passed. We paved until the end<br />
of September, at which point the winds<br />
and falling temperatures were having a<br />
real impact.”<br />
RESULTS TO DATE<br />
Despite the many challenges<br />
encountered in 2020, the Timmins<br />
Airport project hit its goals. Airport<br />
manager David Dayment credits this<br />
success to Miller Paving’s willingness<br />
to work closely with the City of Timmins,<br />
plus the paving company’s tenacity in<br />
getting things done.<br />
“The guys were very attentive to our<br />
operational needs,” says Dayment.<br />
“They worked through some weekends<br />
to stay on schedule. They were prepared<br />
to work evenings and into weeknights if<br />
they had to, but fortunately things never<br />
got that far. Meanwhile, the runway and<br />
taxiways got paved and restored to peak<br />
condition — and ready to accommodate<br />
737s and other large aircraft.”<br />
20 OAPC | ASPHALTOPICS<br />
As for <strong>2021</strong>? “The last phase of the<br />
Timmins Airport paving project consists<br />
of the ends of Runway 10-28, which<br />
includes the removal of existing asphalt,<br />
regrading and placing approximately<br />
14,000 tonnes of asphalt as well as line<br />
painting,” Cote says. “Just the ends<br />
of that runway — everything else has<br />
already been done!”