APRIL - JUNE EXTERNAL NEWSLETTER
MILESTONES
2016 - 2021 SERVICE DELIVERY
UMANY ANO K U PHUHL ISO
Amathole District Municipality brings you this booklet
to present the Service Delivery Milestones attained
by the current council since it took to office in 2016.
The Amathole District Municipality as a Water Services
Authority and Water Services provider, plans,
constructs and operates water and sanitation services
in 6 Local Municipalities under its jurisdiction.
Though predominantly rural in its nature, the district
is working tirelessly to ensure all our communities
has access to services.
Introduction
2
Our
Vision
3
THE ADM VISION
Here at Amathole, we subscribe to a vision of:
"Commitment towards selfless, excellent and
sustainable service to all our communities"
The above statement is an aspirational description of
what our municipality would like to achieve or accomplish
in the mid-term and long-term future. It is
intended to serves as a clear guide for choosing current
and future courses of action, projects and how
we respond to the needs of the district and its constituency.
MISSION
The Amathole District Municipality, in its
developmental mandate, is dedicated in contributing
to: Ensuring access to socio-economic opportunities.
Building the capacity of local municipalities within
ADM’s area of jurisdiction.
Ascribe to a culture of accountability and clean
governance.
Sound financial management.
Political and administrative interface to enhance
good service delivery.
Contributing to the betterment of our communities
through a participatory development process.
The above statement is what defines the present
state or purpose of our municipality.
In short the mission answers why we exists -
Selflessness
We will commit and dedicate ourselves to the
provision of services to our community.
Pro-poor
The poorest of the poor will be the main focal point
for ADM’s business and service delivery.
Responsiveness
We will continue to strive for improved turnaround
time in the delivery of services and in dealing with
our valuable customers.
Transformative
We will make considerable strides to ensure
sufficient institutional capacity
(skills and human capital) to effect transformation.
VALUES
Inclusivity
We will include all our stakeholders in our planning,
implementation, monitoring, evaluation and reporting
in ensuring an integrated effort towards service delivery.
• Dignity and respect
• We will ensure that our service delivery restores
human dignity and respect.
• Good work ethics
• We will be professional in our conduct and
ascribe to the Batho Pele principles.
• Transparency
• Throughout our business operations we will ensure
access to information and fairness to our
stakeholders.
• Integrity
• We will constantly conduct ourselves with utmost
integrity as councillors and officials of ADM.
• Accountability
• We are committed to being held to account by our
stakeholders.
Foreword
by
Executive
Mayor
4
2021 marks the end of our five (5) year term as the
political leadership of Amathole District Municipality
which requires us to account to you as our valuable
stakeholders the strides made in addressing service
delivery backlogs since we took to office in 2016. This
service delivery milestones booklet incorporates our
grant spending patterns which have resulted in the
implementation of a number of projects across the
district some of which are still ongoing. Our country
and the global community at large is faced with a
health pandemic and other related socio-economic
challenges. Ofcourse, challenges which comes with
this new normal are plenty but we remain confident
that we can overcome. Ours is not to despair but to
employ measurers to mitigate against the impact
whilst attending to the needs of our communities on
the ground.
Against the persistent drought and related challenges,
we have strived to use all resources at our disposal
to bring services closer to our people, especially
those who stay in the periphery of our rural district.
We remain committed to work tirelessly through innovative
and creative ways to ensure our infrastructure
meet the required standards. The municipality is
at an advanced stage of implementing projects that
will provide new infrastructure, rehabilitation and
upgrading of existing ones, as well as improve water
management infrastructure.
Since 2016/17 financial year to date, 12 888 households
have been provided with basic level of water
supply and 75 091 households with basic level of
sanitation across the District. More than 10 900 work
opportunities were created during the implementation
of both water and sanitation projects. As part of
our commitment to restore dignity of our people, we
vowed to make bucket system a thing of the past in
this district. As such 874 bucket systems have been
eradicated in Raymond Mhlaba and Great Kei.
With the Department of Water and Sanitation finally
approving a budget of R725 million for the implementation
of Ngqamakhwe Regional Water Supply
Scheme which entails the construction of bulk water
supply from Tsomo to Ngqamakhwe, we are certain
that once all phases of this Scheme are completed,
water will be provided to approximately 78,534
people in the Ngqamakwe rural supply, 49,325 people
for the Cluster 8 area within CHDM and 44,040
people within the Butterworth urban supply area. Under
Mbhashe Local Municipality, Xhora water Supply
Scheme is under construction, completed to date is
the dam and Water Treatment works. Once the entire
project is complete it will serve approximately 133
rural villages with a population of about 66,900 in
8,082 households.
