VT4E-XG07-P3ZEN-110001_Water Balance Diagram_Rev.E
Water Balance Diagram
Water Balance Diagram
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Water Balance Diagram [Case 1]
(Plant normal operation case at VWO, 1% Make-up at BMCR is
considered only for Demi. water consumption, Seawater)
Total
Seawater
intake
CWP
(2 x 50%,
Total 2 pumps)
E
B
(45)
10.00
(44)
16.00
(43)
26.14
(46)
0.14
Service Water
1,363.1
NOTE 3) Storage Tank
(73)
(82)
(1 x 3700 m 3 )
From VT4
0.00
68.41
-
(52) (52) (126)
29.22 0.53
0.53
Oily Waste Water 0.55
General use
701.2 12.7 12.7
Separator
13.2
(79) (122) (58) (123)
1.44
0.08
0.09
0.09
S
Chemical area washing
34.5
2.0
2.3
2.3
(77)
1.35
(48) (124)
8.75
1.48
210.1
Ash Handling System
35.6
(64) (129)
0.17
0.17
Chemical Dosing
4.0
4.0
(68) (118)
0.00 GAH, GGH, ESP, Note 2)
0.00
- Chimney Washing
-
(85) (29)
171.02
28.04
NOTE 3) (5) (132)
BWRO
4,104.4 BWRO
672.9
Degasifier
27.60 Condensate
23.68 Boiler/Steam
0.00
0.00
Storage Tank
BLR blowdown pit
Reject (33)
662
568
-
-
(1 x 400 m 3 )
Turbine Cycle
1.74
Condensate
BWRO
Filtered Water
Transfer Pump
Buffer Pond
41.8
Chemical (2 x 100%)
(8)
Cleaning CPP Regen.
0.02
(17)
(92) (91) 0.01 (31)
MBP
Pump
0.5
5.51
F
187.67
18.39
0.2
(121)
(2 x 100%)
132.2
Back 4,504.0 441.4
(9) 0.37
(12)
Washing 0.31
(3)
8.8
3.90
Aux. Steam Consumers
(169)
L
CCW Leakage
7.5
27.97
93.7
18.39 Pre-treatment Filters
671.4
C
4.06
Soot Blowing
441.4
97.4
(BLR/GAH/GGH)
(114) (94)
4.5
188.5
107 4,524.6
Screen wash
(117) water pump
(105)
88,326 (2 x 100%)
88,010 85,221
86,569
4 185
2,119,821 2,112,250 2,045,296
(115)
122.4
2,938
120
56.80
627.4
240.0
384.0
3.4
Condensate
(22)
(92) 187.67
(7)
Polishing Plant
N
0.73
DM Water
4,504.0 27.66
0.06
17.5
Storage Tank
Chemial Dosing
(117) NOTE 6) (1 x 1400 m 3 )
663.9
1.5
(127) (21)
88,326
(93)
DM Plant
3.90
0.72
2,119,821 0.86
Regen. Pump
DM Water
93.7
17.3
A
Clarifier
(2 x 100%)
86,569 20.6
Supply
Pump
(2 x 100%)
Traveling Band Screen
Washing
86,259 83,525
(108) (111)
Closed Cooling
2,625
88,010
62,991
Heat Exchangers &
2,112,250
2,572
CVP coolers
87,197
(110)
165
3,964
162
Fire fighting
NOTE 5) (51)
Potable Water Consumers
0.00
Potable water
-
treatment
32.5
0.00 BLR Blowdown
1,641.8
BWRO
(160)
- Quenching water
Feed BWRO feed pump
1.35
Package Sanitary
(65)
M
(84) Pump flow for DM plant
32.5
Treatment System
0.07
Cycle losses
Vent
102.61
(2 x 100%) Design
SCR
E
0.1
(6)
0.00
2,462.7
SWRO
29.78 (34) 32.99 (28) NOTE 3) 18.17
-
714.7
791.7
Demi. Water Plant
436
VT4 Chlorination
system
CHS Dust
suppression
Pump
(2 x 100%)
ACW booster
pump
(2 x 100%)
Junction tower
/ Belt
conveyor
Coal pile &
Stacker /
reclaimer
Coal
washdown
R
Service Water
Pump
(2 x 100%)
Potable Water
Pump
(2 x 100%)
SDCC CW
booster
pump
(2 x 100%)
Potable Water
Storage Tank
(1 x 40 m 3 )
Steam Turbine
Condensers
SDCC
Heat exchangers
Irregular Waste Water
Storage Tank
G
L
Safety Shower &
Eye Washers
WT & WWT BLDG
Main Electrical BLDG
Control BLDG
Local Elec. BLDG
F
Q
C
(112)
14,794
355,064
14,500
Service Water Consumers
Landscaping
14,794
355,064
14,633
7.27
174.5
(150)
0.00
(153) (152)
0.00
Dewatering System
0.00
- -
-
D
G
88,132
2,115,175
87,449
0.00
-
Contaminated
Storm Water Runoff
Oily Area
Clean Storm Water
Runoff
(42)
16.89
Contaminated
0.00
R
SDCC Make up
Storm Water Runoff
405.4
Coal Area
-
(47) (133)
2.71 Coal feeder chute
Coal run off
0.14
65.0
spray water
pond
3.4
(120) (134) (162)
0.15 Regular Waste Water
7.58
Waste Water
Final pH
8.93
3.6
Storage Tank
181.9
Treatment System adjustment tank
214.4
S
D
H
O
A B E
P
FGD Aeration Basins
Absorber
Spray Pump
(2 x 100%)
N
Absorbed in
Ash
O
P
SCR Vaporizer
Sampling System
Solid Disposal
M
Sea Water Outfall
Q
H
Ton/h ( VWO CASE with 1% Cycle loss at BMCR + Average water flow consumption in Intermittent case ) (172)
Ton/day ( In case of intermittent consumer Total water consumption during a day when water is required)
FGD Absorber
88,141
m3/h ( If required, i.e. for seawater line )
2,115,389
87,458
Seawater Pump : To Sea
Desalinated & DM water
Intermittent *** or Connection Point : A , this symbol of each alphabet is connected to another symbol which has same alphabet.
Waste Water
NOTE
1) The purpose of Water Balance Diagram is to show the expected water consumption of Vinh Tan 4 Extension Power Plant Project. Therefore intermittent cases are considered based on average water consumption.
2) The flowrate in each table is based on average water consumption & discharge flow, and washing water for GAH, ESP, Chimney, etc. which will be required during plant overhaul (Not required during Plant normal operation) is not Considered.
and maximum water consumption of each consumer in the intermittent case will be considered in each system or equipment design, so not shown in this WBD.
