DISTRICT OVERVIEW<br />
SMART SCALE, continued<br />
Town Of <strong>Culpeper</strong><br />
Orange Road/Fredericksburg Road Roundabout<br />
The project converts the Orange Road/Fredericksburg<br />
Road signalized intersection to a single-lane roundabout.<br />
The project includes adding pedestrian crosswalks and<br />
sidewalks on each approaching roadway.<br />
Estimated cost: $12,636,129<br />
Old Brandy Road Sidewalk Extension<br />
The Old Brandy Road sidewalk extension project proposes<br />
approximately 2,800 feet of five-foot-wide sidewalk along<br />
the north side of Old Brandy Road from the existing<br />
sidewalk infrastructure near Wine Street Memorial Park<br />
to James Madison Highway and adjacent commercial<br />
development.<br />
Estimated cost: $8,292,885<br />
Orange Road Sidewalk Extension<br />
This project proposes construction of approximately 2,500<br />
linear feet of five-foot-wide sidewalk along the east side<br />
of Orange Road from Standpipe Road and just south of<br />
the Orange Road/Fredericksburg Road intersection.<br />
Town Of Warrenton<br />
Business U.S. 17/Broadview Avenue/Shopping Center<br />
Intersection Improvement<br />
This project would convert the existing intersection into<br />
a peanut-shaped hybrid roundabout and includes bicycle/<br />
pedestrian facilities and crosswalks.<br />
Estimated cost: $14,890,760<br />
West Lee Street/U.S. 17 Business/Winchester Street<br />
Intersection Improvement<br />
This project would convert an existing intersection to<br />
a single/double-lane hybrid roundabout and includes a<br />
shared-use path, sidewalks, crosswalks and bike lanes.<br />
Estimated cost: $15,128,120<br />
Lee Highway/Blackwell Road Safety Improvement<br />
The project would convert an existing intersection to a<br />
single/double-lane hybrid roundabout and includes a<br />
shared-use path, sidewalks, crosswalks and replacement<br />
of the box culvert on Blackwell Road.<br />
Estimated cost: $14,066,640<br />
Estimated cost: $8,592,462<br />
SMART SCALE Round 5<br />
38 <strong>Culpeper</strong> <strong>District</strong> project applications<br />
$541,688,348 total value<br />
TRANSPORTATION UPDATE // PUBLISHED NOVEMBER 30, <strong>2022</strong> 15