Indeed the new normal has presented challenges in
the traditional way that we interact with our communities,
in that the lockdown regulations prevented us
from convening face-to-face gatherings. However,
we are happy with how the people of Amathole have
responded to various digital platforms such as our
community radio stations and various social media
platforms. These efforts have enabled a wider reach
of citizens and our stakeholders. We want to encourage
and thank our communities and stakeholders for
their active participation in the affairs of the municipality.
Together, we have developed strategic documents
that have potential to stand the test of time when it
comes to changing the lives of our people for the better.
These include:
•Vision 2058: Building a Smart District with its clear
Catalytic Projects
•The Municipal Turnaround Strategy
•Economic Growth and Development Strategy and its
Sector Plans.
•I must also mention the successful hosting of the
District-Wide Water Indaba, District-Wide Economic
Growth and Development Summit and the Post COVID
19 Economic Stimulus.
local government that is responsive, accountable,
effective and efficient in serving the people of Amathole.
Hence in the year 2021/2022, we will spend
R590 million on Capital Projects focused on Water
and Sanitation throughout the district. We are confident
that through these and other projects and programmes,
we will succeed in playing our role to create
a better life for the people of the district.
All of what we have achieved and that which we will
still achieve and count amongst our legacy would not
have been possible without the support of our strategic
partners and our communities at large. For this I
want to thank all of them and plead for more support,
collaborations and cooperation. I also want to thank
the entire Council of ADM together with leadership of
our local municipalities for the commitment and for
never failing to provide strategic leadership even under
difficult periods. Lastly, let me extend a word of
gratitude to the administration as led by the Municipal
Manger, for their outstanding work in the execution
of the mandate bestowed upon us.
Thank You.
EXECUTIVE MAYOR:
Cllr. K.C. Maneli
All these achievements, were efforts aimed at fulfilling
the promise we made to ourselves - to turn ADM
around and restore it to its former glory. As our IDP
together with SDBIP and Budget reflect, we stand
committed in building a capable and developmental
5
Executive
Summary
By
Municipal
Manager
6
The service delivery milestones booklet provides an
opportunity to account on the path that has been
traversed by Council in the past five years.
The Local Government sphere is in its last cycle for
the current term of Municipal Councils with the
upcoming local government elections which will
usher in the 6th term.
During this current term, Amathole District
Municipality has set a strong foundation of its long
term plan of Envisioning an Amathole Smart District
towards 2058, known as “Vision 2058: Building
a Smart District”. One of the key enablers towards
2058 is building Strategic Partnerships which share
in our vision and can contribute to its realization.
ADM has forged partnerships with the ECDC, Municipal
Infrastructure Support Agency, GIZ through the
Governance Support Programme II and the University
of Fort Hare in this regard. Further to these engagements
with Infrastructure South Africa have been undertaken.
A critical milestone has been the development and
implementation of the Municipal Turnaround
Strategy (MTAS) to “Bring ADM Back to its Former
Glory” since 2018, following the development of a
Diagnostic Report together with the Municipal Infrastructure
Agency (MISA). ADM has made a footprint
in all pillars of the MTAS Framework, however the Organisation
Development and Design has been slow in
the attainment of the targets against the timeframe
set. In the year under review there has been acceleration
towards the development of Job Descriptions and
Job evaluation process. The next phase of migration
into the staff establishment will be the focus area. In
addition, ADM will explore various funding options of
the Mutual Separation Agreement as means to cut the
Cost of Employment.
Amathole District Municipality continues to render
services in the provision of water and sanitation services
as both a Water Services Authority (WSA) and
a Water Service Provider (WSP), which are functions
assigned for us to implement without fail. Drought in
the district is still upon us and therefore continuous
effects are made to lobby funding for the Sustainable
Water Solution and addressing the refurbishment of
the aging infrastructure. Through the various grants
such as Regional Bulk Infrastructure Grant (RBIG)
and Municipal Infrastructure Grant (MIG), ADM continues
to address infrastructure backlogs especially
in the Eastern Region of the District.
COVID-19 Pandemic has put water and sanitation
provision in the spotlight. Some of the solutions
being implemented are as per the outcomes of the
Water and Sanitation Indaba held in 2019. There has
been temporary solution such as water carting and
allocation of water tanks in strategic locations to ensure
accessibility of this scarce resource to ADM’s
communities. Further to this there has been drilling
of boreholes as part of exploring the underground
water sources. In the long term, the development of
the Aqua/Solar Hybrid Sea Water Desalination Plant is
the sustainable water solution for the entire District
including the construction of the Fox Wood Dam in
Raymond Mhlaba.
The 2020 Institutional Strategic Planning Session
held in February 2021 in close cooperation with our
six local municipalities and our strategic stakeholders
provided an account of the path that have been
traversed by the institution during this current term
and to develop a clear plan for the next financial year,
looking towards the 6th Term of Local Government.
