Major Achievements<br />

� Shortest construction of any NPP in China from 1st concrete to In-Service<br />

(54 months)<br />

� Shortest duration to construct perimeter wall (14 days)<br />

� Best integrated leak rate of all <strong>CANDU</strong> 6 nuclear power plants<br />

� 70 heavy lifts of equipment with the VHL crane<br />

� Steam S e ge generator e o installed s ed in 8 hours ou s<br />

� Fuel channels installed in 64 days<br />

PROTECTED - SENSITIVE / PROTÉGÉ - DÉLICAT 12