Configurator Cuts Cycle<br />

Time, Shortens Long-<br />

Range Planning<br />

As part of an effort to cut<br />

equipment delivery times,<br />

<strong>Dresser</strong>-<strong>Rand</strong> has developed<br />

a technologically complex<br />

system that simplifies the<br />

proposal process, allowing<br />

the company to produce a<br />

proposal in two to five days in<br />

the client’s office.<br />

Called the “Product<br />

Configurator,” <strong>Dresser</strong>-<strong>Rand</strong><br />

product engineers can<br />

compile client needs to devise<br />

an engineered solution with<br />

drawings ready for manufacture.<br />

“We call it ‘building what<br />

we bid,’” said Allan Kidd,<br />

project manager, product<br />

configuration.<br />

“The Configurator is the<br />

starting block in a sprint to<br />

faster client solutions,” he<br />

explained. “It allows us to<br />

discuss with clients their<br />

exact needs and convert<br />

them into manufacturable<br />

information on the spot.”<br />

The Configurator is a software<br />

package written by <strong>Dresser</strong>-<br />

<strong>Rand</strong> engineers. It allows the<br />

regional business team (the<br />

product engineers, application<br />

engineers, etc.) to select and<br />

configure machinery and<br />

services, establish a price,<br />

and guarantee that it will build<br />

what it has bid. And it can<br />

actually be done in the client’s<br />

office within two to five days,<br />

depending on the project<br />

scope.<br />

“We can start building our<br />

equipment as soon as a<br />

contract is signed,” said Gary<br />

Jacobik, quality assurance<br />

manager on the Configurator<br />

development team.<br />

“There are no coordination<br />

meetings required, as the<br />

project application is developed<br />

with the client in the<br />

client's office. Normally it<br />

would take 10 weeks to<br />

complete the first issue of<br />

engineering documents, then<br />

meet with the client for<br />

coordination meetings.<br />

The time for preliminary<br />

engineering is totally eliminated<br />

with the Configurator.<br />

With the Configurator, we’re<br />

able to cut off at least six<br />

weeks, reducing lead time<br />

before manufacture by as<br />

much as 16 to 20 weeks.”<br />

Typical industry cycle time<br />

from quotation to delivery is<br />

12 to 14 months.<br />

With the Configurator and<br />

other timesaving solutions<br />

that <strong>Dresser</strong>-<strong>Rand</strong> has<br />

developed in recent years,<br />

delivery time is reduced to six<br />

months.<br />

Highly Engineered<br />

Products<br />

Because <strong>Dresser</strong>-<strong>Rand</strong>’s<br />

equipment is highly engineered<br />

– individual for not<br />

only each client, but also<br />

each client application –<br />

solutions for clients had been<br />

complex and time<br />

consuming. The Configurator,<br />

however, allows <strong>Dresser</strong>-<strong>Rand</strong><br />

to speed up the process.<br />

Informational fields are<br />

populated across a series of<br />

templates and modules. This<br />

allows the product team to<br />

quickly define the performance<br />

and configuration of<br />

<strong>Dresser</strong>-<strong>Rand</strong>’s entire line of<br />

turbo equipment and package<br />

services. The Configurator<br />

can delineate all of the turbo<br />

machinery features required.<br />

“We automate the creation of<br />

an entire project bill of<br />

materials and services,”<br />

Jacobik explained. “They're<br />

developed for each part of the<br />

compressor. A bill of materials<br />

is developed for each component.”<br />

The end result is that<br />

at the close of the initial<br />

meeting with a client, the<br />

<strong>Dresser</strong>-<strong>Rand</strong> product<br />

procurement team has a set<br />

of drawings, data, and details,<br />

coupled with a pricing<br />

structure that has all of the<br />

information that the client<br />

needs to make a decision. “In<br />

a matter of a few days in the<br />

client’s office, he knows<br />

everything he needs to know<br />

about a <strong>Dresser</strong>-<strong>Rand</strong><br />

solution,” Jacobik said.<br />