ADM Council has been faced with many challenges
ranging from financial constraints, service delivery
protests and labour unrests. Further to this, the
COVID-19 Pandemic has forced the Municipality to
think outside the box and be innovative and creative
in service delivery. To ensure business continuity and
communication internally and externally Information
and Communication Technology became the key enabler.
In fulfilment of its responsibilities, ADM’s Institutional
Strategic Planning Session resolved that the 2021/22
Strategic Focus areas as the:
•2021 Service Delivery Outreach Programme
•Satellite Office Outreach Programme
•Initiation of Labour Relations Act Section 189
discussion
•Streamlining ADM Service Delivery model to two
options
7
•Capacity Assessment of Local Municipalities for the
devolving of Fire Services function for their
implementation
•Capacity Assessment and devolving of Regional
Waste disposal sites to Mnquma Local Municipality
•Supporting the Section 139 (5) (a) Eastern Cape
Provincial Government intervention and Section 154
requested from National and Provincial Government
•Communication and Marketing of ADM and ASPIRE
Programmes
Further to this, the following focus areas still remain
matters of emphasis, namely:
•Effective Satellite Office Model
•Building ADM as a Smart District
•Resource Mobilisation
•Service Delivery and Infrastructure Investment
•Organisational Development and Re-design
•Implementation of Financial Recovery Plan
•Revenue Enhancement
•Focus on Core functions
•Planning, ICT, Communication and Financial Systems
•Stakeholder Relations and Public Participation
Amathole District Municipality has welcomed the
Eastern Cape Provincial Government invoking of Section
139 5(a) into Amathole District Municipality and
Council has further resolved to officially request support
from National and Provincial Government in line
with the 154 of the Constitution. As ADM, we view this
intervention as strengthening of the Municipal Turnaround
Strategy.
While the National Treasury is developing the Mandatory
Financial Recovery Plan to be implemented
by Amathole District Municipality, ADM continues to
implement its Voluntary Financial Recovery Plan as
a move towards a financially sustainable institution.
More than ever before, the impact of COVID-19
pandemic resulted in the development of the Post
COVID-19 Economic Recovery Plan as part of creating
a conducive environment to diversify the District’s
economy thus contributing to various Revenue
Enhancement sources and mechanisms.
ADM’s Development Agency, ASPIRE, will continue
to be the driving machinery of the District catalytic
and strategic projects. This is part of strides of Envisioning
an Amathole Smart District towards 2058 informed
by the opportunities presented by the Fourth
Industrial Revolution (4IR) of Smart Solutions in providing
service delivery in an efficient, economical and
effective manner to the communities of Amathole
District Municipality.
Going into the next term of administration, ADM will
continue to make strides in the alignment of Vision
2058, Municipal Turnaround Strategy and the District
Development Model by utilizing the IDP as its implementing
tool.
Indeed, the past four years has not been an easy journey,
it had its ups and downs, successes and failures
but the interface between Political and Administrative
leadership is the anchor of “Bringing ADM Back
to its Former Glory”.
MUNICIPAL MANAGER
Dr. T.T Mnyimba
SERVICE
DELIVERY
MILESTONES
MANDELA MONTH ACTIVITIES:
Members of the community appreciates the
strides taken by ADM to the destitute homes
AWARENESS CAMPAIGNS:
Awareness campaign on bulk water
usage were held to save water and
to prevent vandilism
8
INDIGENT REGISTRATION:
Communities from rural areas are
encouraged to register and benefit from
the government.
DROUGHT INTERVENTION:
Water Supply augmentation through drilling and
equiping of boreholes
LAUNCH OF PROJECTS:
Another way of political leadership to interface
with communities.
IDP/BUDGET ROADSHOWS:
IDP and budget are presented to the
communities in the interest of promoting
transparency and accountability.
WATER FORUM:
Where water issues are discussed.
MAYORAL IMBIZO:
The Executive speaks with communities on
matters of governance.
9
COMMUNITY MEETING:
A platform for the Executive to interface with
communities on matters of governance
ANNUAL REPORT ROADSHOWS
The institution reports back to communities
on expenditure patterns
SODA:
Platform for the Executive Mayor to address
successes of the district and points out
projects to be implemented
HOUSEHOLD BENEFITED
2016-2020
SERVICES PROVIDED (NO. HOUSEHOLDS) 2016/17 2017/18 2018/19 2019/20 2020/21
(end Dec 20)
Total
Water 3 612 2 231 5 709 1 336 0 12 888
Sanitation 1 537 21 916 13 819 25 815 12 004 75 091
10
FINANCIAL
YEAR
2016/2017
11
COMPLETED WATER PROJECT - 2016/2017 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Ngqushwa Water Services Reticulation Ngqushwa Mthombe, Gobozane, Wesley,
Qaukeni, Macibi, Kwa Pelisile,
Ntilini, Zalara, Tamara B & C, Nonibe,
Qaga, Masele, Cross roads,
Tyityaba, Hoyi, Woolbridge, Tuku B,
Lovers Twist, Mtati, Lujiko1 &
2, New Loots, Nqula, Daninge B,
Wesley Mbekweni, Mgwalana,
Upper and Lower Gwalana,
Mahlubini, Celetyume, Nqwenerana,
Cisira, Ncala, Forosi, Mgwangqwa,
Mxaxa, Magqwazeni.