3) 1% cycle makeup at BMCR is considered only to calculate Demi. water plant capacity as per Contractual requirement, but it is NOT considered in total freshwater consumption because of following reasons ;
- In case of super critical boiler for VT4 Extension Project no boiler blowdown water is generated during normal operation.
- All water or steam losses from power generation cycle such as boiler / gas air heater / gas gas heater soot blowing steam, and sampling water are already included in total Demi. water consumption.
4) Quenching water for boiler blowdown is not included in total water consumption because normally blowdown is not required during normal operation for once through type boiler and 1% makeup is already considered.
5) Potable water consumption is calculated from 250 working people in Vinh Tan 4 Extension Plant, 130 liter/day/person, and design capacity of potable water treatment is 40 m3/day.
6) Required Raw water for Vinh Tan 4 Extension Project will be supplied from Sea or Lake, therefore Seawater RO system system & Lake water treatment system will be supplied either.
But this Water Balance Diagram is based on the case that seawater is utilized as Raw water.
Total
Seawater
intake
CWP
(2 x 50%,
Total 2 pumps)
Water Balance Diagram [Case 2]
Service Water Consumers
(Plant normal operation case at VWO, Seawater)
(2 x 100%)
29.22 0.53 0.53 0.55
E
B
(52) (52) (126)
Oily Waste Water
701.2 12.7
General use
12.7 Separator
13.2
(79) (122) (58) (123)
(45)
1.44 0.08
0.09 0.09
Junction tower
S
Chemical area washing
D
10.00 / Belt
34.5 2.0
2.3 2.3
0.00
240.0 conveyor NOTE 5) (51)
-
(44)
Potable Water Consumers
0.00 7.27
Absorbed in
16.00 Coal pile & Potable water
Landscaping
- 174.5
Ash
Stacker /
treatment
Contaminated
384.0
reclaimer
Safety Shower &
(48) (124)
Storm Water Runoff
(46)
Eye Washers
8.75 1.48
Oily Area
Ash Handling System
O
0.14 Coal
210.1 35.6
3.4 washdown
(64) (129)
WT & WWT BLDG
(43)
Potable Water
0.17 0.17
Storage Tank
Chemical Dosing
P
Clean Storm Water
26.14 4.0 4.0
(1 x 40 m 3 )
Runoff
627.4
R
Main Electrical BLDG
(68) (118)
0.00 GAH, GGH, ESP, Note 2)
0.00
CHS Dust
G
- Chimney Washing
-
suppression
Potable Water
Pump
Pump
(42)
Control BLDG
(2 x 100%)
(2 x 100%)
(77)
16.89 Contaminated
0.00
R
SDCC Make up
Storm Water Runoff
1.35 405.4
Coal Area
-
56.80 32.5
Local Elec. BLDG
(47) (133)
Service Water
1,363.1 2.71 Coal feeder chute
Coal run off
0.14
Storage Tank
(73)
65.0
spray water
pond
3.4
(82)
(1 x 3700 m 3 )
0.00
From VT4
Fire fighting
68.41 -
0.00 BLR Blowdown
1,641.8 (160)
- Quenching water
BWRO
Feed
1.35
Package Sanitary
(65)
M
(84) Pump
32.5
Treatment System
0.07
Cycle losses
Vent
102.61
(2 x 100%)
SCR
0.1
0.00
2,462.7
SWRO
11.61 (40)
0.00 -
278.7 Demi. Water Plant
-
(85) (35)
171.02 9.87
NOTE 3) (5) (132)
BWRO
4,104.4 BWRO
236.9 Degasifier
9.43 Condensate
5.51 Boiler/Steam
0.00
0.00
Storage Tank
BLR blowdown pit
Reject (39)
226 132 - -
(1 x 400 m 3 )
Turbine Cycle
1.74
Condensate
BWRO
Filtered Water
Transfer Pump
Buffer Pond
41.8
Chemical (2 x 100%)
(8)
Cleaning CPP Regen.
0.02
(17)
(92) (91) 0.01 (37)
MBP
Pump
0.5
5.51
F
187.67 18.39 0.2 (121)
(2 x 100%)
132.2
Back 4,504.0 441.4 (9) 0.37
(12)
Washing 0.31 (4)
8.8 3.90
Aux. Steam Consumers
(169)
L
CCW Leakage
7.5 9.81 93.7
18.39 Pre-treatment Filters
235.3
C
4.06
Soot Blowing
441.4
97.4
(BLR/GAH/GGH)
Condensate
(22)
(92) 187.67
(7)
Polishing Plant
N
0.73
DM Water
4,504.0 9.50
0.06
17.5
Storage Tank
Chemial Dosing
(117) NOTE 6) (1 x 1400 m 3 )
227.9
1.5
(127) (21)
88,326 (93)
DM Plant
3.90 0.72
2,119,821 0.86 Regen. Pump
DM Water
93.7 17.3
A
Clarifier
86,569 20.6
(2 x 100%)
Supply
Pump
(2 x 100%)
Traveling Band Screen
Washing
(120) (134) (162)
0.15 Regular Waste Water
7.58 Waste Water
Final pH
8.93
3.6 Storage Tank
181.9 Treatment System adjustment tank
214.4
(114) (94)
-
4.5 188.5
(153) (152)
107 4,524.6 G L F Q C S D H O P
0.00
0.00
Dewatering System
4 185 - -
Screen wash
(117) water pump
(105)
88,326
(2 x 100%)
88,010 85,221
2,119,821 2,112,250 2,045,296
86,569 86,259 83,525
(115)
122.4
2,938
120
VT4 Chlorination
system
ACW booster
pump
(2 x 100%)
(108) (111)
Closed Cooling
2,625 88,010 88,132
62,991
Heat Exchangers &
2,112,250
FGD Aeration Basins
2,115,175
2,572 CVP coolers
87,197 87,449
(110)
165
3,964
162
Service Water
Pump
SDCC CW
booster
pump
(2 x 100%)
Steam Turbine
Condensers
SDCC
Heat exchangers
Irregular Waste Water
Storage Tank
A B E
Absorber
Spray Pump
(2 x 100%)
(112)
14,794 14,794
355,064 355,064
14,500 14,633
(150)
0.00
N
SCR Vaporizer
Sampling System
Solid Disposal
M
Sea Water Outfall
Q
H
Ton/h ( VWO CASE + Average water flow consumption in Intermittent case ) (172)
Ton/day ( In case of intermittent consumer Total water consumption during a day when water is required)
88,141
FGD Absorber
m3/h ( If required, i.e. for seawater line )
2,115,389
87,458
Seawater Pump : To Sea
Desalinated & DM water
Intermittent *** or Connection Point : A , this symbol of each alphabet is connected to another symbol which has same alphabet.