Although the Configurator is<br />

unrelated to the EDS<br />

Unigraphics computer aided<br />

drafting system <strong>Dresser</strong>-<strong>Rand</strong><br />

developed, “we’ve designed<br />

them so they shake hands,”<br />

Kidd said. “You can type<br />

information into the<br />

Configurator and it shows up<br />

on CAD.”<br />

Launched in 2000<br />

The Configurator was initially<br />

launched in January 2000,<br />

for pipeline booster (PDI)<br />

centrifugal compressors.<br />

DATUM centrifugal compressors,<br />

packaging, and gas<br />

turbine drive modules will be<br />

added this summer and will<br />

include lube oil systems, dry<br />

gas seal systems, and gas<br />

turbine modules. European<br />

modules will be released<br />

throughout 2000.<br />

The completion date for the<br />

entire Product Configurator<br />

System, including mechanical<br />

drive steam turbines and all<br />

reciprocating products for<br />

process and separable<br />

applications, is June 2001.<br />

Kidd estimates that the<br />

Configurator is 65 percent<br />

complete at this time. “We’re<br />

way ahead of schedule,”<br />

Kidd added. The deadline<br />

next year does not include<br />

expanders, axial compressors,<br />

or power turbines.<br />

With the Configurator, a<br />

regional business procurement<br />

team, which includes engineers<br />

with expertise in all<br />

areas of the equipment,<br />

meets with a client.<br />

“Typically, there will be four<br />

or five people on a specific<br />

project,” Jacobik explained.<br />

The servers for the Windowsbased<br />

Configurator are<br />

located in <strong>Dresser</strong>-<strong>Rand</strong>’s<br />

Olean, New York, facility. A<br />

business procurement team<br />

can access the server by<br />

laptop computer from<br />

anywhere in the world.<br />

“Providing remote access<br />

was the challenging part,”<br />

according to David Prince,<br />

president of Databranch,<br />

<strong>Dresser</strong>-<strong>Rand</strong>’s consultant.<br />

“<strong>Dresser</strong>-<strong>Rand</strong> is one of the<br />

first companies ever to do<br />

this,” Prince said. “This is truly<br />

global in scale and that’s<br />

what’s impressive about it.<br />

<strong>Dresser</strong>-<strong>Rand</strong> is a true leader<br />

in developing this technology<br />

and deploying it worldwide.”<br />

Client Reaction Positive<br />

Initial reactions from the half<br />

dozen clients who have<br />

witnessed the Configurator<br />

during the first four months of<br />

2000 have been very positive.<br />

“I spent some time with one<br />

client recently and I couldn’t<br />

tell who was more excited,<br />

him or us,” Kidd recalled.<br />

There are additional benefits<br />

to clients other than the cycle<br />

time cut from <strong>Dresser</strong>-<strong>Rand</strong>’s<br />

end. “Those clients that<br />

understand the principle of<br />

cycle time reduction are also<br />

interested in reducing their<br />

own cycle time,” Kidd<br />

explained. “We also shorten<br />

the client’s cycle time – from<br />

project concept to completion<br />

– by giving them more<br />

information sooner that's<br />

accurate and reliable upon<br />

receipt. We can sit with them<br />

while they’re going through<br />

their concept stage and, as<br />

a result, shorten their concept<br />

cycle time.”<br />

This has a dramatic impact on<br />

client satisfaction. “The clock<br />

starts ticking when they first<br />

start thinking about a project,<br />

long before they call us to help<br />

them with their energy<br />

solutions,” Kidd said. “This is<br />

significant when you consider<br />

some of the time saved from<br />

initial concept to plant start-up<br />

– say, an LNG plant in<br />

Malaysia, 300 to 400 days off.<br />

The Configurator allows our<br />

product engineer teams to<br />

move with alacrity and<br />

accuracy to fulfill client needs.”<br />

Kidd concedes that the<br />

Configurator and other efforts<br />

by <strong>Dresser</strong>-<strong>Rand</strong> to reduce<br />

cycle time give a whole new<br />

meaning to long-range<br />

planning. In fact, the long<br />

range just got shorter. ■<br />