1452 R 50 824 773
Ngqamakhwe Phase 1 Contract 1 Mnquma Elalini, Mtonjeni and Komkhulu 621 R 3 475 836
Gcuwa West Water Supply Mnquma Ndenxa, Hewu, Cegcuwana,
Mahlubini
845 R 5 354 499
Prudoe Ngqushwa Prudoe 448 R 7 506 075
Gcuwa West Phase 1 Contract 2 Mnquma Mzantsi Village, Mzantsi Est,
Ntshamanzi, Ngomanzi.
246 R 31 199 251
TOTALS 3612 R 98 360 433
12
13
COMPLETED SANITATION PROJECT - 2016/2017 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mnquma RHIG Sanitation Mnquma Mgomanzi No. 6 Village (92 HH)
Phase 1 Contract 1
400 R 4 000 000
Mbhashe RHIG Sanitation Mbhashe 400 R 4 007 360
Ngqamakhwe Ward 17 & 19 Sanitation Project Mnquma Ward 17
(Skolweni, Lalini,
Toboyi, Mission, Kunene & Merelisa,
Ngcangcathelo)
190 R 1 805 000
Seymor Ext 6 Sanitation Raymond Mhlaba Seymor Ext 6 420 R 2 000 000
Komga Commonage Settlement Great Kei Komga 127 R 1 206 500
TOTALS 1537 R 13 018 860
14
FINANCIAL
YEAR
2017/2018
15
COMPLETED WATER PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mgwali South Water Supply Mbhashe Ntlambonkulu and Mngomazi. 643 R 23 300 941
Gcuwa West Water Supply Mnquma Komanishini, Goso, Ezibondeni, and
R Five Village
394 R 32 805 640
Ngqamakhwe Water Supply Scheme Phase 1
Contract 1
Mnquma Biyana, Rwantsana and Bolani 420 R 57 029 092
Xhora Water Supply Scheme Mbhashe 774
TOTALS 2 231 R 113 135 673
16
17
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Raymond Mhlaba Area Wide Sanitation
Region 3A
Raymond Mhlaba
Lushngton/Elukhanyisweni,
Khayelitsha, Ekuphumleni Hertzog
Elundini, Machibini, Siphingweni,
Chamama, Komkhulu, Mdeni,
Mkhuthukeni, Mqayise, Ngwangwane,
Mdlankomo, Phatikhala, Ekuphumleni,
Tyeni, Edika /Kolomane,
Phillipton, Fairbain, Votyiwe/Kolomane,
Tshokotshela, Reads dale,
Buxton Balfour Old Structures,
Maasdorp Jurieshoek, Marais .
4 192 41 081 600,00
Amahlathi Area wide Sanitation Projects
(Region 2A)
Amahlathi
Ward 7(Qolweni, Nyingane1, 2 and
3) Ward 8 (Khayelitsha)Ward 9
(Fresh Waters/ Zwelitsha, Fresh
Waters, Mabhele),Ward 12
(Frankfort; Hokwana )
3 473 34 035 400,00
18
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Amahlathi Area wide Sanitation Projects
(Region 3A)
Amahlathi
Ward 5 (Toise Bongweni,Toise
Ndlovini, Toise Ndumangeni), Ward
6 (Kubusie Zidenge, Lepile, Ohlssons)
Ward 8( Nonkululeko) Ward
9 (Mgwali 3, Gasela Poto, Gasela
Betya, Gasela Nqambo, Ndakana
Stan hope) Ward 13 (Mgwali 1 and
2, Heckel)
2 241 21 961 800,00
Mnquma Area wide Sanitation Region 3A Mnquma Ward 16 (Nofotyo Qwanguleni,
Ngcisininde Komkhulu, Ngcisininde
New Town, Ngcisininde Polar Park,
Ngconde Mangobomvu, Ngconde
Nobanda, Ngculu Ntwasu, Hili hili
Bolani) - Ward 18 (Mpahleni Ntwala,
Mpahleni Mndeni, Mpahleni
Kwasajini, Upper Mpahleni, Lower
Mpahleni, Mpahleni Mpundu,
Mpahleni Mkhwezeni, Mpahleni Eziflathini,
Mpahleni Ngcwazi, Mpahleni
Ntibane) - Ward 20 (13 Villages)
Ward 6 (Mcubakazi).
