CU Nov-Dec 2023
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
CASE study<br />
similar along the length of the building, it<br />
was different enough that each bay of<br />
steel was slightly dissimilar to the next.<br />
DBM Vircon was able to take these<br />
varying parameters of ever-changing<br />
geometry, steel sizes, plate thicknesses,<br />
welds and bolts quantities and develop<br />
these parametric custom components,<br />
complete with engineered checking data,<br />
to control over 60,000 (82%) of these<br />
connections. A huge time saving as the<br />
geometry evolved.<br />
With 23,861 tonnes of steel in the roof<br />
and façade structure and 79,374 main<br />
pieces of steel within the seven different<br />
Tekla models, the heavy use of<br />
parametric custom components enabled<br />
DBM Vircon to rapidly connect geometry<br />
that would otherwise have been<br />
extremely repetitive and time consuming.<br />
Likewise, connections that were required<br />
to change due to design updates could<br />
be updated on mass, far quicker than<br />
updating manually created ones as in a<br />
typical process.<br />
A custom set of these connection<br />
parameters were exported from Tekla to<br />
Excel, allowing AECOM to rapidly check a<br />
set of parametric connections covering a<br />
wide range of variables. This ensured<br />
consistent output of modelled<br />
connections over having to individually<br />
check many manually applied<br />
connections. DBM Vircon achieved ratios<br />
in some models of 100 parametric<br />
components controlling 10,000<br />
connection locations.<br />
THE RESULTS<br />
"As fabrication has been progressing, a<br />
number of benefits have been identified,"<br />
said Rick Sheldon, Project Manager at<br />
AAHK. The collaborative process required<br />
DBM Vircon and AECOM to work to a<br />
coordinated program, resulting in AAHK<br />
having a much clearer understanding of<br />
the status of the structural steel design, in<br />
particular the connection designs, and the<br />
Architectural construction detailing. This<br />
provided far greater clarity and certainty<br />
with the tender quantities.<br />
The transparency afforded by AAHK's<br />
access to the information in Trimble<br />
Connect provided greater certainty with<br />
tender quantities, resulting in reduced risk<br />
during the tender process. The process<br />
basically eliminated the usual requirement<br />
for significant RFI's post award as AECOM<br />
addressed these prior to tender. It is<br />
believed this will also considerably reduce<br />
the potential for any delays claims.<br />
A more complete set of structural<br />
information was provided to the tenderers<br />
- the extent of steelwork (including often<br />
neglected secondary steelwork) and<br />
more specific structural connection<br />
details required of the Tekla model,<br />
resulting in reduced risk for the delivery of<br />
the entire project.<br />
The collaborative processes developed<br />
by DBM Vircon and AECOM for the<br />
design stage extended into the<br />
construction stage, with a slightly<br />
modified version of the design workflow,<br />
used by the contractor, incorporating<br />
changes in the Tekla Model. These were<br />
required by the contractor's erection<br />
phase analysis consultants for end point<br />
analysis related changes and required<br />
pre-cambers, the steel fabricator for his<br />
fabrication preferences and also the<br />
various subcontractors for the MEP<br />
services, roof and façade subcontractors<br />
for their brackets and secondary<br />
steelwork fixings. This is also being<br />
managed through Trimble Connect."<br />
"We're extremely proud of the teamwork<br />
and collaboration displayed by all project<br />
stakeholders, particularly in the wake of<br />
the major disruptions and dislocations<br />
caused by the COVID-19 pandemic," said<br />
Simon Schmitt, Business Manager at<br />
DBM Vircon. AECOM, DBM Vircon and<br />
their mutual use of Tekla Structures and<br />
Trimble Connect played a major role in<br />
enabling this collaboration.<br />
"Trimble Connect allowed for a fully<br />
transparent and traceable 3D platform<br />
where all project stakeholders could<br />
collaborate seamlessly, regardless of their<br />
physical location. It offered a reliable<br />
solution for information transfer and<br />
tagging of ToDo's in the model which was<br />
an integral part of how the engineering<br />
team completed their checks of the live<br />
3D detail model environment where the<br />
approvals took place."<br />
Watch the animation video demonstrating<br />
some of the automated processes here:<br />
https://youtu.be/UVqg2Mkg3o0<br />
www.dbmvircon.com<br />
<strong>Nov</strong>ember/<strong>Dec</strong>ember <strong>2023</strong> 11