Waste Water
NOTE
1) The purpose of Water Balance Diagram is to show the expected water consumption of Vinh Tan 4 Extension Power Plant Project. Therefore intermittent cases are considered based on average water consumption.
2) The flowrate in each table is based on average water consumption & discharge flow, and washing water for GAH, ESP, Chimney, etc. which will be required during plant overhaul (Not required during Plant normal operation) is not Considered.
and maximum water consumption of each consumer in the intermittent case will be considered in each system or equipment design, so not shown in this WBD.
3) Quenching water for boiler blowdown is not included in total water consumption because normally blowdown is not required during normal operation for once through type boiler.
4) Potable water consumption is calculated from 250 working people in Vinh Tan 4 Extension Plant, 130 liter/day/person, and design capacity of potable water treatment is 40 m3/day.
5) Required Raw water for Vinh Tan 4 Extension Project will be supplied from Sea or Lake, therefore Seawater RO system system & Lake water treatment system will be supplied either.
But this Water Balance Diagram is based on the case that seawater is utilized as Raw water.
Water Balance Diagram [Case 3]
(Plant normal operation case at VWO, 1% Make-up at BMCR is
considered only for Demi. water consumption, Lakewater)
Total
Seawater
intake
CWP
(2 x 50%,
Total 2 pumps)
B
(45)
10.00
(44)
16.00
(43)
26.14
(46)
0.14
Service Water
56.80
NOTE 3)
Storage Tank
1,363.1
(95) (1 x 3700 m 3 )
(73)
68.41
0.00
1,641.8
From VT4
-
(114)
4.5 0
107 -
4 -
Screen wash
(116) water pump
(105)
88,137
(2 x 100%)
88,010 85,221
2,115,296 2,112,250 2,045,296
86,384 86,259 83,525
(115)
122.4
2,938
120
627.4
240.0
384.0
3.4
(110)
165
3,964
162
Service Water
Pump
(2 x 100%)
N
Service Water Consumers
(52) (52) (140)
29.22 0.53 0.53
Oily Waste Water 0.55
General use
701.2 12.7 12.7
Separator
13.2
(79) (136) (58) (137)
1.44
0.08
0.09
0.09
S
Chemical area washing
34.5
2.0
2.3
2.3
(77)
1.35
32.5
Steam Turbine
Condensers
(48) (138)
8.75
1.48
210.1
Ash Handling System
35.6
(64) (143)
0.17
0.17
Chemical Dosing
4.0
4.0
(68) (118)
0.00 GAH, GGH, ESP, Note 2)
0.00
- Chimney Washing
-
Condensate Polishing
(22)
(7)
DM Water
27.66
0.06
Storage Tank
Chemial Dosing
Plant
N
0.73
17.5
(116) (103) (1 x 1400 m 3 )
663.9
1.5
(141) (21)
88,137
(102)
79.59
From VT4
3.90
0.72
Raw Water
DM Plant
2,115,296
1.88
1,910.2
93.7
17.3
A
Clarifier
Terminal Point
Regen. Pump
DM Water
86,384 45.1
(2 x 100%)
Supply
Pump
(2 x 100%)
Traveling Band Screen
Washing
Fire fighting
NOTE 5) (51)
Potable Water Consumers
0.00
Potable water
-
treatment
Potable Water
Pump
(2 x 100%)
Potable Water
Storage Tank
(1 x 40 m 3 )
Landscaping
(120) (149) (166)
0.15 Regular Waste Water
17.26
Waste Water
Final pH
18.62
3.6
Storage Tank
414.3
Treatment System adjustment tank
446.8
(112)
14,794 14,794
355,064 355,064
14,500 14,633
132.2
7.27
174.5
(155)
0.00
4.06
97.4
(158) (157)
0.38
Dewatering System
1.50
9.0
36.1
-
0.00
-
Contaminated
Storm Water Runoff
Oily Area
Clean Storm Water
Runoff
0.00 BLR Blowdown
(160)
- Quenching water
BWRO
(100) Feed
1.35
Package Sanitary
(65)
M
9.31
Pump
32.5
Treatment System
0.07
Cycle losses
Vent
(101) 223.3
(2 x 100%)
SCR
0.1
(6)
0.00
77.71 UF back
32.99 (28) NOTE 3) 18.17
-
E
Back
1,865.1 wash Pump
791.7
Demi. Water Plant
436
(3 x 50%)
Washing (29)
(145) 28.04
NOTE 3) (5) (132)
BWRO
9.31
672.9 Degasifier
27.60
Condensate
23.68 Boiler/Steam
0.00
0.00
Pre-treatment Filters
Storage Tank
BLR blowdown pit
223.3
662
568
-
-
(1 x 400 m 3 )
Turbine Cycle
BWRO Chemical BWRO
Condensate
Transfer Pump
Cleaning Reject (8)
(2 x 100%)
(31) (27) CPP Regen.
0.02
(17)
0.01
4.95
MBP
0.5
5.51
F
Pump
0.2
118.7
(135)
(2 x 100%)
(101)
E
(9) 0.37
(12)
77.71
0.31
(3)
8.8
3.90
1,865.1 L
K
7.5
27.97
93.7
671.4
C
VT4 Chlorination
system
CHS Dust
suppression
Pump
(2 x 100%)
ACW booster
pump
(2 x 100%)
Junction tower
/ Belt
conveyor
Coal pile &
Stacker /
reclaimer
Coal
washdown
R
SDCC CW
booster
pump
(2 x 100%)
SDCC
Heat exchangers
Safety Shower &
Eye Washers
WT & WWT BLDG
Main Electrical BLDG
Control BLDG
Local Elec. BLDG
Irregular Waste Water
Storage Tank
G L F Q
B S C D H
O
P
CCW Leakage
A
D
Absorbed in
Ash
(42)
16.89
Contaminated
0.00
R
SDCC Make up
Storm Water Runoff
405.4
Coal Area
-
(47) (133)
2.71 Coal feeder chute
Coal run off
0.14
pond
65.0
spray water
3.4
K
Absorber
Spray Pump
(2 x 100%)
O
P
G
Aux. Steam Consumers
Soot Blowing
(BLR/GAH/GGH)
SCR Vaporizer
Sampling System
Solid Disposal
(108) (111)
Closed Cooling
2,625
88,010
88,015
Heat Exchangers &
FGD Aeration Basins
E
62,991 2,112,250
2,112,369
2,572
CVP coolers
87,197
87,332
M
Sea Water Outfall
Q
H
Ton/h ( VWO CASE with 1% Cycle loss at BMCR + Average water flow consumption in Intermittent case ) ` (176)
Ton/day ( In case of intermittent consumer Total water consumption during a day when water is required)
88,034
FGD Absorber
E
m3/h ( If required, i.e. for seawater line )
2,112,816
87,350
Seawater Pump : To Sea
Desalinated & DM water
Intermittent *** or Connection Point : A , this symbol of each alphabet is connected to another symbol which has same alphabet.