4 302 42 159 600,00
19
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Amahlathi Area wide Sanitation Projects
(Region 3A)
Amahlathi
Ward 5 (Toise Bongweni,Toise
Ndlovini, Toise Ndumangeni), Ward
6 (Kubusie Zidenge, Lepile, Ohlssons)
Ward 8( Nonkululeko) Ward
9 (Mgwali 3, Gasela Poto, Gasela
Betya, Gasela Nqambo, Ndakana
Stan hope) Ward 13 (Mgwali 1 and
2, Heckel)
2 241 21 961 800,00
Mnquma Area wide Sanitation Region 3A Mnquma Ward 16 (Nofotyo Qwanguleni,
Ngcisininde Komkhulu, Ngcisininde
New Town, Ngcisininde Polar Park,
Ngconde Mangobomvu, Ngconde
Nobanda, Ngculu Ntwasu, Hili hili
Bolani) - Ward 18 (Mpahleni Ntwala,
Mpahleni Mndeni, Mpahleni
Kwasajini, Upper Mpahleni, Lower
Mpahleni, Mpahleni Mpundu,
Mpahleni Mkhwezeni, Mpahleni Eziflathini,
Mpahleni Ngcwazi, Mpahleni
Ntibane) - Ward 20 (13 Villages)
Ward 6 (Mcubakazi).
4 302 42 159 600,00
20
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mbhashe Area Wide Sanitation Region 2B Mbhashe Ward 17 (Ganyamanzi,Qingqala,
Lower Bufumba, Mbukuqweni,
Wawa); Ward 18 (Phuthuma,);
Ward 19(Mpame, Mdikane) Ward
28(Folokhwe, Tshezi, Mbutye, Bafazi)
1 600 15 680 000,00
Mbhashe Area Wide Sanitation Region 2C Mbhashe Mwana, Njiveni, Mdizeni, Hlakothi,
Vuyisile, Qatywa, Ngubezulu, Ekukwezeni,
Sibonda, Manqanyeni,
Ncihana Block 4
2 325 22 785 000,00
21
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mbhashe Area Wide Sanitation Region 3B Mbhashe Ward 29 Mpume, Ngqeza, Ngwane,
Mtokwane, Nondobo, Ntubeni/
Plaatyi, Ngomane, Ward 24 Lower
Gwadu, Nomawaka, Mbozi, Phathilizwe,
Msengeni, Xonyeni, Mhlabulungile,
Shixini
1 304 R12 779 200,00
Mbhashe Area Wide Sanitation Region 2D Mbhashe Ward 4 (Upper Timane, Upper
Colosa, Mputhi Phantsi kwesiporo,
Mputhi Zweliwelile, Zwelakhe,
Munyu Komkhulu, Nyoka, Zanoxolo,
Mzantsi, Komkhulu, Kwagqawe,
Maxhama, Ejojweni, Mjelo)Ward
5(Bolotwa, Vinindwa, Nyakatha,
Mazizini, Zanohlanga, Ngqaqeni)
Ward 6 (Matolweni, Bangweni, Entla
kwesporo, Mhuku, Ntabeni)
1 401 R 13 729 800
Mbhashe Area Wide Sanitation Region 1B Mbhashe Ward 11 (Upper Dadamba, Nkanga,
Zenzele, Lower Dadamba, Nqadu,
Weza, Ncedana, Maya, Pezulu,
Ntshingeni.) Ward 30 (Papasini,
Ntlabane, Qakazana, Tswelelelitye,
Kulokhala, Mandluntsha, Swekileni,
Kulozulu, Gangatha.)
150 R 1 470 000
22
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mbhashe Ward (RHIG) Mbhashe Ward 22 (Dumalisile, Mlethe, Tenza,
Xazini, Gojela, Msizilweni, Zwelitsha,
Beechamwood, Goqo, Camshe,
Nquba, Lower Jotelo, Upper Jotelo,
Folokwe, Mangwevini, Nompha,
Celani, Skwati)
450 R 4 410 000
Mnquma Ward (RHIG) Mnquma Ward 11 (Nciba, Maqwathini,
Manqulo, eZisoyini, Phumlani,
Bumbane) & Ward 14
(Ntombo, Tyinirha, Ngqileni, Votini,
Nyili, Ntandathu, Dyam-dyam)
450 R 4 410 000
Ngqamakhwe Ward 17 and 19 Mnquma 28 R 274 400
23
COMPLETED SANITATION PROJECT - 2017/2018 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mbhashe Ward (RHIG) Mbhashe Ward 22 (Dumalisile, Mlethe, Tenza,
Xazini, Gojela, Msizilweni, Zwelitsha,
Beechamwood, Goqo, Camshe,
Nquba, Lower Jotelo, Upper Jotelo,
Folokwe, Mangwevini, Nompha,
Celani, Skwati)
450 R 4 410 000
Mnquma Ward (RHIG) Mnquma Ward 11 (Nciba, Maqwathini,
Manqulo, eZisoyini, Phumlani, Bumbane)
& Ward 14 (Ntombo, Tyinirha,
Ngqileni, Votini, Nyili, Ntandathu,
Dyam-dyam)
450 R 4 410 000
Ngqamakhwe Ward 17 and 19 Mnquma 28 R 274 400
TOTALS 21 916 R 214 776 800
24
FINANCIAL
YEAR
2018/2019
25
COMPLETED WATER PROJECT - 2018/19 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Xhora Water Supply Scheme Phase 1C and D Mbhashe Madindi B, Nginza, Tshinirha, Ntlonyane
F, Mngazana, Fameni D,
Mtshayelweni C, Mtshauelweni D,
Gqubuza, Dingata, Tsholonorha B,
Ntlonyana A & G, Gobisandla, Bumbane,
Mbotyi C, Mpozolo, Hobeni B,
Hobeni C, Makhamesa, Mbelu, Xwili,
Mbhashe, Mantshilibeni.
