Annual Repor t and Financial Statements 2009 11<br />

OpERaTIONS REVIEw 2009 (CONTINuED)<br />

Dunboyne Line<br />

Track laying, station and car park works are continuing on<br />

the new Dunboyne line. The project is still on target to<br />

enable commuter services from the M3 Parkway station<br />

to commence in September 2010, with intermediate<br />

stations at Hansfield and Dunboyne.<br />

Cork Commuter service<br />

Glounthaune/Midleton was opened for service in July<br />

2009 with 9 miles of track laid, 2 stations completed, 9<br />

level crossings closed and 3 level crossings automated.<br />

The new Glanmire road bridge to facilitate the closure of<br />

the Woodhill level crossing was opened to traffic in<br />

October, 2009.<br />

Other works<br />

n Accessibility works were completed at 12 stations.<br />

n 1,360 car parking spaces (in 10 locations) were added<br />

in 2009 to the car parking pool.<br />

n Ticket Validation machines were installed at 4 stations<br />

(including Heuston and Bray) during the year.<br />

n Rosslare Berth 2 linkspan replacement was completed<br />

and is fully operational.<br />

City Centre Re-Signalling – Implementation Phase<br />

Installation is substantially complete on the Howth branch.<br />

Installation of cable route and construction of supporting<br />

structures for signals & location cases is ongoing on the<br />

mainline between Howth Junction and Clongriffin Station.<br />

Construction of SET buildings is complete at 8 DART<br />

stations.<br />

Level Crossing Automation<br />

An automation programme to remotely monitor road<br />

crossings progressed during 2009. 59 crossings are being<br />

monitored to date at the Mallow and Athlone centres and<br />

this number is expected to rise to 75 at end 2010.<br />

Rolling stock<br />

Acceptance into service of all the remaining InterCity<br />

railcars was completed with the introduction into service<br />

in November of set 45 (the last high density 6-car). There<br />

are twenty nine 3-car and fifteen 6-car sets now in service<br />

with replacements for sets 10 and 11, damaged at sea<br />

during delivery, due in 2011. Production for the 51 vehicle<br />

order commences in April 2010 with deliveries planned for<br />

2011.<br />

The reliability of the rolling stock fleets have been<br />

improved significantly over the last two years with the<br />

number of incidents causing delay more than halved. The<br />

improved rolling stock reliability has directly supported the<br />

improved reliability of services.<br />

The resolution of several system and component issues<br />

related to the DART Class 8100 refurbishment project has<br />

been completed. In particular, the Class 8100 floors were<br />

poorly installed during the original refurbishment project<br />

and are being refitted under warranty.<br />

The manufacturers (CAF of Spain) of the MkIV carriages<br />

operating on Dublin Cork route and the Class 29000 DMU<br />

operating commuter services into Dublin are being<br />

pursued under the contracts to rectify known technical<br />

deficiencies with their products. Remedy of these issues<br />

will improve reliability and passenger comfort.<br />

Significant improvements in productivity and operational<br />

control of the Mechanical Engineering Workshops and<br />

Depots have been achieved over the last three years.