Waste Water
NOTE
1) The purpose of Water Balance Diagram is to show the expected water consumption of Vinh Tan 4 Extension Power Plant Project. Therefore intermittent cases are considered based on average water consumption.
2) The flowrate in each table is based on average water consumption & discharge flow, and washing water for GAH, ESP, Chimney, etc. which will be required during plant overhaul (Not required during Plant normal operation) is not Considered.
and maximum water consumption of each consumer in the intermittent case will be considered in each system or equipment design, so not shown in this WBD.
3) 1% cycle makeup at BMCR is considered only to calculate Demi. water plant capacity as per Contractual requirement, but it is NOT considered in total freshwater consumption because of following reasons ;
- In case of super critical boiler for VT4 Extension Project no boiler blowdown water is generated during normal operation.
- All water or steam losses from power generation cycle such as boiler / gas air heater / gas gas heater soot blowing steam, and sampling water are already included in total Demi. water consumption.
4) Quenching water for boiler blowdown is not included in total water consumption because normally blowdown is not required during normal operation for once through type boiler and 1% makeup is already considered.
5) Potable water consumption is calculated from 250 working people in Vinh Tan 4 Extension Plant, 130 liter/day/person, and design capacity of potable water treatment is 40 m3/day.
6) Required Raw water for Vinh Tan 4 Extension Project will be supplied from Sea or Lake, therefore Seawater RO system system & Lake water treatment system will be supplied either.
But this Water Balance Diagram is based on the case that Lake water is utilized as Raw water.
Total
Seawater
intake
CWP
(2 x 50%,
Total 2 pumps)
N
Service Water Consumers
(52) (52) (140)
Oily Waste Water 0.55
General use
701.2 12.7 12.7 Separator
13.2
Water Balance Diagram [Case 4]
(2 x 100%)
(Plant normal operation case at VWO, Lakewater)
29.22 0.53 0.53
B
(79) (136) (58) (137)
1.44 0.08
0.09 0.09
S
Chemical area washing
(45)
34.5 2.0
2.3 2.3
Junction tower
D
0.00
10.00 / Belt NOTE 5) (51)
-
240.0 conveyor
Potable Water Consumers
0.00 7.27
Landscaping
Absorbed in
(44)
Potable water
- 174.5
Ash
16.00 Coal pile &
treatment
Safety Shower &
(48) (138)
Contaminated
Stacker /
Eye Washers
Storm Water Runoff
384.0
reclaimer
8.75 1.48
Ash Handling System
O
Oily Area
(46)
210.1 35.6
0.14 Coal
WT & WWT BLDG
(64) (143)
3.4 washdown Potable Water
0.17 0.17
(43)
Storage Tank
Chemical Dosing
P
4.0 4.0
Clean Storm Water
(1 x 40 m 3 )
26.14
Main Electrical BLDG
(68) (118)
Runoff
627.4 R
0.00 GAH, GGH, ESP, Note 2)
0.00
G
- Chimney Washing
-
CHS Dust
Potable Water
suppression
Pump
Control BLDG
(42)
(2 x 100%)
(77)
16.89
Contaminated
Pump
0.00
(2 x 100%)
SDCC Make up
Storm Water Runoff
1.35 405.4 Coal Area
-
R
56.80 32.5
(47) (133)
Service Water
Local Elec. BLDG
Storage Tank
1,363.1 2.71 Coal feeder chute
Coal run off
0.14
(95) (1 x 3700 m 3 )
(73)
65.0 spray water
pond
3.4
68.41 0.00
From VT4
Fire fighting
1,641.8 -
0.00 BLR Blowdown
(160)
- Quenching water
BWRO
(100) Feed
1.35
Package Sanitary
(65)
M
9.31 Pump
32.5
Treatment System
0.07
Cycle losses
Vent
(101)
223.3 (2 x 100%)
SCR
0.1
0.00
77.71 UF back
11.61 (40)
0.00 -
Back
1,865.1
wash Pump
(3 x 50%)
278.7 Demi. Water Plant
-
Washing (35)
(145) 9.87
NOTE 3) (5) (132)
BWRO
9.31 236.9 Degasifier
9.43 Condensate
5.51 Boiler/Steam
0.00
0.00
Pre-treatment Filters
Storage Tank
BLR blowdown pit
223.3 226 132 - -
(1 x 400 m 3 )
Turbine Cycle
BWRO Chemical BWRO
Condensate
Transfer Pump
Cleaning Reject (8)
(2 x 100%)
(37) (39) CPP Regen.
0.02
(17)
0.01 1.74 MBP
Pump
0.5
5.51
F
0.2 41.8 (135)
(2 x 100%)
132.2
(101) (9) 0.37
(12)
77.71 0.31 (4)
8.8
3.90
CCW Leakage
Aux. Steam Consumers
1,865.1 L
K
7.5 9.81 93.7
235.3
C
4.06
Soot Blowing
97.4
(BLR/GAH/GGH)
(120) (149) (166)
0.15 Regular Waste Water
17.26 Waste Water
Final pH
18.62
3.6 Storage Tank
414.3 Treatment System adjustment tank
446.8
(114)
-
4.5 0
(158) (157)
107 - G L F Q
B S C D H O P
0.38
1.50
Dewatering System
4 - 9.0 36.1
Screen wash
(116) water pump
(105)
88,137
(2 x 100%)
88,010 85,221
2,115,296 2,112,250 2,045,296
86,384 86,259 83,525
(115)
122.4
2,938
120
(108) (111)
Closed Cooling
2,625 88,010 88,012
Heat Exchangers &
FGD Aeration Basins
62,991 2,112,250 2,112,292
2,572 CVP coolers
87,197 87,332
(110)
165
3,964
162
Service Water
Pump
Condensate Polishing
(22)
(7)
DM Water
9.50
0.06
Storage Tank
Chemical Dosing
Plant
N
0.73
17.5
(116) (103) (1 x 1400 m 3 )
227.9
1.5
(141) (21)
88,137 (102)
79.59
From VT4
3.90 0.72
Raw Water
DM Plant
2,115,296 1.88 1,910.2 93.7 17.3
A
Clarifier
Terminal Point
Regen. Pump
DM Water
86,384 45.1
(2 x 100%)
Supply
Pump
(2 x 100%)
Traveling Band Screen
Washing
VT4 Chlorination
system
ACW booster
pump
(2 x 100%)
SDCC CW
booster
pump
(2 x 100%)
Steam Turbine
Condensers
SDCC
Heat exchangers
Irregular Waste Water
Storage Tank
K
Absorber
Spray
Pump (2 x
(112)
14,794 14,794
355,064 355,064
14,500 14,633
A
(155)
0.00
SCR Vaporizer
Sampling System
Solid Disposal
M
Sea Water Outfall
Q
H
Ton/h ( VWO CASE + Average water flow consumption in Intermittent case ) (176)
Ton/day ( In case of intermittent consumer Total water consumption during a day when water is required)
88,031
FGD Absorber
m3/h ( If required, i.e. for seawater line )
2,112,739
87,350
Seawater Pump : To Sea
Desalinated & DM water
Intermittent *** or Connection Point : A , this symbol of each alphabet is connected to another symbol which has same alphabet.
