General Overview & Constra<strong>in</strong>ts<br />
� Brownfield <strong>Project</strong>s to be liquidated over 6 years:<br />
- Cost = A$1.6 Billion<br />
- Human Resource = 1.2 million offshore Man-hours<br />
= 1.0 million onshore Man-hours<br />
� Limited beds offshore<br />
� Limited eng<strong>in</strong>eer<strong>in</strong>g and design resources <strong>in</strong> Perth<br />
� Loss of experienced Operations personnel<br />
� High level of concurrent activities on board NRA<br />
� Unplanned events occur daily on this age<strong>in</strong>g facility<br />
� Reliability of Supply is paramount as gas from these projects already committed<br />
� Delivery of projects over a different timeframe is not an option!<br />
© <strong>Transfield</strong> <strong>Worley</strong> Services 2008<br />
Brownfield <strong>Project</strong>s