Summary of Major Discussion Points:<br />
� Terhaar (FERC) provided an overview of FERC’s Integrated Licensing Process (ILP),<br />
schedule, study criteria and evaluation of study plans. (This presentation can be found<br />
on www.ktrel.com and is entitled FERC ILP and Study Criteria 10‐14‐09 Terhaar<br />
Presentation)<br />
� Turetzky asked why <strong>Duke</strong> would not be required to receive a water quality certification<br />
certificate from NC. Terhaar explained that a water quality certificate is only required if<br />
there is a project release within state boundaries.<br />
� Huff (<strong>Duke</strong>) provided an introduction to early ILP milestones including the Pre‐<br />
Application Document (PAD) and Study Plans. (This presentation can be found on<br />
www.ktrel.com and is entitled KT Relicensing Schedule 10‐14‐09 Huff Presentation)<br />
� Kearns provided the group with an overview of what RC Members can expect to<br />
experience by participating in the relicensing process. Kearns explained that the<br />
Stakeholder Team’s main focus will be to balance all resource interests to develop a<br />
preferred alternative for FERC’s Environmental Assessment (EA). Kearns explained that,<br />
each RC is grouped in a resource area that FERC will review as part of the EA. He went<br />
on to further explain how each RC will operate and interact with the Stakeholder Team.<br />
� He went on to further explain that in order to effectively develop a preferred<br />
alternative, the Team will need to understand what items should be included in a<br />
license, such as project operations, recreation, shoreline management, fisheries, and<br />
aesthetics. Many of the answers to questions relating to these areas will be answered<br />
through the studies.<br />
� Kearns provided the group with an overview of the relicensing website www.ktrel.com.<br />
(This presentation can be found on www.ktrel.com and is entitled K Rel Web Site Primer<br />
10‐14‐09 Kearns Presentation)<br />
� Kearns informed the group that, during afternoon breakouts with each RC , Committee<br />
Members would be reviewing the Technical Data Library, preliminary study ideas and<br />
briefly discussing any new studies ideas.<br />
Decisions:<br />
� RC Coordinators and K&W will work to schedule future RC meetings with overlapping<br />
Committee Members side‐by‐side to help reduce travel.<br />
Action Items: None<br />
Next Meeting Date: Varies depending on RC