Waste Water
NOTE
1) The purpose of Water Balance Diagram is to show the expected water consumption of Vinh Tan 4 Extension Power Plant Project. Therefore intermittent cases are considered based on average water consumption.
2) The flowrate in each table is based on average water consumption & discharge flow, and washing water for GAH, ESP, Chimney, etc. which will be required during plant overhaul (Not required during Plant normal operation) is not Considered.
and maximum water consumption of each consumer in the intermittent case will be considered in each system or equipment design, so not shown in this WBD.
3) Quenching water for boiler blowdown is not included in total water consumption because normally blowdown is not required during normal operation for once through type boiler.
4) Potable water consumption is calculated from 250 working people in Vinh Tan 4 Extension Plant, 130 liter/day/person, and design capacity of potable water treatment is 40 m3/day.
5) Required Raw water for Vinh Tan 4 Extension Project will be supplied from Sea or Lake, therefore Seawater RO system system & Lake water treatment system will be supplied either.
But this Water Balance Diagram is based on the case that Lake water is utilized as Raw water.
ATTACHMENT 1. WATER BALANCE CALCULATION
DOC NO.
VT4E-XG07-P3ZEN-110001
PROJECT
VINH TAN 4 EXTENSION POWER PLANT
REV NO.
E
PAGE NO. 1
No. Particulars Formula Unit Values Remarks / Reference
Plant Water Balance Calculation for Plant
Date: 2019-05-28
Rev no:
FA. Rev. E
0. TOTAL FRESH WATER CONSUMPTION
Total Freshwater Consumption at Seawater Case 1 & Case 2 (1) = (82) Ton/h 68.41
Ton/day 1641.77
Total Freshwater Consumption at Lakewater Case 3 & Case 4 (2) = (101) Ton/h 77.71
Ton/day 1865.10
1. DEMI. WATER CONSUMPTION
Total DM water consumptions (1% Cycle Make up at BMCR + Misc. Loss) (3) = (5) + (6) + (7) + (8) + (9) Ton/h 27.98 This value shows expected Demi. water consumption including 1%
(For Case 1 & 3) + (11) + (12) + (17) Ton/day 671.56 CYCLE LOSS at BMCR and will be used only for calculation
of Demi. water consumption for Demi. water Plant capacity calculation.
Total ACTUAL DM water consumptions (4) = (5) + (7) + (8) + (9) Ton/h 9.81 This value shows expected ACTUAL Demi. water consumption
(During normal operation without 1% Cycle loss) + (11) + (12) + (17) Ton/day 235.53 and will be used for total water consumption calculation
(For Case 2 & 4)
and service water production process.
A. Boiler Blowdown
Loss from Boiler Blowdown (5) Ton/h 0.00 No Blowdown during Plant normal Operation
B. Power Cycle Loss
Power Cycle Loss Power Unit at BMCR (6) = 1816.815 x 0.01 Ton/h 18.17 Continuous, 1% of Main Steam at BMCR
(For Case 1 & 3)
C. Chemical Dosing System
Chemical Dosing System (7) = 3 x 0.5 / 24 Ton/h 0.06 Intermittent, 3 ton / hr, 0.5 hr / day
D. CCW Leakage
CCW Header Tank (Make up) (8) = 2200 x 0.001 / 100 Ton/h 0.02 Assumption, Intermittent (0.001% leakage of Normal CCW flow,
and CCWP rated flow 2200 m3/hr)
E. Demi. Plant Regeneration
Mixed Bed Polisher Regeneration (9) = 30 / 1000 / 0.001006349 / 24 / 4 Ton/h 0.31 Intermittent, 30m3/cycle, 3hr/time, 1 time/4 days
Specific volume 0.001006349 m3/kg
Mixed Bed Polisher Backwash & Rinse (10) = 5.4. / 1000 / 0.001006349 / 24 / 4 Ton/h 0.06 Intermittent, 5.4 m3/cycle, 1 time/4 days (from degasifier)
F. BWRO Chemical Cleaning & Flushing (11) = 35 / 24 / (365 / 2) / 1000 Ton/h 0.01 Intermittent, 35 m3/day, 1 Cleaning / 6 months
/ 0.001006349
G. CPP Regeneration (12) = (16) Ton/h 3.90
No. of Mixed Bed Polisher (13) No. 2.00 2 Working MBP
Required water per MBP for 1 Regeneration Cycle (14) m 3 /cycle 330.00
(15) = (14) / 1000 / 0.001006349 Ton/cycle 327.92 Specific Volume 0.001006349 m3/kg
Required Average Demi. water for CPP (16) = (15) x 2 / 24 / 7 Ton/h 3.90 Intermittent, 1 Regeneration / Week
H. Misc. Cycle loss from Aux. Steam Consumption &Sampling (17) = (18) + (19) + (20) + (21) + (22) Ton/h 5.51 Consumption not returned to power generation cycle
Boiler Soot Blowing (18) = 23.255 x 3 / 24 Ton/h 2.91 Intermittent 3 times / day, 23.255 ton / time
GAH Soot Blowing (19) = 8 x 3 / 24 Ton/h 1.00 Intermittent 3 times / day, 8 ton / time
GGH Soot Blowing (20) = 1.2 x 3 / 24 Ton/h 0.15 Intermittent 3 times / day, 1.2 ton / time
Loss from Sampling System (21) = 72 / 1000 x 10 Ton/h 0.72 Continuous, 72 kg / hr per sampling point, Total 10 points
SCR Vaporizer (22) Ton/h 0.73 Continuous, 0.73 ton / hr for VT4 & VT4 Extension PJT
2. BWRO
A. Based on DM water consumptions with 1% Cycle Make up at BMCR
+ Misc. Loss (For Demin. Water Plant Design and For Case 3)
Total Flow to Demi. Water Plant (23) = (3) + (10) Ton/h 28.04
BWRO Chemical Cleaning & Flushing (24) = 35 / 24 / (365 / 2) m 3 /h 0.01 Intermittent, 35 m3/day, 1 Cleaning / 6 months
(25) = (24) / 1000 / 0.001006349 Ton/h 0.01 Specific Volume 0.001006349 m3/kg
Reject Ratio from BWRO (26) % 15.00
Reject Flow from BWRO (27) = (23) x 0.15 / (1 - 0.15) Ton/h 4.95 Continuous
Total Flow from Service Water Tank to BWRO (28) = (23) + (27) Ton/h 32.99
E
B. Based on DM water consumptions with 1% Cycle Make up at BMCR
+ Misc. Loss (For Case 1)
Total Flow to Demi. Water Plant (29) = (3) + (10) Ton/h 28.04
BWRO Chemical Cleaning & Flushing (30) = 35 / 24 / (365 / 2) m 3 /h 0.01 Intermittent, 35 m3/day, 1 Cleaning / 6 months
(31) = (30) / 1000 / 0.001006349 Ton/h 0.01 Specific Volume 0.001006349 m3/kg
Reject Ratio from BWRO (32) % 15.00
E
Reject Flow from BWRO (33) = ((4) + (10)) x 0.15 / (1 - 0.15) Ton/h 1.74
Continuous, This rejected water from BMCR will be reused in Case 1, 2
so the flow is calculated based on the actual DM water consumption.