2068 R 26 152 003
Gcuwa West Water Supply Project Phase 2
contract 3
Mnquma
Mantunzeleni, Mcuncuzo, Mgagasi,
Mazizini, Esidutyini.
2298 R 18 084 542
TOTALS 4366 R 44 236 545
26
27
COMPLETED SANITATION PROJECT - 2018/19 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Amahlathi 3A Amahlathi Mgwali 1, Kwazidenge, Heckel,
Mgwali 4, Mgwali 2,
739 R 7 242 200
Amahlathi 2A Amahlathi Gwili gwili, Zanyokhwe, Mangati,
Stanhope, Rockdale, Emelley, Nyingane,
Nyathela.
2763 R 27 077 400
Mbhashe 2B Mbhashe kolota, Thalimofu, Phuthuma, Qaso,
Khohlo, Mbombela, Cawe, Sidabekweni,
Mbelu, Mathyanini, Kwa
Tshezi, Mission, Mdikana.
1250 R 12 250 000
Mbhashe 2C Mbhashe Mmangweni, Dangazele, Maxhama,
Qatama, Nowonga-Kulophungula,
Ngqwangele, Qatywa, Maqadini,
Cala, Nomelody, Njuqwana, Nqakayi,
Mhlanga, Geya, Nyandeni,Bhula,
Mbetshe, Mncwabe, Dungashe,
Emampondweni, Kwelo Mthombe,
Mngazana, Lubanzi.
2018 R 19 776 400
28
COMPLETED SANITATION PROJECT - 2018/19 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Mbhashe 2D Mbhashe Dayimane, Silityiwa, Makhobeni,
Sirhoshweni, Nkawukazi, Nyandeni,
Sihlabeni, Ntabeni, Madaka, Betane,
Krweleda, Matolweni, Mission.
Mbhashe 3B Mbhashe Xonyeni, Mbozi, Nomawaka,
Mhlabalungile,
Mbhashe 1B Mbhashe Lower Dadamba, Upper Dadamba,
Kulozulu, Gangatha, Madluntsha,
Mboya, Weza.
Mnquma 3A Mnquma Ndiki, Mdeni, New Look, Mantunzeleni,
Thunga, Zingqayi, Hilihili,
Qwanguleni, Esihlabeni, Mambabaleni,Thanga.
Nkonkobe Region 3A Raymond Mhlaba Majwarheni, Mazotshweni, Ngobe,
Nomaqamba, Balfour, Upper Ncera,
Toll, Khwezana, Dish, Lushington,
Meva, Nkobonkobo, Lenge, Nomaqamba,
Khayelitsha, Ngobe,
Mgquba, Gaga, Ngwabeni,
Sigingqini, Lalini, Memela,
Sikolweni.
250 R 2 450 000
145 R 1 421 000
391 R 3 831 800
461 R 4 517 800
2632 R 25 793 600
Mnquma RHIG Ward 11 &14 Mnquma Deyi, Ntshatshongo, Nduveni,
Manqulo .
