FAUQUIER COUNTY<br />

In Design<br />

Safety Improvements at I-66 Exit 31<br />

Design work is underway on this $1.1 million project<br />

to improve safety on Interstate 66 at exit 31. VDOT will<br />

make improvements to address recurring crashes at this<br />

location on the interstate. Interstate Corridor funds will<br />

be used and advertising for construction begins July 2024.<br />

I-66 Sequential Dynamic Chevrons<br />

Preliminary engineering is under way for this safety<br />

project on Interstate 66 west at mile marker 22 in<br />

Marshall.<br />

Crews pour concrete for the new deck of the U.S. 17<br />

Southbound bridge over Norfolk Southern Railroad<br />

and Route 805.<br />

Under Construction<br />

Rehabilitation of U.S. 17 Southbound<br />

Bridge over Norfolk Southern Railroad<br />

and Route 805<br />

CONTRACTOR: Caton Construction Group, Inc. of Charlottesville<br />

CONTRACT AMOUNT: $4.9 million<br />

COMPLETION DATE: Dec. 8, <strong>2022</strong><br />

A VDOT contractor is replacing the superstructure,<br />

including the deck and railings, of the U.S. 17 (Marsh<br />

Road) southbound bridge that spans the Norfolk<br />

Southern Railroad and Route 805 (Bealeton Road). The<br />

existing bridge was built in 1948.<br />

The new bridge will have two 12-foot travel lanes with<br />

improved shoulders; the deck will be 38 feet wide from<br />

rail to rail. Southbound traffic is restricted to one 12-foot<br />

travel lane for the majority of the project with a reduced<br />

speed limit of 35 miles per hour through the work zone.<br />

This project, which uses Interstate Corridor funds, will<br />

install LED chevrons to alert drivers to the upcoming exit<br />

28. Construction anticipated to begin February 2025.<br />

I-66 CCTV Cameras<br />

VDOT will use Interstate Corridor funds to install cameras<br />

on Interstate 66 exit 23. These cameras provide more<br />

traffic monitoring for the Traffic Operations Center, and<br />

will be part of the VA511 system of cameras. Construction<br />

anticipated to begin July 2024.<br />

I-66 Changeable Message Signs (CMS)<br />

With this project, VDOT will install changeable message<br />

signs on westbound Interstate 66 just east of exits 28<br />

and 29. CMS provides information that supports quick<br />

and appropriate decisions by motorists in response<br />

to abnormal roadway, traffic, weather or security<br />

conditions. Construction anticipated to begin July 2024.<br />

Interstate 66/U.S. 17<br />

Safety Improvements<br />

Design work began early this year on this $16.4 million<br />

SMART SCALE project to improve safety, increase<br />

visibility, and reduce congestion. It will restructure the<br />

way drivers navigate the exits and combines several<br />

alternative intersections to improve safety. VDOT expects<br />

to advertise this project in the winter of 2026.<br />

32 VIRGINIA DEPARTMENT OF TRANSPORTATION \\ CULPEPER DISTRICT