Total Flow from Service Water Tank to BWRO (34) = (29) + (33) Ton/h 29.78
C. Based on ACTUAL DM water consumptions with 0% Cycle Make up at
BMCR + Misc. Loss (For Case 2 & 4)
Total Flow to Demi. Water Plant (35) = (4) + (10) Ton/h 9.87
BWRO Chemical Cleaning & Flushing (36) = 35 / 24 / (365 / 2) m 3 /h 0.01 Intermittent, 35 m3/day, 1 Cleaning / 6 months
(37) = (36) / 1000 / 0.001006349 Ton/h 0.01 Specific Volume 0.001006349 m3/kg
Reject Ratio from BWRO (38) % 15.00
Reject Flow from BWRO (39) = (35) x 0.15 / (1 - 0.15) Ton/h 1.74 Continuous
Total Flow from Service Water Tank to BWRO (40) = (35) + (39) Ton/h 11.61
ATTACHMENT 1. WATER BALANCE CALCULATION
DOC NO.
VT4E-XG07-P3ZEN-110001
PROJECT
VINH TAN 4 EXTENSION POWER PLANT
REV NO.
E
PAGE NO. 2
3. SERVICE WATER CONSUMPTION
Total Service Water consumption (41) = (42) + (44) + (45) + (46) Ton/h 55.36
+ (47) + (48) + (51) + (52) + (58)
+ (64) + (65) + (68)
A. SDCC Make up
SDCC Make up & Drain chain conveyor (42) = (15 + 2) / 1000 / 0.001006349 Ton/h 16.89 Continuous, for SDCC make up, 15 m3 / hr
Continuous, for drag chain conveyor, 2 m3 / hr
Specific Volume 0.001006349 m3/kg
B. Coal Handling System
Coal pile, Stacker / reclaimer, Junction tower & Belt conveyor, (43) = (44) + (45) + (46) Ton/h 26.14 Continuous, total 26.14 ton/hr (Only total flow has been confirmed by supplier.)
and Washdown Total
Calculation for each consumption will be updated after receiving detail
detail information from supplier.
Coal Pile Spray & Stacker / Reclaimer (44) Later Ton/h 16.00 To be updated after receiving detail water consumption of each equipment
from package supplier.
Junction Tower & Belt Conveyor (45) Later Ton/h 10.00 To be updated after receiving detail water consumption of each equipment
from package supplier.
Washdown water (46) Later Ton/h 0.14 To be updated after receiving detail water consumption of each equipment
from package supplier.
Coal feeder chute spray water (47) Ton/h 2.71 Continuous, 2.71 ton / hr
C. ASH Handling System (48) = (49) + (50) Ton/h 8.75
Bottom Ash Silo (49) = 2.1 / 1000 / 0.001006349 Ton/h 2.09 Continuous, 2.1 m3/h, Specific Volume 0.001006349 m3/kg
Fly Ash Silo (for truck wet unloading) (50) = 40 x 4 / 24 Ton/h 6.67 Intermittent, 40 ton / hr, 4hrs / day
D. Landscaping
Landscaping (51) Ton/h 0.00 Intermittent, Not considered because it will be supplied from VT4 PJT.
E. General Washing Water (52) = (57) Ton/h 0.53
Flow through each hose (53) Ton/h 2.27 10 GPM per hose
Number of hose for General Washing in Plant Area (54) No. 56.00 Assumption
Number of hose for 10% service factor (55) = (54) x 0.1 No. 5.60
Time for hose opeartion (per day) (56) Min. 60.00
Average service water consumption for General Usage (57) = (53) x (55) x (56) / 60 / 24 Ton/h 0.53
F. Chemical Area Washing Water (Not included above)
Chemical Area Washing Water (Not included above) (58) = (63) Ton/h 0.09
- Flow through each hose (59) Ton/h 2.27 10 GPM per hose
- Number of hose for Plant area (60) No. 10.00 Assumption
- Number of hose for 10% service factor (61) = (60) x 10 / 100 No. 1.00
- Time for hose opeartion (per day) (62) Min. 60.00
- Average service water consumption for General Usage (63) = (59) x (61) x (62) / 60 / 24 Ton/h 0.09
G. Chemical Dosing System
Chemical Dosing System Fume Scrubber (64) = 2 x 2 / 24 Ton/h 0.17 Intermittent, 2 ton / hr, 2hrs / day
H. SCR (65) = (66) + (67) Ton/h 0.07
SCR Vaporizer (66) = 16 x 0.5 / 24 / 30 / 1000 Ton/h 0.01 Intermittent, 16 m3 / hr, 0.5 hr / month, Specific Volume 0.001006349 m3/kg
/ 0.001006349
Waste Ammonia Dilution Tank (67) = 10 x 1 / 24 / 7 / 1000 Ton/h 0.06 Intermittent, 10 m3 / hr, 1 hr / week, Specific Volume 0.001006349 m3/kg
/ 0.001006349
I. Washing Water During Plant Overhaul Period (68) = (69) + (70) + (71) + (72) Ton/h 0.00 Not considered in Water Balance Diagram
because Not required During Plant Normal Operation
Gas Gas Heater LP Water Washing Water (69) Ton/h 0.00 Not considered, 150 m3 / hr for 8 hrs (during Overhaul)
Gas Air Heater Washing water (70) Ton/h 0.00 Not considered, Assumption 200 m3 / hr for 8 hrs (during Overhaul)
ESP Internal Washing Water (71) Ton/h 0.00 Not considered, 180 m3 / hr for 6 hrs (during Overhaul)
Chimney wash water (72) Ton/h 0.00 Not considered, 4.5 m3 / hr for 0.5 hrs (during Overhaul)
0
4. FIRE FIGHTING WATER CONSUMPTION (73) 0.00 Supplied from Vinh Tan 4 Power Plant & NOT used During normal operation
ATTACHMENT 1. WATER BALANCE CALCULATION
DOC NO.