353 R 3 459 400
TOTALS 11002 107 819 600
29
FINANCIAL
YEAR
2019/2020
30
COMPLETED WATER PROJECT - 2019/20 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Gcuwa West Water Supply Scheme:
Phase 2 Contract 2
Mnquma
Gcuwa West Water Supply Scheme:
Phas 2 Contract 2
196 12 662 831
Komga Commonage Great Kei Komga Commonage 1140 29 983 577
TOTALS 1336 42 646 408
31
32
COMPLETED SANITATION PROJECT - 2019/20 FUNDING SOURCE: MIG
PROJECT NAME LM VILLAGES SERVED NO OF HH PROJECT VALUE
Amahlathi Region 2A Amahlathi 3 353 43 589 000
Amahlathi Region 2A Amahlathi 944 12 272 000
Amahlathi Region 2A Mbhashe 404 5 252 000
Amahlathi Region 2A Mbhashe 1 250 16 250 000
Amahlathi Region 2A Mbhashe 2 493 32 409 000
Amahlathi Region 2A Mbhashe 250 3 250 000
Amahlathi Region 2A Mbhashe 271 3 523 000
Amahlathi Region 2A Raymond Mhlaba 2 511 32 643 000
Amahlathi Region 2A Ngqushwa 977 12 701 000
Amahlathi Region 2A Mnquma 229 2 977 000
Amahlathi Region 2A Mnquma 508 6 604 000
Amahlathi Region 2A Mnquma 629 8 177 000
33
COMMUNITY
AWARENESS ON
COVID-19
34
ACCELERATED SERVICE DELIVERY
WATER CONSERVATION AND
DEMAND MANAGEMENT
INITIATIVES
35
GREAT KEI LOCAL
MUNICIPALITY
Site analysis complete for all towns;
Billing Analysis & Revenue Enhancement;
Reservoir No. 3 Leak Repairs – Siviwe Township;
Leak repairs on Kei Bridge Rising Main during shutdown;
Leak repairs in Kei Mouth Water Treatment Works during shutdown;
Leak Repairs in Haga-Haga during shutdown;
PLANNED ACTIVITIES
Leak Detection;
Zoning and development of Schematics;
Monthly Billing Analysis and Water Balancing;
Installation of Zone Meters;
At least 4 additional leaks have since been identified on the Kei Bridge rising
main. These need to be repaired as a matter of urgency;
Preparations were being made to repair these leaks and replace / repair the air
valves on the rising main. Seven air valves were found and assessed and found
to be non-functional. This is more than likely the main cause of the leaks which
have been identified
36
AMAHLATHI
LOCAL
MUNICIPALITY
Water loss and leak detection in Keiskammahoek;
Dontsa Water Supply Scheme pipeline repairs;
Supply and Install 4 x Amatola Water Bulk line meters;
Monthly Billing Analysis and Water Balancing;
Various Leak Repairs.
PLANNED ACTIVITIES
Dontsa Water Supply Scheme pipeline repairs;
Bumbane Pump Station standby booster pump station supply and installation;
Masincedane WTW to Bumbane PS pipeline leak detections and repairs;
Monthly Billing Analysis and Water Balancing;
Installation of 10 x Amatola Water Bulk line meters.
37
RAYMOND
MHLABA LOCAL
MUNICIPALITY
Visual inspection within Seymour. Some smaller leaks on valves have been detected
and repaired;
Visual leak inspections within Hogsback;
Zoning of Bedford and Adelaide- repair of existing gave valves and fire hydrants.
Repair of Fish river bulk line and Bedford location supply gate valve repairs
vandalized;
Installation of bulk meters and level dex on the main reservoir which supply
Bedford and Adelaide on Fish River rising main;
Zoning and replacement of faulty bulk meters including gate valves along Bedford
main line;
Installation and repairs of bulk meters from Fish River and borehole that supply
Adelaide;
Repairs of leaking gate valves and bulk meters supply Adelaide town and surroundings
including zoning;
Supply and Installation of 7 x Bulk Check Meters;
PLANNED ACTIVITIES
Installation of bulk meters and level dex on the main reservoir which supply
Bedford and Adelaide on Fish River rising main;
Zoning and replacement of faulty bulk meters including gate valves along
Bedford main line;
Repairs of leaking gate valves and bulk meters supply Adelaide town and
surroundings; including zoning;
Supply and Install 10 x Amatola Water Bulk line meters;
38
MNQUMA LOCAL
MUNICIPALITY
5 x Reservoir Repairs in Centane; Ngqamakwe and Butterworth;
Various Network Leak Repairs;
Analyse ADM monthly billing;
PLANNED ACTIVITIES
Analyze ADM monthly billing and prepare water balances;
Assist ADM to roll out “Rural Yard Connection Policy”;
Top 100 Consumer Analysis using Billing;
Complete zoning and develop schematics;
15 x reservoir repairs;
Updating GIS shape files for Infrastructure As-built changes;
39
MBHASHE
LOCAL
MUNICIPALITY
Meter Verifications and Top user consumption assessment;
Monthly Billing Analysis and Water Balancing;
Develop schematics;
Various Network Leak Repairs;
Mcwasa WTW operations during shutdown
PLANNED ACTIVITIES
Leak Detection;
Zoning and development of Schematics;
Monthly Billing Analysis and Water Balancing;
Installation of Zone Meters;
Reservoir Repairs.
40
NGQUSHWA
LOCAL
MUNICIPALITY
Water loss and leak detection in Keiskammahoek;
Dontsa Water Supply Scheme pipeline repairs;
Supply and Install 4 x Amatola Water Bulk line meters;
Monthly Billing Analysis and Water Balancing;
Various Leak Repairs.
