Major Achievements<br />
� Shortest construction of any NPP in China from 1st concrete to In-Service<br />
(54 months)<br />
� Shortest duration to construct perimeter wall (14 days)<br />
� Best integrated leak rate of all <strong>CANDU</strong> 6 nuclear power plants<br />
� 70 heavy lifts of equipment with the VHL crane<br />
� Steam S e ge generator e o installed s ed in 8 hours ou s<br />
� Fuel channels installed in 64 days<br />