VT4E-XG07-P3ZEN-110001
PROJECT
VINH TAN 4 EXTENSION POWER PLANT
REV NO.
E
PAGE NO. 3
5. POTABLE WATER CONSUMPTION
Number of people (74) Person 250.00 Assumption
Consumption per each person (75) = 130 / 1000 Ton/day 0.13 130 Liter / person / day, TCXDVN 33:2006 WATER SUPPLY
DISTRIBUTION SYSTEM AND FACILITIES-DESIGN STANDARD, Table 3.1.
Potable water requirement of people per Day (76) = (74) x (75) Ton/day 32.50
Potable water requirement of people per Hour (77) = (76) / 24 Ton/h 1.35 This value is considered as the average required Potable water
Backwash flow for potable water system (78) = 2.04 x 1 / 24 / 1000 / 0.001006349 Ton/h 0.08 2.04m3/cycle, 1 cycle/day, Specific Volume 0.001006349 m3/kg
Service water flow to potable water system (79) = (77) + (78) Ton/h 1.44
Safety Shower and Eye Washer for Chemical area (80) Ton/h 0.00 In normal operation, NOT used. 4.55 m 3 /h per each Safety shower
& Eye washer, 0.69 m3/h per each Eye washer
6. SWRO for Seawater Case 1, 2
Total Required Service, Potable, Fire fighting, & BWRO Feed Water (81) = (40) + (41) + (73) + (79) Ton/h 68.41
Required SWRO Output Flow (82) = (81) Ton/h 68.4071
Reject Ratio from SWRO (83) % 60.00
Reject Flow from SWRO (84) = (81) x 0.61 / (1 - 0.61) Ton/h 102.61
Total Flow from Filtered Water Tank (85) = (82) + (84) Ton/h 171.02
BWRO Reject Flow to Filtered Water Tank (86) = (33) or (39) Ton/h 1.74
Backwash flow for UF (87) = 339.72 / 24 x 1.0203 Ton/h 14.44 Backwash water is 339.72 m3/day, Density 1.0203 ton/m3
Backwash water for AC filter (88) = 31.68 / 24 x 1.0203 Ton/h 1.35 Backwash water is 31.68 m3/day, Density 1.0203 ton/m3
Rinse water for AC filter (89) = 34.2 / 24 x 1.0203 Ton/h 1.45 Backwash water is 34.2 m3/day, Density 1.0203 ton/m3
Rinse water for disc filter (90) = 27 / 24 x 1.0203 Ton/h 1.15 Backwash water is 27 m3/day, Density 1.0203 ton/m3
Reject Flow from Pretreatment (91) = (87) + (88) +(89) + (90) Ton/h 18.39
Flow from Pretreatment to Filtered Water Tank (92) = (85) - (86) + (91) Ton/h 187.67
Reject Ratio from Clarifier (88) % 5.00
Reject Flow from Clarifier (93) Ton/h 0.86 From WTP Supplier
Total Clarifier Seawater Inlet flow (94) = (92) + (93) Ton/h 188.53
7. Pretreatment for Lake water Case 3, 4
Total Required Service, Potable, Fire fighting, & BWRO Feed Water (95) = (40) + (41) + (73) + (79) Ton/h 68.41
Backwash flow for UF (96) = 178.81 / 24 x 0.993691 Ton/h 7.40 Backwash water is 178.81 m3/day, Density 0.993691 ton/m3
Backwash water for AC filter (97) = 15.84 / 24 x 0.993691 Ton/h 0.66 Backwash water is 15.84 m3/day, Density 0.993691 ton/m3
Rinse water for AC filter (98) = 17.1 / 24 x 0.993691 Ton/h 0.71 Backwash water is 17.1 m3/day, Density 0.993691 ton/m3
Rinse water for disc filter (99) = 13 / 24 x 0.993691 Ton/h 0.54 Backwash water is 13 m3/day, Density 0.993691 ton/m3
Reject Flow from Pretreatment (100) = (96) + (97) + (98) + (99) Ton/h 9.31
Flow from Clarified Tank to Pretreatment (101) = (95) + (100) Ton/h 77.71 Continuous
Reject Flow from Clarifier (102) Ton/h 1.88 From WTP Supplier
Total Clarifier Inlet flow (103) = (101) + (102) Ton/h 79.59
8. SEAWATER CONSUMPTION
A. Circulating Water and Auxiliar Cooling Water (104) = (105) + (108) Ton/h 87845.27 1.012770512
Circulating Water for Condenser (105) Ton/h 85220.66 Continuous, 85,220.656 t/h
Cooling Water for CCW Heat Exchanger (106) Ton/h 2288.61 Continuous, 2,288.614 ton/h
Cooling Water for Condenser Vacuum Pump Collers (107) Ton/h 336.00 Continuous, 336 ton / hr
Cooling Water for CCW Heat Exchanger & CVP Cooler (108) = (106) + (107) Ton/h 2624.6140 Continuous
B. SDCC
SDCC Cooling Water (109) = (110) / 1020.3 x 1000 m 3 /h 161.88 Seawater density 1020.3 kg/m3
(110) Ton/h 165.16 Continuous, 165.162 t/h
C. Total Seawater To FGD Aeration Basin
Total Seawater To FGD Aeration Basin (111) = (105) + (108) + (110) Ton/h 88010.4320 Continuous
Seawater spray to FGD absorber (112) = 14500 x 1020.3 / 1000 Ton/h 14794.35 Continuous 14,500 m3/h
Seawater density 1020.3 kg/m3
D. Misc. Seawater Consumption
Traveling Band Screen Wash water (113) = 70 x 1.5 / 24 m 3 /h 4.38 Intermittent, 70 m3/h, 1.5 hr washing / day
(114) = (113) x 1020.3 / 1000 Ton/h 4.46
Seawater supply to VT4 Chlorination Plant (115) Ton/h 122.44 Continuous 122.436 t/h
E. Total Seawater from Intake
Lake Water Case 3, 4
Total Average Pumped Seawater from Intake (116) = (111) + (114) + (115) Ton/h 88137.33 Averaged Value
Seawater Case 1, 2
Total Average Pumped Seawater from Intake (117) = (111) + (114) + (94) + (115) Ton/h 88325.86 Averaged Value
ATTACHMENT 1. WATER BALANCE CALCULATION
DOC NO.
VT4E-XG07-P3ZEN-110001
PROJECT
VINH TAN 4 EXTENSION POWER PLANT
REV NO.