41
DROUGHT
INTERVENTION
42
NO. SOURCE VOLUME AVAILABLE STATUS COMMENT
AVAILABLE
1
Golf Course
boreholes x 4
1 mill litres per day
Awaiting eskom connection
Temporary generators
installed on two
boreholes for tanker
filling when required
WATER
2
Teko Kona
boreholes x 3
1 mill litres per day
Completing pump installation.
Expected completion
end March 2021
Water will be pumped
to Ibika reservoir once
pump installation
complete
SUPPLY
3
Teko Fihla
boreholes x 3
500 000 litres per
day
Operational
Used for filling tankers
DURING
DROUGHT
4 23 handpumps
40 000 litres per
day
Operational
Only 3 fit for human
consumption, rest to be
used for non-drinking
purposes only
5 Mission
120 000 litres per
day
New
Under construction
6
Ngqamakwe
Regional Supply
10 mil litres per day
for Butterworth
New
Phase 1 under
construction – 36 month
project
43
AVAILABLE
WATER
SUPPLY:
HANDPUMPS
LOCATIONS
44
WATER
DISTRIBUTION:
Tanks (75)
45
JOB
OPPORTUNITIES
CREATED
46
FY
NO. OF
PROJECTS
W/O
CREATED
YOUTH WOMEN DISABLED
SOURCE:
WATER AND
SANITATION
PROGRAMME
16/17 14 772 417 142 -
17/18 20 2462 1250 712 1
18/19 18 275 1571 319 1
19/20 18 3687 2288 436 8
W/O: work opportunity
20/21 13 1547 911 207 7
TOTAL 10 943 6437 1816 17
47
Local
Municipality
2016/
17
2017/
18
2018/
19
TOTAL Women Youth
Persons
with
Disability
Other
Ngqushwa 66 40 84 190 65 60 4 61
SOURCE:
EPWP
Amahlathi 101 40 52 193 85 55 5 48
Raymond
Mhlaba
45 40 78 163 62 54 2 45
Mbhashe 44 40 55 139 63 70 2 4
Great Kei 40 40 30 110 25 76 0 9
Mnquma 67 40 65 172 65 55 4 48
TOTAL
967 365 370 17 215
48
ADM Executive Mayor:
Cllr Khanyile Maneli
UMANY ANO K U PHUHL ISO
ENVISIONING AN AMATHOLE SMART DISTRICT TOWARDS 2058
Aspire Board Chairperson:
Prof Christian Adendorff
“Vision 2058” is a 40-year, two generational
projection in preparation
of our District on smart concepts
and opportunities presented by the
4th Industrial Revolution. It is an
unfolding of research and development
undertaken by ADM informed by NDP
2030, EC Vision 2030, AU Agenda 2063
and UN 17 Sustainable Development
Goals; aimed at socio-economic upliftment
of the District, its local
Municipalities and communities.
Fostering stakeholder support and cooperation
is key to achieving “Vision
2058”. This is stipulated as per the four
vision below:
ADM Municipal Manager
Dr Thandekile Mnyimba
Aspire Acting CEO:
Ms Akhona Tinta
49
11 catalytic projects with smart solutions within the 4th Industrial Revolution,
have been identified based on our natural and artificial endowment.
In order to be an appropriate vehicle for the realisation of “Vision 2058”, since
2018, Amathole District Municipality has been implementing its Municipal Turnaround
Strategy (MTAS) in its pursuit to build a Culture of Excellence by “Bringing
ADM Back to its Former Glory”.
50
ASPIRE (Amathole District Economic Development Agency) is currently implementing
its Repositioning and Transformation Strategy towards being the implementers
of a “Prosperous and Smart Amathole District” with focus on creating a
conducive environment in diversifying socio-economic development in Amathole
District. www.amathole.gov.za
51
Conclusion
South Africa‘s Constitution provides that, one of the
objectives of local government is to “provide a
democratic and accountable government for local
communities”.
This booklet presents an opportunity to account for
the public purse entrusted to the municipality to
accelerate service delivery to all our communities.
The amount of work we have put in the past financial
years is testimony to our commitment to serve our
communities and ensure provision of selfless, excellent
and sustainable services to all whilst creating a
favorable environment for local economic development.
commitment and for never failing to provide strategic
leadership even under difficult periods.
Amid unprecedented times presented by the global
coronavirus pandemic, I urge all of you to be alert,
observe all Covid-19 protocols and
#choose_vaccination
ADM Executive Mayor:
Cllr Khanyile Maneli
All of what we have achieved and that which we will
still achieve and count amongst our legacy would not
have been possible without the support of our strategic
partners and our communities at large. For this I
want to thank all of them and plead for more support,
collaborations and cooperation in the strides we
continue to make in pursuance of our vision 2058 – of
building a smart district.
52
I also want to thank the entire Council of ADM together
with leadership of our local municipalities for the
Virtual State of the District Address
held on the 24 June 2021
53