E
PAGE NO. 4
9. WASTE WATER
A. Waste Water to Irregular Waste Water Storage Tank
Waste Water from Washing Water During Plant Overhaul Period (118) = (68) Ton/h 0.00 Assumed Max. flow is 200 m3 / hr for 8 hrs (during Ovehaul)
Waste Water from BWRO Chemical Cleaning & Flushing (119) = (25) or (31) or (37) Ton/h 0.01
Flow from Boiler Blowdown Pit (132) = (5) Ton/h 0.00
Contaminated Storm Water Runoff from Coal Area (133) = (46) Ton/h 0.14 From Washdown water and Storm Water
But storm drain is not considered in Water Balance diagram
Averaged Waste Water to Irregular Waste Water Storage Tank (120) = (118) + (119) + (132) + (133) Ton/h 0.15
B. Waster Water to Regular Waste Water Storage Tank
Seawater Case 1, 2
Waste Water from Demi. Plant Regeneration (121) = (9) + (10) Ton/h 0.37
Waste water from Potablization backwash (122) = (78) Ton/h 0.08
Waste Water from Chemical Area Washing Water (123) = (63) Ton/h 0.09
Waste Water from Ash Handling System (124) = (50) x 0.2222 Ton/h 1.48 22.22 % of supplied serviice water for Fly Ash Silo
(77.78 % of supplied service water is absorbed in Fly Ash)
Waste Water from Irregular Waste Water Storage Tank (125) = (120) Ton/h 0.15
Oily Waste Water (126) = (52) + (8) Ton/h 0.55 From General Washing Water & CCW system Leakage
Waste Water from CPP Regeneration (127) = (12) Ton/h 3.90
Waste Water from Chemical Dosing (DM water) (128) = (7) Ton/h 0.06
Waste Water from Chemical Dosing (Service water) (129) = (64) Ton/h 0.17
Waste Water from Sampling System (130) = (21) Ton/h 0.72
Return Water from Dewatering System (131) = (153) Ton/h 0.00 From below "Dewatering System" Calculation
Total Averaged Waste Water to Regular Waste Water Storage Tank (134) = (121) + (122) + (123) + (124) + Ton/h 7.58
(125) + (126) + (127) + (128) +
(129) + (130) + (131)
Lake Water Case 3, 4
Waste Water from Demi. Plant Regeneration (135) = (9) + (10) Ton/h 0.37
Waste water from Potablization backwash (136) = (78) Ton/h 0.08
Waste Water from Chemical Area Washing Water (137) = (63) Ton/h 0.09
Waste Water from Ash Handling System (138) = (50) x 0.2222 Ton/h 1.48 22.22 % of supplied serviice water for Fly Ash Silo
(77.78 % of supplied service water is absorbed in Fly Ash)
Waste Water from Irregular Waste Water Storage Tank (139) = (120) Ton/h 0.15
Oily Waste Water (140) = (52) + (8) Ton/h 0.55 From General Washing Water & CCW system Leakage
Waste Water from CPP Regeneration (141) = (12) Ton/h 3.90
Waste Water from Chemical Dosing (DM water) (142) = (7) Ton/h 0.06
Waste Water from Chemical Dosing (Service water) (143) = (64) Ton/h 0.17
Waste Water from Sampling System (144) = (21) Ton/h 0.72
Waste Water from Pretreatment Filters Back Wash (145) = (100) Ton/h 9.31
Recovery Water from Dewatering System (146) = (158) Ton/h 0.38 From below "Dewatering System" Calculation
Total Averaged Waste Water to Regular Waste Water Storage Tank (149) = (135) + (136) + (137) + (138) + Ton/h 17.26
(139) + (140) + (141) + (142) +
(143) + (144) + (145) + (146) +
C. Dewatering System
Seawater Case 1, 2
Waste Water from Regular Waste Water Storage Tank to Dewatering System (150) Ton/h 0.00
Total Flow to Dewatering System (151) = (150) Ton/h 0.00
Water Reject to Solid Disposal (152) = (151) x 0.8 Ton/h 0.00 80% of Water included in Solid Disposal
Return Flow to Regular Waste Water Storage Tank (153) = (151) - (152) Ton/h 0.00
Lake Water Case 3, 4
Waste Water from Clarifier to Dewatering System (154) = (102) Ton/h 1.88
Waste Water from Regular Waste Water Storage Tank to Dewatering System (155) Ton/h 0.00
Total Flow to Dewatering System (156) = (154) + (155) Ton/h 1.88
Water Reject to Solid Disposal (157) = (156) x 0.8 Ton/h 1.50 80% of Water included in Solid Disposal
Return Flow to Regular Waste Water Storage Tank (158) = (156) - (157) Ton/h 0.38
D. Treated Water to Outfall
Seawater Case 1, 2
Waste Water from Waste Water Treatment System (159) = (134) - (150) Ton/h 7.58
Treated Water from Package Sanitary Treatment System (160) = (77) Ton/h 1.35 ( = Potable Water Consumption)
Total Treated Water (161) = (159) + (160) Ton/h 8.93
Total Treated Water to Outfall (162) = (161) Ton/h 8.93
Lake Water Case 3, 4
Waste Water from Waste Water Treatment System (163) = (149) - (155) Ton/h 17.26
Treated Water from Package Sanitary Treatment System (164) = (77) Ton/h 1.35 ( = Potable Water Consumption)
Total Treated Water (165) = (163) + (164) Ton/h 18.62
Total Treated Water to Outfall (166) = (165) Ton/h 18.62
10. Total Flow to Outfall
Seawater Case 1, 2
Total Seawater To FGD Aeration Basin (167) = (111) Ton/h 88010.43
Reject from Clarifier (168) = (93) Ton/h 0.86
Reject from Pretreatment Filters (169) = (91) Ton/h 18.39
Reject from SWRO (170) = (84) Ton/h 102.61
Total Treated Water to Outfall (171) = (162) Ton/h 8.93
Total Flow to Outfall (172) = (167) + (168) + (169) + (170) Ton/h 88141.23
+ (171)
Lake Water Case 4
Total Seawater To FGD Aeration Basin (173) = (111) Ton/h 88010.43
Reject from BWRO (174) = (33) or (39) Ton/h 1.74
Total Treated Water to Outfall (175) = (166) Ton/h 18.62
Total Flow to Outfall (176) = (173) + (174) + (175) Ton/h 88030.79
Lake Water Case 3
Total Seawater To FGD Aeration Basin (177) = (111) Ton/h 88010.43
Reject from BWRO (178) = (27) Ton/h 4.95
Total Treated Water to Outfall (179) = (166) Ton/h 18.62
Total Flow to Outfall (180) = (177) + (178) + (179) Ton/h 88033.99
E
E
E
E
E
E